BELL FM 3470 (3534-01-011)

Items: 23

County: BELL
Length: N/A
Highway: FM 3470
District: WACO
Control Number: 3534-01-011
DBE Goal: N/A
Project: STP 2017(398)
Guaranty: N/A
Time: 64 WORKING DAYS
Engineer's Estimate: $3,468,716.30
Date: 12/01/2016 (9 years ago)
Contract Number: N/A
Type: MILL/SEAL/INLY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$3,468,716.30
$3,489,225.84
Over/Under Est: 0.59% $20,509.54
Over/Under Est: 3.65% $126,651.63
Amt Left: 3.04% $106,142.09
$3,615,162.93
Over/Under Est: 4.22% $146,446.63
Amt Left: 3.61% $125,937.09
Delta: -0.55% -$19,795.00
Over/Under Est: 12.32% $427,243.76
Amt Left: 11.66% $406,734.22
Delta: -7.77% -$280,797.13
Over/Under Est: 35.03% $1,215,041.43
Amt Left: 34.23% $1,194,531.89
Delta: -20.22% -$787,797.67

Bid Items & Bid Tabulations

23 Total 0 of 23
BELL  |  FM 3470  |  WACO  |  3534-01-011  |  12/01/2016  |  $3,468,716.30  |  STP 2017(398)  |  MILL/SEAL/INLY  |  64 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
OLDCASTLE MATERIALS TEXAS, INC.
CLARK CONSTRUCTION OF TEXAS, INC.
AUSTIN MATERIALS, LLC
KNIFE RIVER CORPORATION - SOUTH
BIG CREEK CONSTRUCTION, LTD.
TOM (ASPHALT) PG 70-22
TON 1,120.000 $85.000 $90.000 $98.180 $90.000 $105.000 $115.000
TOM-F (AGGREGATE) SAC-B
TON 15,341.000 $100.000 $90.000 $98.180 $90.000 $105.000 $115.000
HIR (SURFACE) (2")
SY 280,792.000 $5.000 $4.750 $4.750 $4.750 $4.940 $6.000
HIR (RECYCLING AGENT)
GAL 140,396.000 $1.500 $2.750 $2.750 $2.750 $2.750 $3.500
MOBILIZATION
LS 1.000 $120,000.000 $211,000.030 $177,769.190 $288,100.000 $270,000.000 $450,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $5,000.000 $1,000.000 $1,800.000 $12,350.000 $8,500.000 $20,000.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 6,021.000 $1.000 $0.850 $1.000 $1.000 $1.200 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 9,051.000 $1.000 $0.850 $1.000 $1.000 $1.200 $1.000
REFL PAV MRK TY I (W)8"(DOT)(090MIL)
LF 141.000 $0.850 $0.950 $5.000 $0.900 $1.040 $1.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 3,539.000 $0.850 $0.650 $0.650 $0.550 $0.800 $1.000
REFL PAV MRK TY I (W)12"(SLD)(090MIL)
LF 438.000 $2.300 $3.050 $3.000 $2.780 $2.500 $4.000
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 1,061.000 $6.500 $6.100 $4.550 $5.660 $6.240 $7.500
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 19,210.000 $0.400 $0.270 $0.280 $0.290 $0.370 $0.310
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 15,838.000 $0.300 $0.270 $0.280 $0.270 $0.350 $0.310
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 16,850.000 $0.300 $0.270 $0.280 $0.280 $0.370 $0.310
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 68,735.000 $0.300 $0.270 $0.280 $0.280 $0.350 $0.310
PREFAB PAV MRK TY C (W) (ARROW)
EA 34.000 $200.000 $185.000 $165.000 $203.000 $184.000 $200.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 2.000 $400.000 $290.000 $285.000 $380.000 $353.000 $300.000
PREFAB PAV MRK TY C (W) (UTURN ARROW)
EA 1.000 $300.000 $340.000 $265.000 $425.000 $374.000 $340.000
PREFAB PAV MRK TY C (W) (WORD)
EA 5.000 $260.000 $245.000 $285.000 $255.000 $218.000 $335.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 20.000 $50.000 $36.000 $32.000 $29.500 $42.000 $40.000
REFL PAV MRKR TY I-C
EA 987.000 $4.000 $2.850 $3.000 $2.880 $3.430 $3.000
REFL PAV MRKR TY II-A-A
EA 1,857.000 $3.500 $2.850 $2.660 $2.880 $3.220 $3.000
Totals: $3,468,716.300 $3,489,225.840 $3,595,367.930 $3,615,162.930 $3,895,960.060 $4,683,757.730