BEXAR IH 410 (0521-04-293)

Items: 134

County: BEXAR
Length: 1.6430 MILES
Highway: IH 410
District: SAN ANTONIO
Control Number: 0521-04-293
DBE Goal: 4.0%
Project: CM 2025(391)
Guaranty: $75,000.00
Time: 195 WORKING DAYS
Engineer's Estimate: $2,896,669.01
Date: 03/05/2025 (1 year ago)
Contract Number: 3253221
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Project ID: A00183345
Contract Type: Federal
Project Description: CONSTRUCT CONTINUOUS 6' SIDEWALKS TO CLOSE GAPS. REMOVE AND REPLACE NON ADA COMPLIANT PEDESTRIAN STRUCTURES AND BARRIERS.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
CARLOS ARCILA
DANNY GALLEGOS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$2,896,669.01
$2,872,934.12
Over/Under Est: -0.82% -$23,734.89
$3,460,983.63
Over/Under Est: 19.48% $564,314.62
Amt Left: 20.47% $588,049.51
$3,461,365.40
Over/Under Est: 19.49% $564,696.39
Amt Left: 20.48% $588,431.28
Delta: -0.01% -$381.77
$3,527,349.57
Over/Under Est: 21.77% $630,680.56
Amt Left: 22.78% $654,415.45
Delta: -1.91% -$65,984.17
Over/Under Est: 22.42% $649,379.77
Amt Left: 23.43% $673,114.66
Delta: -0.53% -$18,699.21
$4,404,056.85
Over/Under Est: 52.04% $1,507,387.84
Amt Left: 53.29% $1,531,122.73
Delta: -24.20% -$858,008.07
Subcontractor Percentage Amount
SOUTH TEXAS TRAFFIC ALLIANCE INC. 5.27% $154,269.58
LONE STAR EROSION CONTROL 2.79% $81,672.13
LONE STAR PAVING COMPANY 2.57% $75,232.03
LIGHT IT UP ELECTRIC 2.34% $68,499.21
STRIPE IT UP, LLC 2.17% $63,522.77
NATIONAL WORKS, INC. 0.50% $14,636.58
GRATR LANDSCAPES, LTD. 0.36% $10,538.34
JANDY GROUP, LLC 0.33% $9,660.14
BOBCAT TRUCKING, INC. 0.02% $585.46
Total: 16.35% $478,616.24

Bid Items & Bid Tabulations

134 Total 0 of 134
BEXAR  |  IH 410  |  SAN ANTONIO  |  0521-04-293  |  03/05/2025  |  $2,896,669.01  |  CM 2025(391)  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  195 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
E-Z BEL CONSTRUCTION, LLC
TI-ZACK CONCRETE, LLC
DAN WILLIAMS COMPANY
TALBERT COMPANIES LLC
MP HEAVY CONSTRUCTION INC
BRICE HIGHWAY LLC
PREPARING ROW
STA 83.990 $1,800.000 $550.000 $825.000 $4,000.000 $2,687.500 $2,384.000 $4,640.000
REMOV CONC (RIPRAP)
SY 110.000 $24.790 $10.000 $24.620 $50.000 $13.276 $13.590 $95.150
REMOV CONC (MEDIANS)
SY 24.000 $20.320 $25.000 $37.620 $70.000 $30.100 $30.800 $110.170
REMOV CONC (PAVERS)
SY 5.000 $25.000 $25.000 $36.120 $320.000 $7.708 $7.890 $205.530
REMOV CONC (DRIVEWAYS)
SY 1,837.000 $33.000 $25.000 $19.660 $30.000 $18.856 $19.300 $92.770
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 211.000 $41.000 $25.000 $21.400 $35.000 $19.479 $20.000 $51.110
REMOV CONC (CURB)
LF 1,805.000 $12.300 $4.000 $10.000 $10.500 $4.150 $21.800 $15.060
REMOV CONC (FOUNDATIONS)
CY 1.000 $275.860 $25.000 $902.880 $1,000.000 $42.140 $550.000 $1,037.460
RMV (8") TRT/UNTRT BASE & ASPH PAV
SY 131.000 $20.000 $11.000 $27.570 $35.000 $6.558 $6.750 $62.480
EXCAV (SPECIAL)
CY 160.400 $134.370 $25.000 $56.290 $61.000 $26.660 $28.000 $205.720
EMBANK (FNL)(OC)(TY B)
CY 133.400 $144.590 $31.000 $67.680 $61.000 $27.950 $36.000 $340.560
COMPOST MANUF TOPSOIL (4")
SY 3,380.000 $4.620 $1.000 $5.240 $8.500 $2.956 $3.500 $2.750
BLOCK SODDING
SY 3,380.000 $7.810 $7.950 $7.700 $8.250 $8.546 $8.750 $7.950
VEGETATIVE WATERING
TGL 52.730 $76.940 $110.000 $1.100 $20.000 $84.151 $30.000 $392.400
D-GR HMA TY-C PG70-22 (LEVEL-UP)
TON 17.300 $203.870 $748.140 $330.000 $650.000 $215.000 $255.000 $250.000
PLANE ASPH CONC PAV(0" TO 2")
SY 867.000 $5.270 $10.500 $16.500 $35.000 $11.180 $4.250 $6.410
PLANE ASPH CONC PAV(0" TO 3")
SY 391.000 $5.010 $16.100 $22.000 $37.000 $9.675 $6.050 $6.600
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 8.000 $332.610 $260.000 $440.000 $450.000 $403.125 $737.000 $385.000
CL A CONC (MISC)
CY 10.000 $759.000 $490.000 $936.600 $900.000 $1,935.000 $787.500 $2,650.930
CL C CONC (MISC)
CY 24.300 $2,000.000 $480.000 $936.600 $900.000 $1,290.000 $4,000.000 $2,382.030
RIPRAP (CONC)(4 IN)
CY 117.500 $773.000 $560.000 $936.600 $675.000 $575.254 $701.000 $918.050
RAIL (HANDRAIL)(TY D)
LF 33.000 $103.160 $250.000 $396.000 $250.000 $371.972 $250.000 $413.550
INLET (COMP)(TY SIDEWALK BRIDGE)
EA 1.000 $11,598.850 $14,500.000 $24,750.000 $12,500.000 $16,125.000 $5,000.000 $7,716.220
GRATE & FRAME
EA 4.000 $2,500.000 $5,000.000 $9,350.000 $4,500.000 $1,612.500 $2,700.000 $5,152.480
MOBILIZATION
LS 1.000 $263,939.390 $200,000.000 $349,000.000 $340,000.000 $480,863.000 $459,000.000 $400,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $7,500.000 $1,000.000 $8,800.000 $25,000.000 $6,450.000 $3,500.000 $16,200.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $11,792.630 $30,000.000 $2,000.000 $12,000.000 $6,472.564 $11,000.000 $34,789.480
TMA (STATIONARY)
DAY 130.000 $252.750 $360.000 $1.100 $150.000 $242.542 $220.000 $526.250
TMA (MOBILE OPERATION)
HR 160.000 $123.200 $84.000 $1.100 $65.000 $67.499 $70.000 $174.270
CONSTRUCTION PERIMETER FENCE
LF 5,000.000 $9.000 $3.500 $1.100 $2.000 $2.096 $2.150 $1.950
SANDBAGS FOR EROSION CONTROL
EA 100.000 $40.000 $10.000 $0.110 $10.000 $10.750 $11.000 $10.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 8,800.000 $6.460 $7.000 $0.110 $3.500 $3.709 $3.800 $3.450
BIODEG EROSN CONT LOGS (REMOVE)
LF 8,800.000 $1.630 $1.000 $0.110 $1.000 $0.538 $0.550 $0.500
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 1,000.000 $50.000 $23.000 $60.000 $35.000 $104.812 $95.000 $89.210
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 60.000 $54.520 $26.000 $60.000 $35.000 $104.812 $94.000 $90.980
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 1,000.000 $16.710 $10.000 $11.000 $20.000 $34.282 $22.500 $14.790
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 60.000 $20.350 $7.000 $11.000 $20.000 $27.821 $22.000 $21.940
COLORED TEXTURED CONC (4")
SY 25.000 $94.140 $100.000 $177.750 $300.000 $138.621 $132.000 $313.410
LANDSCAPE PAVERS
SY 63.000 $97.620 $100.000 $165.000 $115.000 $135.321 $98.000 $256.940
REMOVE AND RELAY PAVERS
SY 83.000 $100.000 $100.000 $165.000 $125.000 $14.512 $185.000 $300.000
CONC CURB (TY II)
LF 1,878.000 $48.000 $24.000 $54.350 $35.000 $14.330 $14.660 $8.730
CONC CURB (MONO) (TY II)
LF 414.000 $22.890 $33.000 $45.980 $38.000 $16.662 $17.500 $8.730
CONC CURB (TY C1)
LF 1,141.000 $102.000 $77.000 $276.730 $175.000 $215.000 $220.000 $360.680
CONC CURB (TY C2)
LF 60.000 $150.000 $243.000 $298.900 $265.000 $304.322 $312.000 $360.790
INTERSECTIONS (ACP)
SY 1,196.000 $70.000 $151.000 $187.320 $90.000 $124.700 $156.000 $55.000
DRIVEWAYS (CONC)
SY 1,808.000 $102.250 $124.000 $146.260 $120.000 $103.114 $117.000 $166.710
CONC SIDEWALKS (4")
SY 4,902.000 $94.730 $97.000 $125.000 $70.000 $85.484 $87.500 $116.420
CONC SIDEWALKS (6")
SY 56.000 $96.460 $100.000 $177.820 $90.000 $105.888 $109.000 $231.200
CURB RAMPS (TY 1)
EA 13.000 $2,478.120 $5,000.000 $2,838.180 $2,600.000 $2,262.907 $2,316.000 $4,984.900
CURB RAMPS (TY 2)
EA 25.000 $3,000.000 $5,000.000 $2,838.180 $2,600.000 $2,760.826 $2,826.000 $4,984.900
CURB RAMPS (TY 3)
EA 9.000 $3,000.000 $5,000.000 $2,838.180 $2,600.000 $2,833.248 $2,900.000 $4,984.900
CURB RAMPS (TY 7)
EA 10.000 $2,750.000 $5,000.000 $2,838.180 $2,600.000 $2,470.189 $2,528.000 $4,984.900
CURB RAMPS (TY 22)
EA 1.000 $4,000.000 $6,000.000 $2,838.180 $4,200.000 $3,389.626 $3,469.000 $4,984.930
CONC MEDIAN
SY 80.000 $113.250 $270.000 $177.820 $115.000 $301.000 $308.000 $253.440
REMOVE METAL BEAM GUARD FENCE
LF 275.000 $6.620 $6.000 $5.780 $6.000 $5.644 $3.000 $6.000
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $399.800 $170.000 $302.500 $450.000 $295.625 $252.000 $450.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $201.990 $450.000 $357.500 $450.000 $349.375 $299.000 $450.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 8.000 $260.000 $300.000 $605.000 $560.000 $322.500 $307.000 $560.000
REMOVE RD IL ASM (TRANS-BASE)
EA 1.000 $786.540 $738.000 $1,100.000 $1,100.000 $1,075.000 $583.000 $1,050.000
REPLACE LUMINAIRE W/(150W EQ) LED
EA 6.000 $532.330 $680.000 $880.000 $600.000 $860.000 $704.000 $600.000
REPLACE LUMINAIRE W/(250W EQ) LED
EA 8.000 $827.520 $680.000 $880.000 $600.000 $860.000 $990.000 $600.000
IN RD IL (TY SA) 40T-8 (250W EQ) LED
EA 1.000 $4,665.140 $13,000.000 $10,450.000 $11,000.000 $10,212.500 $7,480.000 $9,820.000
CONDT (PVC) (SCH 40) (2")
LF 545.000 $16.040 $15.000 $22.000 $22.000 $21.500 $12.000 $22.000
CONDT (PVC) (SCH 80) (2")
LF 265.000 $27.230 $30.000 $22.000 $24.000 $21.500 $13.500 $24.000
CONDT (PVC) (SCH 80) (3")
LF 375.000 $37.120 $30.000 $33.000 $28.000 $32.250 $17.450 $28.000
CONDUIT (PREPARE)
LF 8,295.000 $1.920 $1.000 $2.200 $3.000 $2.150 $7.810 $3.000
ELEC CONDR (NO.14) INSULATED
LF 100.000 $1.760 $1.000 $4.400 $1.200 $4.300 $1.400 $1.200
ELEC CONDR (NO.8) BARE
LF 670.000 $2.100 $2.000 $4.400 $1.900 $4.300 $2.130 $1.900
ELEC CONDR (NO.8) INSULATED
LF 1,340.000 $1.940 $2.500 $4.400 $1.900 $4.300 $2.200 $1.900
ELEC CONDR (NO.6) BARE
LF 425.000 $2.200 $2.500 $4.400 $2.400 $4.300 $1.750 $2.400
ELEC CONDR (NO.6) INSULATED
LF 1,050.000 $2.330 $3.000 $4.400 $2.400 $4.300 $2.330 $2.400
GROUND BOX TY A (122311)W/APRON
EA 1.000 $1,316.970 $1,500.000 $1,540.000 $2,000.000 $1,505.000 $1,118.000 $1,525.000
GROUND BOX TY D (162922)
EA 7.000 $1,158.630 $1,000.000 $1,540.000 $2,000.000 $1,505.000 $1,441.000 $1,410.000
GROUND BOX TY D (162922)W/APRON
EA 3.000 $1,639.370 $2,000.000 $2,090.000 $2,000.000 $2,042.500 $1,310.000 $1,785.000
REMOVE GROUND BOX
EA 17.000 $247.310 $270.000 $440.000 $250.000 $430.000 $352.000 $200.000
REMOVE ELECTRICAL SERVICES
EA 1.000 $669.660 $370.000 $825.000 $1,000.000 $806.250 $968.000 $500.000
ELC SRV TY A 240/480 060(NS)SS(E)SP(U)
EA 1.000 $8,538.800 $10,000.000 $9,900.000 $12,500.000 $9,675.000 $7,320.000 $9,450.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 23.000 $795.630 $550.000 $850.000 $1,200.000 $591.250 $700.000 $1,545.000
RELOCATE SM RD SN SUP&AM TY S80
EA 4.000 $900.000 $859.000 $850.000 $1,000.000 $591.250 $600.000 $1,655.000
RELOCATE SM RD SN SUP&AM(SIGN ONLY)
EA 6.000 $204.500 $115.000 $850.000 $120.000 $147.812 $650.000 $115.420
REMOVE SM RD SN (FOUNDATION ONLY)
EA 6.000 $216.540 $137.500 $275.000 $120.000 $147.812 $125.000 $117.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 2,044.000 $1.000 $2.650 $1.930 $1.750 $2.849 $0.680 $1.750
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 606.000 $1.430 $2.850 $1.930 $1.750 $3.064 $0.810 $1.750
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 811.000 $1.570 $4.000 $5.500 $3.000 $5.375 $1.300 $10.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 3,007.000 $9.680 $6.000 $10.450 $9.500 $6.450 $9.450 $9.500
REFL PAV MRK TY I (Y)8"(SLD)(100MIL)
LF 756.000 $1.250 $2.000 $1.650 $1.500 $2.150 $1.150 $1.500
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 81.000 $8.550 $6.000 $10.450 $9.500 $6.450 $9.000 $9.500
RE PM TY II (W) 4" (BRK)
LF 134.000 $0.770 $2.000 $1.100 $1.000 $2.150 $0.300 $1.000
PAVEMENT SLER 4"
LF 134.000 $0.540 $0.500 $1.100 $1.000 $0.538 $0.500 $1.000
PAVEMENT SLER 8"
LF 756.000 $0.920 $0.500 $1.650 $1.500 $0.538 $0.600 $1.500
PAVEMENT SLER 24"
LF 3,088.000 $3.810 $2.000 $3.850 $3.500 $2.150 $2.500 $3.500
ELIM EXT PM & MRKS (4")
LF 104.000 $0.730 $1.000 $1.650 $1.500 $1.075 $0.820 $1.500
ELIM EXT PM & MRKS (8")
LF 756.000 $1.710 $1.000 $1.650 $1.500 $1.075 $1.500 $1.500
ELIM EXT PM & MRKS (24")
LF 2,653.000 $8.250 $3.000 $2.750 $2.500 $3.225 $5.000 $2.500
PAV SURF PREP FOR MRK (4")
LF 134.000 $0.340 $0.110 $0.170 $1.000 $0.118 $0.720 $0.150
PAV SURF PREP FOR MRK (8")
LF 756.000 $0.520 $0.110 $0.330 $1.000 $0.118 $0.900 $0.300
PAV SURF PREP FOR MRK (24")
LF 3,088.000 $1.360 $0.550 $0.550 $1.000 $0.591 $1.200 $0.500
INSTALL HWY TRF SIG (UPGRADE)
EA 3.000 $7,040.710 $5,600.000 $3,300.000 $3,500.000 $3,225.000 $10,010.000 $3,150.000
TEMP TRAF SIGNALS
EA 1.000 $25,000.000 $130,000.000 $93,500.000 $125,000.000 $91,375.000 $201,300.000 $75,454.000
PED SIG SEC (LED)(COUNTDOWN)
EA 12.000 $677.000 $850.000 $907.500 $700.000 $886.875 $1,210.000 $675.000
TRF SIG CBL (TY A)(12 AWG)(4 CONDR)
LF 7,085.000 $2.580 $3.000 $3.300 $3.200 $3.225 $4.630 $3.200
TRF SIG CBL (TY A)(12 AWG)(7 CONDR)
LF 2,425.000 $3.460 $4.000 $4.400 $4.200 $4.300 $6.330 $4.200
TRF SIG CBL (TY C)(14 AWG)(2 CONDR)
LF 11,470.000 $1.990 $2.000 $2.200 $2.900 $2.150 $3.340 $2.900
PED POLE ASSEMBLY
EA 17.000 $2,534.840 $2,000.000 $2,640.000 $3,250.000 $2,580.000 $5,500.000 $2,600.000
REMOVE PED POLE ASSEMBLY
EA 10.000 $643.000 $135.000 $550.000 $1,000.000 $537.500 $216.000 $375.000
PED DETECT PUSH BUTTON (APS)
EA 32.000 $1,105.490 $1,100.000 $935.000 $1,200.000 $913.750 $1,440.000 $1,150.000
PED DETECTOR CONTROLLER UNIT
EA 2.000 $1,874.820 $6,000.000 $3,850.000 $5,000.000 $3,762.500 $5,520.000 $3,745.000
REMOVAL OF CONDUIT
LF 730.000 $10.460 $3.000 $3.300 $3.500 $322.500 $15.600 $3.500
REMOVAL OF CABLES
LF 21,385.000 $0.950 $1.000 $1.100 $1.000 $1.075 $1.200 $1.000
REMOVAL OF PEDESTRIAN PUSH BUTTONS
EA 18.000 $122.330 $100.000 $82.500 $80.000 $80.625 $36.000 $80.000
ITS COM CBL (ETHERNET)
LF 505.000 $2.620 $4.000 $4.400 $2.000 $4.300 $3.540 $2.000
SYSTEM INTEGRATION
LS 1.000 $5,000.000 $10,000.000 $7,700.000 $7,000.000 $7,525.000 $9,840.000 $6,508.000
MANHOLE (PREPARE)
EA 2.000 $290.000 $2,500.000 $2,200.000 $1,500.000 $2,150.000 $900.000 $1,200.000
GROUND BOX (PREPARE)
EA 19.000 $260.510 $200.000 $550.000 $225.000 $537.500 $460.000 $225.000
REMOVE ITS RADIO
EA 1.000 $2,706.090 $200.000 $935.000 $550.000 $913.750 $900.000 $550.000
RELOCATE CCTV FIELD EQUIPMENT
EA 1.000 $3,672.280 $400.000 $2,200.000 $2,000.000 $2,150.000 $4,320.000 $2,000.000
FIELD HARDENED ETHERNET SWITCH RELOCATE
EA 1.000 $500.000 $800.000 $1,650.000 $1,000.000 $1,612.500 $1,032.000 $1,000.000
FIBER OPTIC CBL (SINGLE-MODE)(12 FIBER)
LF 2,280.000 $1.560 $4.000 $6.600 $2.500 $6.450 $3.720 $2.500
FO SPLICE ENCLOSURE (TYPE 2)
EA 1.000 $2,112.500 $2,300.000 $2,750.000 $1,800.000 $2,687.500 $2,421.000 $1,800.000
FIBER OPTIC FUSION SPLICE
EA 4.000 $116.790 $400.000 $550.000 $160.000 $537.500 $227.000 $160.000
FIBER OPTIC PATCH PANEL (12 POSITION)
EA 3.000 $2,313.690 $1,800.000 $2,750.000 $2,150.000 $2,687.500 $2,260.000 $2,110.000
REMOVE FIBER OPTIC CABLE
LF 1,610.000 $2.180 $3.000 $5.500 $3.000 $5.375 $1.320 $3.000
RELOCATE FIBER OPTIC CABLE
LF 50.000 $8.760 $6.000 $22.000 $14.000 $21.500 $15.900 $14.000
REMOVE EXISTING CABLES (POWER)
LF 120.000 $1.580 $4.000 $5.500 $4.000 $5.375 $1.320 $4.000
REMOVE EXISTING CABLES (COMMUNICATION)
LF 285.000 $0.520 $4.000 $5.500 $3.000 $5.375 $1.320 $3.000
REMOVE EXISTING LANE CONTROL SYSTEM
EA 1.000 $6,000.000 $3,500.000 $5,500.000 $4,000.000 $5,375.000 $4,080.000 $3,025.000
REMOVE EXISTING FIBER HUB
EA 1.000 $15,000.000 $6,000.000 $7,700.000 $6,000.000 $7,525.000 $11,400.000 $5,500.000
REMOV EXIST WIRELESS ETHERNET RADIO LNK
EA 1.000 $500.000 $1,500.000 $2,750.000 $1,800.000 $2,687.500 $900.000 $1,700.000
NEW METER BOX
EA 3.000 $1,200.000 $500.000 $1,375.000 $2,000.000 $5,321.250 $5,900.000 $750.000
ADJUST VALVE BOX
EA 11.000 $2,000.000 $400.000 $497.450 $1,850.000 $2,217.725 $1,500.000 $1,622.430
RELOCATE EXIST & NEW METER BOX
EA 3.000 $1,500.000 $700.000 $2,750.000 $2,000.000 $5,321.250 $3,500.000 $3,688.030
FIRE HYDRANT ASSEMBLY
EA 1.000 $11,000.000 $10,000.000 $16,500.000 $12,500.000 $11,277.707 $2,900.000 $15,502.210
SAN SWR STRUCTURES (RECONSTRUCT EX MH)
EA 4.000 $10,000.000 $25,500.000 $11,000.000 $13,000.000 $14,960.775 $2,500.000 $6,058.070
EXISTING MANHOLE ADJUSTMENTS
EA 2.000 $3,000.000 $3,000.000 $1,368.000 $7,500.000 $13,359.050 $1,800.000 $4,350.880
Totals: $2,896,669.011 $2,872,934.122 $3,460,983.631 $3,461,365.400 $3,527,353.690 $3,546,048.780 $4,404,056.848
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $3,900.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $23,200.00
ITS: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,500.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $8,400.00
Total: $37,000.00