Show Job Controls
Bid Cobra

BEXAR US 281 (0073-02-088)

Items: 17

County: BEXAR
Length: N/A
Highway: US 281
District: SAN ANTONIO
Control Number: 0073-02-088
DBE Goal: 0.0%
Project: STP 2B24(174)HES
Guaranty: N/A
Time: 97 WORKING DAYS
Engineer's Estimate: $1,997,645.39
Date: 06/05/2024 (2 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
ORLANDO GALLEGOS
THANYA TARROSA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (11)
E
Engineer's Estimate
$1,997,645.39
$1,472,160.93
Over/Under Est: -26.31% -$525,484.46
Over/Under Est: -20.16% -$402,753.48
Amt Left: 8.34% $122,730.98
Over/Under Est: -18.64% -$372,278.94
Amt Left: 10.41% $153,205.52
Delta: -1.91% -$30,474.54
$1,750,037.70
Over/Under Est: -12.39% -$247,607.69
Amt Left: 18.88% $277,876.77
Delta: -7.67% -$124,671.25
Over/Under Est: -11.89% -$237,552.39
Amt Left: 19.56% $287,932.07
Delta: -0.57% -$10,055.30
$1,814,687.50
Over/Under Est: -9.16% -$182,957.89
Amt Left: 23.27% $342,526.57
Delta: -3.10% -$54,594.50
Over/Under Est: -5.72% -$114,288.64
Amt Left: 27.93% $411,195.82
Delta: -3.78% -$68,669.25
Over/Under Est: -1.02% -$20,303.59
Amt Left: 34.32% $505,180.87
Delta: -4.99% -$93,985.05
$2,284,688.00
Over/Under Est: 14.37% $287,042.61
Amt Left: 55.19% $812,527.07
Delta: -15.54% -$307,346.20
Over/Under Est: 16.09% $321,332.76
Amt Left: 57.52% $846,817.22
Delta: -1.50% -$34,290.15
$2,450,922.00
Over/Under Est: 22.69% $453,276.61
Amt Left: 66.48% $978,761.07
Delta: -5.69% -$131,943.85
Subcontractor Percentage Amount
TRP CONSTRUCTION GROUP, LLC 1.04% $15,310.47
Total: 1.04% $15,310.47

Bid Items & Bid Tabulations

17 Total 0 of 17
BEXAR  |  US 281  |  SAN ANTONIO  |  0073-02-088  |  06/05/2024  |  $1,997,645.39  |  STP 2B24(174)HES  |  HAZARD ELIM & SAFETY  |  97 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ROADWAY SPECIALTIES, INC.
SCOUT 5 CONSTRUCTION LLC
SCR CIVIL CONSTRUCTION, LLC
DAN WILLIAMS COMPANY
MASSANA CONSTRUCTION INC.
ROSS SA ENTERPRISE LLC
HAZMAT INTERNATIONAL, INC.
MB WESTERN INDUSTRIAL CONTRACTING CO.
HJC FARMS, INC.
AARON CONCRETE CONTRACTORS, LLC
FNH CONSTRUCTION, LLC
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 306.000 $34.400 $60.420 $0.010 $40.000 $50.000 $55.000 $50.000 $55.000 $35.000 $35.000 $250.000 $100.000
BLADING
HR 256.000 $199.970 $141.320 $0.010 $100.000 $150.000 $90.000 $75.000 $150.000 $250.000 $200.000 $300.000 $150.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 29,225.000 $0.290 $0.270 $0.010 $0.250 $0.200 $0.250 $0.500 $0.500 $0.280 $0.350 $0.350 $1.000
DRILL SEED (TEMP)(WARM OR COOL)
SY 29,225.000 $0.190 $0.270 $0.010 $0.150 $0.180 $0.150 $0.500 $0.500 $0.260 $0.250 $0.300 $1.000
VEGETATIVE WATERING
MG 455.900 $22.180 $66.020 $0.010 $60.000 $8.000 $57.000 $100.000 $50.000 $175.000 $125.000 $35.000 $30.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 29,225.000 $1.860 $2.150 $0.010 $1.370 $1.200 $1.000 $2.500 $2.250 $1.700 $1.500 $2.000 $5.000
RIPRAP (CL A) (MOW STRIP) (3 IN)
CY 1,218.000 $415.000 $351.580 $800.000 $540.000 $500.000 $400.000 $460.000 $366.000 $635.000 $500.000 $505.000 $600.000
MOBILIZATION
LS 1.000 $175,860.010 $161,752.500 $75,000.000 $121,500.000 $175,000.000 $311,916.700 $85,000.000 $360,000.000 $250,000.000 $350,000.000 $230,000.000 $240,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $10,530.880 $1,160.250 $0.010 $4,800.000 $20,000.000 $12,500.000 $3,900.000 $17,000.000 $2,000.000 $3,000.000 $10,000.000 $8,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,348.000 $3.310 $3.040 $30.000 $4.600 $4.000 $3.500 $3.000 $8.000 $5.680 $6.000 $5.300 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,348.000 $0.800 $0.740 $1.000 $1.150 $1.000 $2.000 $1.000 $2.000 $1.420 $1.250 $1.500 $2.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 320.000 $6.070 $3.370 $80.000 $5.750 $5.000 $6.000 $10.000 $15.000 $7.100 $10.000 $6.500 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 320.000 $1.760 $1.890 $1.000 $1.150 $1.000 $2.000 $1.000 $6.000 $1.420 $7.000 $3.000 $9.000
CABLE BARRIER SYSTEM (TL-4)
LF 43,837.000 $15.740 $11.390 $8.000 $11.600 $11.000 $13.000 $14.000 $12.500 $11.300 $15.000 $17.000 $16.000
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 68.000 $4,457.310 $2,217.540 $1,400.000 $2,000.000 $2,925.000 $2,500.000 $3,500.000 $3,000.000 $2,350.000 $5,000.000 $4,900.000 $4,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 6.000 $14,525.470 $2,593.500 $0.010 $1,800.000 $5,000.000 $1,800.000 $2,000.000 $500.000 $5,000.000 $15,000.000 $8,000.000 $15,000.000
TMA (STATIONARY)
DAY 87.000 $235.780 $409.500 $0.010 $338.000 $204.000 $150.000 $1,000.000 $200.000 $200.000 $200.000 $250.000 $250.000
Totals: $1,997,645.392 $1,472,160.938 $1,594,891.919 $1,625,366.450 $1,750,037.700 $1,760,093.000 $1,814,687.500 $1,883,356.750 $1,977,341.800 $2,284,688.000 $2,318,978.150 $2,450,922.000