BEXAR VARIOUS (0915-00-276)

Items: 94

County: BEXAR
Length: 0.0000 MILES
Highway: VARIOUS
District: SAN ANTONIO
Control Number: 0915-00-276
DBE Goal: 0.0%
Project: C 915-00-276
Guaranty: $100,000.00
Time: 572 WORKING DAYS
Engineer's Estimate: $9,122,455.44
Date: 04/03/2025 (1 year ago)
Contract Number: 4253008
Type: BRIDGE MAINTENANCE
Project ID: A00196404
Project Description: ADDRESS VARIOUS BRIDGE REPAIR INCLUDING SCOUR AND SLOPE FAILURE-2025
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
CARLOS ARCILA
CHRISTEN LOGORIA
CITLALI TAPIA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$9,122,455.44
1
$7,263,765.26
Over/Under Est: -20.37% -$1,858,690.18
$7,514,627.05
Over/Under Est: -17.62% -$1,607,828.39
Amt Left: 3.45% $250,861.79
Over/Under Est: 0.29% $26,470.06
Amt Left: 25.95% $1,885,160.24
Delta: -21.75% -$1,634,298.45
$11,895,137.75
Over/Under Est: 30.39% $2,772,682.31
Amt Left: 63.76% $4,631,372.49
Delta: -30.02% -$2,746,212.25
Subcontractor Percentage Amount
DIIBS SPECIALISTS, LLC 20.19% $1,492,295.13
Total: 20.19% $1,492,295.13

Bid Items & Bid Tabulations

94 Total 0 of 94
BEXAR  |  VARIOUS  |  SAN ANTONIO  |  0915-00-276  |  04/03/2025  |  $9,122,455.44  |  C 915-00-276  |  BRIDGE MAINT  |  572 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RELMCO, INC.
ICOS MANAGEMENT, LLC
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
DAN WILLIAMS COMPANY
PREPARING ROW
STA 5.000 $2,500.000 $15,000.000 $1,080.000 $7,500.000 $5,000.000
REMOV CONC (MOWSTRIP)
LF 8,535.000 $20.000 $15.000 $5.400 $7.500 $5.000
REMOV CONC (RIPRAP)
SY 183.000 $64.570 $30.000 $108.000 $20.000 $50.000
REMOV CONC (RIPRAP)
CY 9.000 $100.000 $200.000 $242.000 $75.000 $500.000
REMOV CONC (CURB)
LF 60.000 $12.000 $50.000 $44.000 $10.000 $15.000
REMOV CONC (SAWCUT)
LF 184.000 $60.000 $15.000 $16.200 $10.000 $7.000
REMOV CONC (ABUTMENT BACKWALL)
CY 3.000 $1,650.000 $2,000.000 $1,080.000 $100.000 $2,000.000
REMOV CONC (RAIL)
LF 299.000 $50.000 $50.000 $86.400 $25.000 $50.000
RMV (9") TRT/UNTRT BASE & ASPH PAV
SY 107.000 $40.000 $20.000 $44.000 $20.000 $30.000
EXCAV (ROADWAY)
CY 1,947.000 $30.000 $35.000 $65.000 $20.000 $75.000
EXCAV (CHANNEL)
CY 1,540.000 $70.000 $35.000 $86.000 $20.000 $75.000
EMBANK (FNL)(DC)(TY C)
CY 2,071.000 $60.000 $75.000 $75.000 $20.000 $145.000
FURN & PLACE TOPSOIL (6")
SY 8,029.000 $2.000 $8.000 $11.000 $10.000 $5.000
BROADCAST SEED (PERM_URBAN_CLAY)
SY 8,029.000 $0.300 $0.600 $0.100 $2.000 $1.250
SOIL RET BLKT(SL_MOD_CLAY_SHORT)
SY 8,029.000 $8.000 $3.000 $1.000 $15.000 $1.750
D-GR HMA TY-B PG64-22
TON 9.000 $175.000 $350.000 $432.000 $250.000 $3,000.000
D-GR HMA TY-C SAC-B PG70-22
TON 36.000 $175.000 $350.000 $324.000 $250.000 $775.000
TEMPORARY SPL SHORING
SF 3,963.000 $40.000 $30.000 $1.000 $100.000 $100.000
CL C CONC (ABUT)(EXTEND)
CY 5.000 $1,651.750 $3,075.000 $2,160.000 $1,000.000 $6,000.000
CL C CONC (CAP)(EXTEND)
CY 52.000 $3,000.000 $1,950.000 $1,080.000 $2,500.000 $15,000.000
CONC STR REPAIR (EPOXY MORTAR)
SF 9.000 $1,500.000 $350.000 $432.000 $325.000 $900.000
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 335.000 $155.590 $275.000 $275.000 $330.000 $400.000
CONC STR REPAIR(DECK REP (FULL DEPTH))
SF 49.000 $677.500 $350.000 $540.000 $350.000 $1,000.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 233.000 $290.710 $275.000 $232.000 $275.000 $450.000
CONC STR REPAIR (STANDARD)
SF 19.000 $2,000.000 $350.000 $262.000 $275.000 $850.000
RIPRAP (CONC)(5 IN)
CY 22.000 $700.000 $525.000 $756.000 $850.000 $1,000.000
RIPRAP (CONC)(CL B)
CY 99.000 $1,000.000 $525.000 $648.000 $850.000 $900.000
RIPRAP (CONC) (CL B) (4 IN)
CY 3.000 $1,265.960 $900.000 $648.000 $850.000 $1,800.000
RIPRAP (CONC) (CL B) (6 IN)
CY 6.000 $1,250.000 $800.000 $972.000 $1,000.000 $1,500.000
RIPRAP (MOW STRIP)(4 IN)
CY 643.000 $700.000 $515.000 $648.000 $750.000 $750.000
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 315.000 $250.000 $195.000 $216.000 $325.000 $350.000
RIPRAP (STONE COMMON)(DRY)(24 IN)
CY 374.000 $300.000 $195.000 $216.000 $350.000 $350.000
RIPRAP (STONE COMMON)(GROUT)(12 IN)
CY 171.000 $350.000 $195.000 $400.000 $250.000 $500.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 48.000 $236.630 $195.000 $270.000 $300.000 $350.000
ELASTOMERIC BEARING (EE1)
EA 13.000 $6,135.000 $4,500.000 $8,640.000 $2,500.000 $12,000.000
STR STEEL (MISC NON-BRIDGE)
LB 1,120.000 $27.070 $35.000 $44.000 $25.000 $25.000
STR STEEL (PEDESTAL)
LB 15.000 $36.000 $300.000 $108.000 $250.000 $400.000
RAIL (TY T2P)
LF 4,647.000 $225.000 $300.000 $324.000 $200.000 $375.000
RAIL (TY T221)
LF 14.000 $169.000 $600.000 $864.000 $200.000 $450.000
RAIL (TY T223)
LF 55.000 $231.160 $600.000 $756.000 $200.000 $225.000
RAIL (TY SSTR)
LF 136.000 $250.000 $600.000 $540.000 $200.000 $175.000
RAIL (TY C223)
LF 128.000 $231.160 $600.000 $540.000 $200.000 $400.000
GABIONS (3' X 3')(GALV)
CY 364.000 $300.000 $250.000 $162.000 $350.000 $350.000
RAISING EXIST STRUCT
EA 3.000 $17,500.000 $75,000.000 $21,600.000 $30,000.000 $135,000.000
REMOV STR (HEADWALL)
EA 2.000 $3,357.300 $4,500.000 $2,160.000 $1,000.000 $5,000.000
REMOVE STR (RAIL)
LF 4,464.000 $111.670 $25.000 $13.000 $10.000 $12.000
REMOVE STR (GABION)
LF 253.000 $80.000 $50.000 $22.000 $50.000 $25.000
ADJUST STL SHOES
EA 1.000 $12,766.670 $8,500.000 $8,640.000 $500.000 $2,500.000
MOBILIZATION
LS 1.000 $811,490.000 $700,000.000 $605,000.000 $885,000.000 $1,800,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 22.000 $5,000.000 $8,500.000 $1.000 $12,000.000 $53,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 131.000 $60.000 $55.000 $10.000 $55.000 $75.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 146.000 $100.000 $80.000 $10.000 $70.000 $100.000
ROCK FILTER DAMS (REMOVE)
LF 277.000 $20.000 $15.000 $5.000 $20.000 $30.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 587.000 $40.000 $30.000 $1.000 $40.000 $30.000
CONSTRUCTION EXITS (REMOVE)
SY 587.000 $15.000 $15.000 $1.000 $10.000 $25.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,069.000 $5.000 $10.000 $2.000 $10.000 $4.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,069.000 $2.000 $4.000 $1.000 $2.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 115.000 $8.000 $12.000 $10.000 $20.000 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 115.000 $4.000 $5.000 $5.000 $5.000 $1.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 6,470.000 $72.000 $40.000 $97.000 $100.000 $75.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 1,990.000 $70.000 $30.000 $97.000 $100.000 $30.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 240.000 $75.000 $30.000 $108.000 $100.000 $30.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 29,620.000 $16.000 $15.000 $16.000 $40.000 $16.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 2,053.000 $15.000 $15.000 $22.000 $20.000 $15.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 420.000 $20.000 $15.000 $22.000 $20.000 $19.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 29,570.000 $19.750 $18.000 $13.000 $35.000 $15.500
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 2,053.000 $20.000 $15.000 $22.000 $30.000 $14.250
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 420.000 $20.000 $15.000 $22.000 $30.000 $18.500
CONC CURB (TY II)
LF 13.000 $50.000 $200.000 $108.000 $50.000 $200.000
MTL W-BEAM GD FEN (TIM POST)
LF 8,445.000 $30.000 $27.950 $30.000 $30.000 $35.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 65.000 $2,300.000 $2,096.250 $2,376.000 $2,500.000 $2,600.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 18.000 $1,600.000 $1,451.250 $2,700.000 $2,500.000 $1,700.000
TL-3 31" SHORT RADIUS (COMPLETE)
EA 1.000 $30,000.000 $31,175.000 $2,160.000 $40,000.000 $32,000.000
REMOVE METAL BEAM GUARD FENCE
LF 10,327.000 $5.000 $2.680 $2.250 $6.000 $5.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 12.000 $385.000 $268.750 $540.000 $500.000 $325.000
GUARDRAIL END TREATMENT (INSTALL)
EA 43.000 $3,400.000 $3,332.500 $4,320.000 $3,700.000 $4,200.000
GUARDRAIL END TREATMENT (REMOVE)
EA 32.000 $370.000 $268.750 $540.000 $500.000 $300.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 50.000 $1,700.000 $800.000 $2,160.000 $2,000.000 $900.000
CRASH CUSH ATTEN (REMOVE)
EA 50.000 $1,000.000 $800.000 $1,080.000 $750.000 $800.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 10.000 $10,000.000 $8,500.000 $10,800.000 $12,000.000 $10,000.000
RELOCATE ELECTRICAL SERVICES
EA 2.000 $1,500.000 $5,500.000 $6,480.000 $12,000.000 $2,000.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 125.000 $40.000 $27.500 $54.000 $50.000 $35.000
DRIFTWOOD REMOVAL
CY 445.000 $262.930 $100.000 $66.000 $100.000 $75.000
CONCRETE RAIL REPLACEMENT (IN-KIND)
LF 41.000 $951.290 $400.000 $1,080.000 $250.000 $600.000
REP STL BRIDGE MBR (STRAIGHTEN MEMB)
EA 3.000 $34,575.000 $45,000.000 $10,800.000 $15,000.000 $25,000.000
REP STL BRIDGE MBR (ANCHOR BOLT NUTS)
EA 2.000 $34,575.000 $1,200.000 $5,400.000 $300.000 $1,500.000
BRIDGE JOINT REPAIR (ARMOR)
LF 33.000 $582.270 $400.000 $486.000 $500.000 $1,200.000
CARBON FIBER REINF POLYMER STRENGTHNING
SF 63.000 $13,000.000 $165.000 $270.000 $150.000 $450.000
CONCRETE BEAM REPAIR (CFRP)
EA 12.000 $25,000.000 $9,500.000 $10,800.000 $10,000.000 $15,000.000
CONCRETE BEAM REP(STRAND SPLICE & CFRP)
EA 2.000 $25,000.000 $4,500.000 $43,200.000 $10,000.000 $25,000.000
LANE CLOSURE(SETUP & REM)(TYP 1)
EA 2.000 $3,000.000 $3,500.000 $8,640.000 $2,000.000 $1,000.000
LANE CLOSURE(SETUP & REM)(TYP 14)
EA 2.000 $3,000.000 $3,500.000 $8,640.000 $2,000.000 $1,000.000
UNDERSEAL COURSE
GAL 24.000 $10.000 $75.000 $220.000 $40.000 $25.000
BONDING COURSE
GAL 20.000 $10.000 $75.000 $220.000 $40.000 $25.000
Totals: $9,122,455.440 $7,263,765.260 $7,514,627.050 $9,148,925.500 $11,895,137.750
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
ENVIRONMENTAL: CONTRACTOR FORCE ACCOUNT WORK (NONPART) $200,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $250,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $365,002.00
Total: $815,002.00