BEXAR VA (0915-00-182)

Items: 49

County: BEXAR
Length: N/A
Highway: VA
District: SAN ANTONIO
Control Number: 0915-00-182
DBE Goal: N/A
Project: STP 2018(733)
Guaranty: N/A
Time: 360 WORKING DAYS
Engineer's Estimate: $1,959,290.68
Date: 04/04/2018 (8 years ago)
Contract Number: N/A
Type: DISTRICTWIDE GUIDESIGNS FY18
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$1,959,290.68
$1,921,528.61
Over/Under Est: -1.93% -$37,762.07
$2,028,509.92
Over/Under Est: 3.53% $69,219.24
Amt Left: 5.57% $106,981.31
Over/Under Est: 9.4% $184,203.32
Amt Left: 11.55% $221,965.39
Delta: -5.67% -$114,984.08
Over/Under Est: 21.92% $429,426.72
Amt Left: 24.31% $467,188.79
Delta: -11.44% -$245,223.40
Over/Under Est: 26.8% $524,996.82
Amt Left: 29.29% $562,758.89
Delta: -4.00% -$95,570.10

Bid Items & Bid Tabulations

49 Total 0 of 49
BEXAR  |  VA  |  SAN ANTONIO  |  0915-00-182  |  04/04/2018  |  $1,959,290.68  |  STP 2018(733)  |  DISTRICTWIDE GUIDESIGNS FY18  |  360 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THE LEVY COMPANY, INC.
MICA CORPORATION
F & W ELECTRICAL CONTRACTORS, INC.
CHAMPION INFRASTRUCTURE, LLC
E-Z BEL CONSTRUCTION, LLC
REMOVING CONC (CTB)
LF 94.000 $7.780 $55.000 $32.250 $135.000 $40.000 $33.000
DRILL SHAFT (30 IN)
LF 58.000 $119.160 $195.580 $286.150 $260.000 $300.000 $275.000
DRILL SHAFT (36 IN)
LF 76.000 $156.530 $227.930 $290.000 $300.000 $400.000 $325.000
DRILL SHAFT (48 IN)
LF 26.000 $270.960 $349.750 $362.000 $380.000 $500.000 $500.000
RIPRAP (MOW STRIP)(4 IN)
CY 45.800 $426.190 $550.000 $592.000 $585.000 $600.000 $585.000
MOBILIZATION
LS 1.000 $178,144.610 $192,152.860 $173,800.000 $103,993.000 $240,000.000 $258,300.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 18.000 $3,500.000 $3,500.000 $9,025.000 $12,366.000 $7,500.000 $14,440.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 100.000 $15.000 $5.000 $5.500 $5.000 $4.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 100.000 $7.500 $2.500 $2.700 $4.000 $2.000 $2.500
PERM CTB (SGL SLOPE) (TY 1) (42 )
LF 27.000 $55.000 $213.960 $135.000 $340.000 $80.000 $125.000
PERM CTB (SGL SLOPE) (TY 3) (42 )
LF 67.000 $144.490 $157.000 $210.000 $340.000 $200.000 $150.000
MTL W-BEAM GD FEN (TIM POST)
LF 788.000 $19.550 $19.900 $21.400 $45.000 $21.000 $22.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 4.000 $1,036.680 $1,090.000 $1,172.000 $2,250.000 $1,200.000 $1,250.000
REMOVE METAL BEAM GUARD FENCE
LF 438.000 $2.520 $2.000 $2.150 $8.000 $1.000 $2.250
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $277.920 $125.000 $135.000 $705.000 $150.000 $150.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,297.300 $2,435.000 $2,620.000 $2,865.000 $2,650.000 $2,600.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $268.160 $250.000 $270.000 $435.000 $220.000 $275.000
REMOVE GROUND BOX
EA 1.000 $303.850 $88.010 $329.000 $100.000 $500.000 $250.000
REMOVE ELECTRICAL SERVICES
EA 4.000 $826.360 $204.480 $329.000 $350.000 $3,000.000 $850.000
ALUMINUM SIGNS (TY A)
SF 303.000 $33.820 $75.190 $19.000 $18.000 $15.500 $17.000
ALUMINUM SIGNS (TY G)
SF 429.000 $22.730 $33.000 $24.350 $21.000 $21.000 $23.000
ALUMINUM SIGNS (TY O)
SF 138.000 $17.160 $21.000 $16.450 $20.000 $31.000 $23.000
REPLACE EXISTING ALUMINUM SIGNS(TY A)
SF 901.000 $29.960 $14.750 $16.550 $18.000 $19.250 $17.000
REPLACE EXISTING ALUMINUM SIGNS(TY G)
SF 17,049.000 $27.400 $23.780 $17.540 $21.000 $25.250 $24.000
REPLACE EXISTING ALUMINUM SIGNS(TY O)
SF 33,343.000 $23.780 $23.270 $23.280 $23.000 $28.000 $24.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 6.000 $468.900 $623.000 $614.000 $625.000 $380.000 $675.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-EXAL)
EA 1.000 $687.500 $707.000 $802.000 $600.000 $435.000 $750.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 1.000 $526.710 $660.470 $650.000 $745.000 $465.000 $750.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T-2EXT)
EA 1.000 $668.090 $696.740 $833.000 $685.000 $500.000 $800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $623.730 $712.060 $781.000 $700.000 $585.000 $800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U-EXAL)
EA 1.000 $804.160 $799.180 $943.000 $700.000 $645.000 $900.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 1.000 $475.060 $867.000 $913.000 $865.000 $445.000 $925.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $638.560 $914.150 $950.000 $925.000 $545.000 $1,000.000
IN SM RD SN SUP&AM TYS80(1)SA(T-EXAL)
EA 2.000 $1,042.640 $999.490 $1,175.000 $925.000 $600.000 $1,100.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $778.400 $945.490 $1,116.000 $985.000 $645.000 $1,100.000
IN SM RD SN SUP&AM TYS80(1)SA(U-2EXT)
EA 1.000 $938.990 $1,006.490 $1,185.000 $1,045.000 $690.000 $1,100.000
IN SM RD SN SUP&AM TYS80(1)SA(U-EXAL)
EA 2.000 $1,166.530 $1,049.860 $1,243.000 $985.000 $705.000 $1,100.000
RELOCATE SM RD SN SUP&AM(SIGN ONLY)
EA 1.000 $279.350 $205.300 $220.000 $70.000 $125.000 $125.000
INSTALL LRSS (STRUCT STEEL)
LB 3,564.000 $5.820 $4.000 $3.780 $13.000 $19.850 $5.000
REMOVE LRSA
EA 23.000 $843.210 $996.720 $716.000 $455.000 $440.000 $950.000
INS OH SN SUP(30 FT CANT)
EA 1.000 $14,789.340 $18,438.900 $15,741.000 $21,850.000 $25,000.000 $25,000.000
INS OH SN SUP(60 FT BRDG)
EA 1.000 $21,000.000 $24,878.870 $21,031.000 $30,550.000 $35,000.000 $35,000.000
INS OH SN SUP(105 FT BRDG)
EA 1.000 $68,050.210 $45,784.730 $39,020.000 $46,750.000 $70,000.000 $75,000.000
REMOVE OVERHD SIGN SUP
EA 6.000 $8,399.550 $5,427.780 $4,753.000 $6,000.000 $7,000.000 $10,000.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 12.000 $24.060 $20.000 $22.000 $20.000 $21.000 $22.000
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
EA 9.000 $5,152.870 $3,499.060 $15,000.000 $4,100.000 $4,800.000 $5,000.000
REMOVAL OF CONTROL CABINET(GRND MNT)
EA 4.000 $845.000 $1,199.520 $3,034.000 $1,845.000 $1,500.000 $1,250.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 85.000 $105.000 $103.380 $129.000 $125.000 $80.000 $125.000
TMA (MOBILE OPERATION)
HR 3,500.000 $13.090 $26.640 $40.000 $60.000 $40.000 $78.000
Totals: $1,959,290.682 $1,921,528.610 $2,028,509.920 $2,143,494.000 $2,388,717.400 $2,484,287.500