BEXAR US 281 (0073-02-090)
Items: 19
County: BEXAR
Length: 0.7060 MILES
Highway: US 281
District: SAN ANTONIO
Control Number: 0073-02-090
DBE Goal: 0.0%
Project: STP 2026(377)HES
Guaranty: $10,000.00
Time: 85 WORKING DAYS
Engineer's Estimate: $476,457.50
Date: 02/05/2026 (4 months ago)
Contract Number: 2263234
Type: INSTALL ILLUMINATION
Project ID: A00206961
Contract Type: Federal
Project Description: INSTALL SAFETY ILLUMINATION ON US 281 ALONG SOUTHSIDE ISD CAMPUS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
BEXAR US 281 (0073-02-090)
Project Name: N/A
Project: STP 2026(377)HES
Length: 0.7060 MILES
Project Type: CONSTRUCTION
Limits From: FM 2537
Limits To: JANET GALE
Project Description: INSTALL SAFETY ILLUMINATION ON US 281 ALONG SOUTHSIDE ISD CAMPUS
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$476,457.50 | |||
| $368,657.75 |
-22.63%
-$107,799.75
|
|||
| $371,782.25 |
-21.97%
-$104,675.25
|
0.85%
$3,124.50
|
||
| $385,603.75 |
-19.07%
-$90,853.75
|
4.6%
$16,946.00
|
-3.72%
-$13,821.50
|
|
| $444,295.75 |
-6.75%
-$32,161.75
|
20.52%
$75,638.00
|
-15.22%
-$58,692.00
|
|
| $481,359.06 |
1.03%
$4,901.56
|
30.57%
$112,701.31
|
-8.34%
-$37,063.31
|
|
| $494,807.00 |
3.85%
$18,349.50
|
34.22%
$126,149.25
|
-2.79%
-$13,447.94
|
|
| $515,222.60 |
8.14%
$38,765.10
|
39.76%
$146,564.85
|
-4.13%
-$20,415.60
|
|
| $531,300.00 |
11.51%
$54,842.50
|
44.12%
$162,642.25
|
-3.12%
-$16,077.40
|
E
Engineer's Estimate
$476,457.50
1
Awarded
$368,657.75
Over/Under Est:
-22.63%
-$107,799.75
$371,782.25
Over/Under Est:
-21.97%
-$104,675.25
Amt Left:
0.85%
$3,124.50
$385,603.75
Over/Under Est:
-19.07%
-$90,853.75
Amt Left:
4.6%
$16,946.00
Delta:
-3.72%
-$13,821.50
$444,295.75
Over/Under Est:
-6.75%
-$32,161.75
Amt Left:
20.52%
$75,638.00
Delta:
-15.22%
-$58,692.00
$481,359.06
Over/Under Est:
1.03%
$4,901.56
Amt Left:
30.57%
$112,701.31
Delta:
-8.34%
-$37,063.31
$494,807.00
Over/Under Est:
3.85%
$18,349.50
Amt Left:
34.22%
$126,149.25
Delta:
-2.79%
-$13,447.94
$515,222.60
Over/Under Est:
8.14%
$38,765.10
Amt Left:
39.76%
$146,564.85
Delta:
-4.13%
-$20,415.60
$531,300.00
Over/Under Est:
11.51%
$54,842.50
Amt Left:
44.12%
$162,642.25
Delta:
-3.12%
-$16,077.40
Bid Items & Bid Tabulations
19
Total
0 of 19
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| CONTRACTOR FORCE ACCOUNT WORK (PART) | $30,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $20,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $15,000.00 |
| Total: | $70,000.00 |