BEXAR VA (0915-00-270)

Items: 114

County: BEXAR
Length: N/A
Highway: VA
District: SAN ANTONIO
Control Number: 0915-00-270
DBE Goal: 400.0%
Project: F 2B24(173)
Guaranty: N/A
Time: 269 WORKING DAYS
Engineer's Estimate: $10,320,441.08
Date: 06/06/2024 (2 years ago)
Contract Number: N/A
Type: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
CHRISTEN LONGORIA
CITLALI TAPIA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$10,320,441.08
1
$9,168,264.03
Over/Under Est: -11.16% -$1,152,177.05
$11,534,338.62
Over/Under Est: 11.76% $1,213,897.54
Amt Left: 25.81% $2,366,074.59
$11,657,309.95
Over/Under Est: 12.95% $1,336,868.87
Amt Left: 27.15% $2,489,045.92
Delta: -1.07% -$122,971.33
Over/Under Est: 33.12% $3,417,625.92
Amt Left: 49.84% $4,569,802.97
Delta: -17.85% -$2,080,757.05
$14,885,325.10
Over/Under Est: 44.23% $4,564,884.02
Amt Left: 62.36% $5,717,061.07
Delta: -8.35% -$1,147,258.10
Subcontractor Percentage Amount
LONE STAR PAVING COMPANY 4.70% $430,908.41
DIIBS SPECIALISTS, LLC 1.37% $125,605.22
TRP CONSTRUCTION GROUP, LLC 0.78% $71,512.46
TORO BRAVO CONSTRUCTION, LLC 0.12% $11,001.92
Total: 6.97% $639,028.01

Bid Items & Bid Tabulations

114 Total 0 of 114
BEXAR  |  VA  |  SAN ANTONIO  |  0915-00-270  |  06/06/2024  |  $10,320,441.08  |  F 2B24(173)  |  BRIDGE MAINT  |  269 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RELMCO, INC.
DEAN WORD COMPANY, LTD.
J3 COMPANY, LLC
CAPITAL EXCAVATION COMPANY
DAN WILLIAMS COMPANY
REMOVING CONC (PAV)
SY 485.000 $30.000 $15.000 $91.400 $20.000 $55.900 $30.000
REMOVING CONC (RIPRAP)
SY 1,180.000 $20.000 $15.000 $10.320 $20.000 $21.150 $16.000
EXCAVATION (ROADWAY)
CY 45,580.000 $22.000 $10.000 $22.850 $17.000 $21.400 $33.500
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 47,300.000 $20.000 $17.000 $48.560 $41.000 $51.000 $56.000
EMBANKMENT (FINAL)(ORD COMP)(TY C2)(DS)
CY 1,137.000 $43.130 $38.000 $44.510 $90.000 $72.600 $80.000
FURNISHING AND PLACING TOPSOIL (3")
SY 19,248.000 $1.500 $3.000 $5.870 $2.000 $3.000 $2.150
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 19,248.000 $0.250 $0.258 $0.280 $0.500 $0.250 $0.250
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 19,230.000 $1.160 $1.613 $1.760 $1.500 $1.650 $1.100
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 5,674.000 $128.000 $75.000 $77.410 $65.000 $100.000 $83.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 279.000 $158.000 $180.600 $209.870 $300.000 $186.000 $205.000
CONC PVMT (CONT REINF - CRCP) (10")
SY 485.000 $85.000 $185.000 $165.000 $175.000 $152.000 $155.000
TEMPORARY SPL SHORING
SF 54,180.000 $30.000 $23.000 $25.000 $40.000 $32.000 $38.000
DRILL SHAFT (30 IN)
LF 5,400.000 $220.000 $295.000 $301.300 $190.000 $210.000 $375.000
DRILL SHAFT (36 IN)
LF 112.000 $277.500 $385.000 $395.710 $240.000 $400.000 $375.000
CL F CONC (FOOTING)
CY 692.000 $500.000 $711.200 $736.050 $780.000 $1,050.000 $750.000
RETAINING WALL (CAST - IN - PLACE)
SF 7,147.000 $120.000 $48.000 $79.920 $88.000 $118.000 $100.000
RIPRAP (CONC)(5 IN)
CY 802.000 $240.000 $495.000 $488.690 $450.000 $735.000 $600.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 117.000 $120.000 $155.000 $122.230 $150.000 $228.000 $225.000
RIPRAP (STONE COMMON)(DRY)(24 IN)
CY 1,500.000 $240.000 $175.000 $122.900 $150.000 $222.000 $225.000
RIPRAP (SPECIAL)
CY 500.000 $250.000 $475.000 $300.000 $150.000 $220.000 $275.000
RIPRAP (MOW STRIP)(4 IN)
CY 55.000 $598.000 $485.000 $689.870 $750.000 $790.000 $560.000
RC PIPE (CL III)(24 IN)
LF 93.000 $145.650 $100.000 $141.270 $125.000 $191.000 $150.000
JCTBOX(COMPL)(PJB)(3FTX3FT)
EA 1.000 $3,850.000 $8,950.000 $4,755.070 $10,000.000 $7,100.000 $6,500.000
REMOV STR (PIPE)
LF 91.000 $14.400 $20.000 $25.160 $40.000 $370.000 $40.000
REMOVE STR (SOUNDWALL)
LF 12.000 $30.000 $1,000.000 $414.970 $550.000 $1,090.000 $500.000
MOBILIZATION
LS 1.000 $921,977.230 $815,000.000 $855,000.000 $975,000.000 $1,200,000.000 $1,400,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 17.000 $10,800.000 $5,000.000 $881.500 $15,000.000 $12,000.000 $20,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 228.000 $27.000 $42.350 $45.250 $40.000 $42.400 $29.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 427.000 $33.650 $26.763 $28.610 $26.000 $26.800 $27.000
CONSTRUCTION EXITS (REMOVE)
SY 427.000 $7.000 $5.170 $5.520 $5.000 $5.150 $11.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 5,303.000 $5.650 $3.850 $4.110 $3.500 $3.850 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 5,303.000 $0.750 $0.275 $0.300 $0.250 $0.300 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 457.000 $2.750 $0.611 $6.510 $6.000 $6.100 $9.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 457.000 $2.000 $1.100 $1.180 $1.000 $1.100 $4.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 4,415.000 $71.910 $25.000 $16.640 $30.000 $101.000 $38.500
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 390.000 $14.440 $10.000 $1.850 $20.000 $51.900 $7.000
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 4,570.000 $17.400 $15.000 $11.990 $20.000 $29.250 $12.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 4,415.000 $19.750 $15.000 $13.920 $20.000 $30.200 $12.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 1,000.000 $9.000 $15.000 $13.510 $20.000 $23.550 $12.000
PORT CTB (FURN & INST)(TL-3 LPCB)
LF 1,000.000 $105.000 $75.000 $16.210 $40.000 $113.000 $85.000
MTL W-BEAM GD FEN (TIM POST)
LF 4,000.000 $30.350 $23.381 $25.570 $25.000 $23.800 $22.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 6.000 $1,875.000 $2,392.950 $2,933.660 $2,400.000 $2,440.000 $2,300.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,600.000 $1,574.875 $1,721.880 $1,600.000 $1,600.000 $1,500.000
REMOVE METAL BEAM GUARD FENCE
LF 3,934.000 $3.510 $3.225 $3.520 $3.000 $3.300 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $280.000 $268.750 $293.840 $250.000 $270.000 $250.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 6.000 $385.000 $268.750 $293.840 $400.000 $270.000 $250.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,250.000 $3,476.550 $3,801.060 $4,000.000 $3,540.000 $3,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $370.000 $268.750 $293.840 $500.000 $270.000 $250.000
CRASH CUSH ATTEN (REMOVE)
EA 12.000 $1,512.260 $913.750 $610.500 $1,000.000 $930.000 $800.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 6.000 $9,892.210 $8,500.000 $9,079.330 $9,000.000 $9,100.000 $8,500.000
CONDT (PVC) (SCH 40) (2")
LF 2,400.000 $19.590 $17.200 $42.320 $40.000 $39.650 $36.000
CONDT (PVC) (SCH 40) (2") (BORE)
LF 100.000 $38.600 $43.000 $96.390 $100.000 $90.300 $82.000
CONDT (PVC) (SCH 40) (2") (STL ENCSE)
LF 100.000 $32.000 $80.625 $69.350 $65.000 $65.000 $59.000
CONDT (PVC) (SCH 40) (3") (BORE)
LF 2,400.000 $38.500 $53.750 $84.630 $80.000 $79.300 $72.000
CONDT (PVC) (SCH 40) (3") (CONC ENCSE)
LF 100.000 $30.490 $38.700 $78.740 $80.000 $73.800 $67.000
ELEC CONDR (NO.6) BARE
LF 2,600.000 $2.730 $1.505 $4.230 $5.000 $3.950 $3.600
ELEC CONDR (NO.6) INSULATED
LF 2,600.000 $2.770 $2.096 $4.580 $5.000 $4.300 $3.900
GROUND BOX TY D (162922)W/APRON
EA 4.000 $1,644.490 $1,467.375 $3,349.730 $3,200.000 $3,140.000 $2,850.000
ELC SRV TY D 120/240 100(NS)GS(N)GC(O)
EA 2.000 $10,700.000 $6,987.500 $6,817.000 $6,500.000 $6,400.000 $7,000.000
REPLACE EXISTING ALUMINUM SIGNS(TY A)
SF 40.000 $40.000 $27.950 $72.280 $28.500 $27.500 $29.000
REPLACE EXISTING ALUMINUM SIGNS(TY G)
SF 396.000 $35.000 $30.100 $72.280 $61.500 $41.850 $62.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 1.000 $750.000 $1,284.625 $1,175.350 $685.000 $1,320.000 $700.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $850.000 $1,397.500 $999.050 $795.000 $1,430.000 $800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $1,000.000 $1,854.375 $940.270 $1,025.000 $1,900.000 $1,100.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 7.000 $600.000 $1,209.375 $940.270 $545.000 $1,240.000 $550.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 50.000 $24.000 $53.750 $38.560 $17.500 $35.900 $33.000
WK ZN PAV MRK REMOV (W)6"(BRK)
LF 1,490.000 $0.850 $1.344 $2.350 $2.000 $0.850 $1.250
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 7,965.000 $0.880 $1.344 $2.350 $2.000 $0.850 $1.250
WK ZN PAV MRK REMOV (W)(ENTR GORE)
EA 1.000 $200.000 $591.250 $528.910 $450.000 $1,060.000 $550.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 2,280.000 $0.860 $1.344 $2.350 $2.000 $0.850 $1.250
REFL PAV MRK TY II (W) 6" (BRK)
LF 1,205.000 $0.170 $0.538 $0.700 $0.600 $0.550 $0.500
REFL PAV MRK TY II (W) 6" (SLD)
LF 8,480.000 $0.150 $0.538 $0.580 $0.500 $0.550 $0.500
REFL PAV MRK TY II (W) 12" (SLD)
LF 48.000 $1.500 $2.688 $1.400 $1.200 $1.650 $2.500
REFL PAV MRK TY II (W) 24" (SLD)
LF 110.000 $2.900 $9.675 $7.640 $6.500 $3.350 $9.000
REFL PAV MRK TY II (W) (ARROW)
EA 5.000 $250.000 $188.125 $91.660 $78.000 $139.000 $175.000
REFL PAV MRK TY II (W) (UTURN ARROW)
EA 2.000 $146.500 $188.125 $111.660 $95.000 $184.000 $178.000
REFL PAV MRK TY II (W) (LNDP ARW)
EA 2.000 $70.880 $209.625 $217.440 $185.000 $175.000 $195.000
REFL PAV MRK TY II (W) (WORD)
EA 7.000 $280.000 $188.125 $99.910 $85.000 $150.000 $175.000
REFL PAV MRK TY II (W) (ENTR GORE)
EA 1.000 $280.000 $591.250 $587.680 $500.000 $1,950.000 $550.000
REFL PAV MRK TY II (W) (EXIT GORE)
EA 1.000 $0.180 $591.250 $587.680 $500.000 $1,720.000 $550.000
REFL PAV MRK TY II (Y) 6" (SLD)
LF 1,380.000 $0.180 $0.538 $0.700 $0.600 $0.550 $0.500
PAVEMENT SEALER 6"
LF 15,965.000 $0.250 $0.538 $0.410 $0.350 $0.550 $0.500
PAVEMENT SEALER 12"
LF 48.000 $0.750 $1.075 $1.180 $1.000 $1.200 $1.000
PAVEMENT SEALER 24"
LF 110.000 $3.000 $2.150 $7.050 $6.000 $1.250 $2.000
PAVEMENT SEALER (ARROW)
EA 5.000 $52.000 $53.750 $88.150 $75.000 $35.600 $50.000
PAVEMENT SEALER (WORD)
EA 7.000 $57.000 $53.750 $129.290 $110.000 $38.950 $50.000
PAVEMENT SEALER (UTURN ARROW)
EA 2.000 $109.570 $53.750 $152.800 $130.000 $122.000 $50.000
PAVEMENT SEALER (LNDP ARROW)
EA 7.000 $195.000 $59.125 $264.460 $225.000 $122.000 $55.000
PAVEMENT SEALER (ENTR GORE)
EA 1.000 $345.000 $591.250 $587.680 $500.000 $1,330.000 $550.000
PAVEMENT SEALER (EXIT GORE)
EA 1.000 $325.000 $591.250 $587.680 $500.000 $870.000 $550.000
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 1,355.000 $0.540 $1.075 $1.400 $1.200 $1.150 $1.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 7,830.000 $0.520 $1.075 $1.180 $1.000 $1.100 $1.000
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 1,830.000 $0.520 $1.075 $1.180 $1.000 $1.100 $1.000
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 10,200.000 $1.000 $1.881 $1.820 $1.550 $1.850 $1.750
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
LF 1,380.000 $1.070 $1.881 $1.820 $1.550 $1.850 $1.750
REFL PAV MRKR TY II-C-R
EA 186.000 $3.500 $6.450 $10.580 $9.000 $5.550 $6.000
ELIM EXT PAV MRK & MRKS (6")
LF 1,450.000 $0.200 $1.075 $1.290 $1.100 $0.500 $1.000
PAV SURF PREP FOR MRK (6")
LF 15,085.000 $0.200 $0.054 $0.300 $0.250 $0.350 $0.050
PAV SURF PREP FOR MRK (12")
LF 48.000 $1.250 $0.323 $2.000 $1.700 $0.400 $0.300
PAV SURF PREP FOR MRK (24")
LF 110.000 $0.980 $0.538 $2.520 $2.150 $0.450 $0.500
PAV SURF PREP FOR MRK (ARROW)
EA 7.000 $27.000 $12.900 $47.010 $40.000 $16.700 $12.000
PAV SURF PREP FOR MRK (UTURN ARR)
EA 2.000 $41.000 $18.275 $52.890 $45.000 $44.500 $17.000
PAV SURF PREP FOR MRK (WORD)
EA 7.000 $25.000 $16.125 $52.890 $45.000 $21.150 $15.000
PAV SURF PREP FOR MRK (EXIT GORE)
EA 1.000 $412.000 $188.125 $205.680 $175.000 $184.000 $175.000
TREE REMOVAL (60" - 72" DIA)
EA 5.000 $5,000.000 $4,500.000 $1,671.280 $5,000.000 $1,290.000 $5,000.000
D-GR HMA TY-B PG64-22 (EXEMPT)
TON 1,448.000 $96.800 $179.550 $117.810 $175.000 $185.000 $180.000
TACK COAT
GAL 376.000 $5.000 $6.300 $11.790 $8.000 $6.500 $6.000
SP MIXES SP-C SAC-B PG70-22 (EXEMPT)
TON 370.000 $200.000 $289.800 $155.520 $280.000 $300.000 $285.000
UNDERSEAL COURSE
GAL 749.000 $5.000 $43.050 $10.390 $40.000 $43.350 $41.000
SOUND WALL
SF 1,247.000 $41.590 $165.000 $201.580 $180.000 $203.000 $200.000
GEOGRID BASE REINFORCEMENT (TY II)
SY 1,360.000 $1.970 $3.000 $2.000 $5.000 $9.400 $2.150
ITS MULTI-DUCT CND (PVC-40)(CONC ENCSE)
LF 100.000 $60.290 $53.750 $52.890 $50.000 $49.550 $45.000
ITS MULTI-DUCT CND (PVC-40)(STL ENCSE)
LF 100.000 $65.000 $134.375 $129.290 $125.000 $121.000 $110.000
SAWCUT AND REMOVAL OF EXIST ASPH PAV
SY 3,085.000 $14.000 $10.000 $18.210 $15.000 $24.200 $9.000
Totals: $10,320,441.080 $9,168,264.100 $11,534,338.620 $11,657,309.950 $13,738,067.000 $14,885,325.100