Show Job Controls
Bid Cobra

BELL FM0817 (6399-61-001)

Items: 17

County: BELL
Length: N/A
Highway: FM0817
District: WACO
Control Number: 6399-61-001
DBE Goal: N/A
Project: RMC - 639961001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $1,019,841.90
Date: 06/01/2022 (4 years ago)
Contract Number: N/A
Type: BASE FAILURE PAVEMENT REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (4)
E
Engineer's Estimate
$1,019,841.90
$1,087,969.99
Over/Under Est: 6.68% $68,128.09
Over/Under Est: 9.65% $98,444.85
Amt Left: 2.79% $30,316.76
Over/Under Est: 15.99% $163,043.90
Amt Left: 8.72% $94,915.81
Delta: -5.78% -$64,599.05
Over/Under Est: 30.24% $308,405.00
Amt Left: 22.08% $240,276.91
Delta: -12.29% -$145,361.10

Bid Items & Bid Tabulations

17 Total 0 of 17
BELL  |  FM0817  |  WACO  |  6399-61-001  |  06/01/2022  |  $1,019,841.90  |  RMC - 639961001  |  BASE FAILURE PAVMT REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
KNIFE RIVER CORPORATION - SOUTH
BIG CREEK CONSTRUCTION, LTD.
LONE STAR PAVING COMPANY
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 1,266.000 $50.000 $106.000 $81.350 $65.000 $125.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 4,000.000 $30.000 $30.000 $34.750 $32.500 $50.000
PLANE ASPH CONC PAV (2")
SY 42,177.000 $2.000 $2.150 $2.700 $2.000 $2.500
MOBILIZATION (CALLOUT)
EA 3.000 $25,181.300 $1.000 $375.000 $250.000 $2,250.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,882.000 $1.000 $1.250 $1.050 $1.500 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,882.000 $1.000 $1.250 $1.050 $1.500 $1.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 100.000 $7.000 $10.000 $7.150 $7.500 $11.500
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 4,704.000 $1.000 $0.720 $1.200 $1.250 $0.850
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 18,816.000 $1.000 $0.680 $0.600 $0.650 $0.800
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 4,704.000 $1.000 $0.750 $1.200 $1.250 $0.900
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 18,816.000 $1.000 $0.730 $0.600 $0.650 $0.850
REFL PAV MRKR TY I-C
EA 200.000 $5.000 $6.000 $4.750 $5.000 $6.900
REFL PAV MRKR TY II-A-A
EA 235.000 $4.000 $8.000 $4.750 $5.000 $9.200
D-GR HMA TY-C PG70-22
TON 4,640.000 $130.000 $149.000 $153.000 $180.000 $163.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 50.000 $80.000 $50.000 $5.250 $50.000 $325.000
TMA (STATIONARY)
DAY 50.000 $160.000 $90.000 $10.200 $40.000 $580.000
TMA (MOBILE OPERATION)
HR 100.000 $80.000 $25.000 $100.000 $10.000 $85.000
Totals: $1,019,841.900 $1,087,969.990 $1,118,286.750 $1,182,885.800 $1,328,246.900