BELL VARIOUS (0909-36-202)
Items: 86
County: BELL
Length: 0.0000 MILES
Highway: VARIOUS
District: WACO
Control Number: 0909-36-202
DBE Goal: 0.0%
Project: STP 2025(762)TAPS
Guaranty: $59,000.00
Time: 203 WORKING DAYS
Engineer's Estimate: $2,991,266.00
Date: 11/05/2025 (7 months ago)
Contract Number: 11253019
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Project ID: A00206364
Contract Type: Federal
Project Description: CONSTRUCT A SHARED USE PATH (SUP) ALONG FM 2483 FROM LAKE BELTON HS TO MORGAN'S POINT RD AND ALONG MORGAN'S POINT RD FROM FM 2483 TO SOBRANTE RD; ADD CROSSWALK AT INTERSECTION OF FM 2483 AND MORGAN'S POINT RD
Mail/Deliver Bids To: N/A
MICHAEL YATES
BELL VARIOUS (0909-36-202)
Project Name: N/A
Project: STP 2025(762)TAPS
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: FM 2483 CITY LIMITS TO MORGAN'S PT RD
Limits To: MORGAN'S PT RD FROM FM 2483 TO SOBRANTE
Project Description: CONSTRUCT A SHARED USE PATH (SUP) ALONG FM 2483 FROM LAKE BELTON HS TO MORGAN'S POINT RD AND ALONG MORGAN'S POINT RD FROM FM 2483 TO SOBRANTE RD; ADD CROSSWALK AT INTERSECTION OF FM 2483 AND MORGAN'S POINT RD
Bidders (11)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,991,266.00 | |||
| $2,475,157.73 |
-17.25%
-$516,108.27
|
|||
| $2,659,503.86 |
-11.09%
-$331,762.14
|
7.45%
$184,346.13
|
||
| $2,695,528.93 |
-9.89%
-$295,737.07
|
8.9%
$220,371.20
|
-1.35%
-$36,025.07
|
|
| $2,716,334.83 |
-9.19%
-$274,931.17
|
9.74%
$241,177.10
|
-0.77%
-$20,805.90
|
|
| $2,834,397.15 |
-5.24%
-$156,868.85
|
14.51%
$359,239.42
|
-4.35%
-$118,062.32
|
|
| $2,839,407.75 |
-5.08%
-$151,858.25
|
14.72%
$364,250.02
|
-0.18%
-$5,010.60
|
|
| $3,034,034.00 |
1.43%
$42,768.00
|
22.58%
$558,876.27
|
-6.85%
-$194,626.25
|
|
| $3,169,886.50 |
5.97%
$178,620.50
|
28.07%
$694,728.77
|
-4.48%
-$135,852.50
|
|
| $3,224,367.75 |
7.79%
$233,101.75
|
30.27%
$749,210.02
|
-1.72%
-$54,481.25
|
|
| $3,252,325.00 |
8.73%
$261,059.00
|
31.4%
$777,167.27
|
-0.87%
-$27,957.25
|
|
| $4,058,324.75 |
35.67%
$1,067,058.75
|
63.96%
$1,583,167.02
|
-24.78%
-$805,999.75
|
E
Engineer's Estimate
$2,991,266.00
1
Awarded
$2,475,157.73
Over/Under Est:
-17.25%
-$516,108.27
$2,659,503.86
Over/Under Est:
-11.09%
-$331,762.14
Amt Left:
7.45%
$184,346.13
$2,695,528.93
Over/Under Est:
-9.89%
-$295,737.07
Amt Left:
8.9%
$220,371.20
Delta:
-1.35%
-$36,025.07
$2,716,334.83
Over/Under Est:
-9.19%
-$274,931.17
Amt Left:
9.74%
$241,177.10
Delta:
-0.77%
-$20,805.90
$2,834,397.15
Over/Under Est:
-5.24%
-$156,868.85
Amt Left:
14.51%
$359,239.42
Delta:
-4.35%
-$118,062.32
$2,839,407.75
Over/Under Est:
-5.08%
-$151,858.25
Amt Left:
14.72%
$364,250.02
Delta:
-0.18%
-$5,010.60
$3,034,034.00
Over/Under Est:
1.43%
$42,768.00
Amt Left:
22.58%
$558,876.27
Delta:
-6.85%
-$194,626.25
$3,169,886.50
Over/Under Est:
5.97%
$178,620.50
Amt Left:
28.07%
$694,728.77
Delta:
-4.48%
-$135,852.50
$3,224,367.75
Over/Under Est:
7.79%
$233,101.75
Amt Left:
30.27%
$749,210.02
Delta:
-1.72%
-$54,481.25
$3,252,325.00
Over/Under Est:
8.73%
$261,059.00
Amt Left:
31.4%
$777,167.27
Delta:
-0.87%
-$27,957.25
$4,058,324.75
Over/Under Est:
35.67%
$1,067,058.75
Amt Left:
63.96%
$1,583,167.02
Delta:
-24.78%
-$805,999.75
| Subcontractor | Percentage | Amount |
|---|---|---|
| URBANGLOW CONTRACTING LLC | 11.55% | $285,880.72 |
| TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. | 2.52% | $62,373.97 |
| AWP SAFETY | 2.34% | $57,918.69 |
| LINEAR TRAFFIC MARKINGS LLC | 0.34% | $8,415.54 |
| THE F.A. BARTLETT TREE EXPERT COMPANY | 0.07% | $1,732.61 |
| Total: | 16.82% | $416,321.53 |
Bid Items & Bid Tabulations
86
Total
0 of 86