BELL SH 195 (0836-02-079)
Items: 51
County: BELL
Length: 4.9700 MILES
Highway: SH 195
District: WACO
Control Number: 0836-02-079
DBE Goal: 3.0%
Project: STP 2025(770)HES
Guaranty: $100,000.00
Time: 120 WORKING DAYS
Engineer's Estimate: $6,524,882.17
Date: 05/02/2025 (1 year ago)
Contract Number: 5253228
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00177444
Contract Type: Federal
Project Description: INSTALL MEDIAN BARRIER
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
MICHAEL YATES
BELL SH 195 (0836-02-079)
Project Name: N/A
Project: STP 2025(770)HES
Length: 4.9700 MILES
Project Type: CONSTRUCTION
Limits From: .7 MI S OF FM 2670
Limits To: WILLIAMSON COUNTY LINE
Project Description: INSTALL MEDIAN BARRIER
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$6,524,882.17 | |||
| $4,930,555.11 |
-24.43%
-$1,594,327.06
|
|||
| $5,448,263.57 |
-16.5%
-$1,076,618.60
|
10.5%
$517,708.46
|
||
| $5,495,495.00 |
-15.78%
-$1,029,387.17
|
11.46%
$564,939.89
|
-0.87%
-$47,231.43
|
|
| $5,651,254.85 |
-13.39%
-$873,627.32
|
14.62%
$720,699.74
|
-2.83%
-$155,759.85
|
|
| $5,799,799.00 |
-11.11%
-$725,083.17
|
17.63%
$869,243.89
|
-2.63%
-$148,544.15
|
|
| $5,966,890.75 |
-8.55%
-$557,991.42
|
21.02%
$1,036,335.64
|
-2.88%
-$167,091.75
|
|
| $6,308,234.10 |
-3.32%
-$216,648.07
|
27.94%
$1,377,678.99
|
-5.72%
-$341,343.35
|
E
Engineer's Estimate
$6,524,882.17
1
Awarded
$4,930,555.11
Over/Under Est:
-24.43%
-$1,594,327.06
$5,448,263.57
Over/Under Est:
-16.5%
-$1,076,618.60
Amt Left:
10.5%
$517,708.46
$5,495,495.00
Over/Under Est:
-15.78%
-$1,029,387.17
Amt Left:
11.46%
$564,939.89
Delta:
-0.87%
-$47,231.43
$5,651,254.85
Over/Under Est:
-13.39%
-$873,627.32
Amt Left:
14.62%
$720,699.74
Delta:
-2.83%
-$155,759.85
$5,799,799.00
Over/Under Est:
-11.11%
-$725,083.17
Amt Left:
17.63%
$869,243.89
Delta:
-2.63%
-$148,544.15
$5,966,890.75
Over/Under Est:
-8.55%
-$557,991.42
Amt Left:
21.02%
$1,036,335.64
Delta:
-2.88%
-$167,091.75
$6,308,234.10
Over/Under Est:
-3.32%
-$216,648.07
Amt Left:
27.94%
$1,377,678.99
Delta:
-5.72%
-$341,343.35
| Subcontractor | Percentage | Amount |
|---|---|---|
| ENVIRONMENTAL SAFETY SERVICES, INC. | 24.11% | $1,164,586.51 |
| SCOTT DERR PAINTING CO, LLC | 1.51% | $72,937.60 |
| LINEAR TRAFFIC MARKINGS LLC | 0.98% | $47,336.99 |
| SUPERIOR TRAFFIC CONTROL, LLC | 0.24% | $11,592.73 |
| Total: | 26.84% | $1,296,453.83 |
Bid Items & Bid Tabulations
51
Total
0 of 51
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $90,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $3,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| Total: | $103,000.00 |