Show Job Controls
Bid Cobra

BELL IH 14 (0231-03-156)

Items: 45

County: BELL
Length: 0.0000 MILES
Highway: IH 14
District: WACO
Control Number: 0231-03-156
DBE Goal: 0.0%
Project: STP 2026(492)VRU
Guaranty: $76,000.00
Time: 126 WORKING DAYS
Engineer's Estimate: $3,792,762.86
Date: 06/03/2026 (7 days ago)
Contract Number: 6263206
Type: INSTALL ILLUMINATION
Project ID: A00197666
Contract Type: Federal
Project Description: SAFETY LIGHTING
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
MICHAEL YATES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (11)
E
Engineer's Estimate
$3,792,762.86
Over/Under Est: -21.4% -$811,737.03
Over/Under Est: -20.9% -$792,762.85
Amt Left: 0.64% $18,974.18
Over/Under Est: -16.42% -$622,941.66
Amt Left: 6.33% $188,795.37
Delta: -5.66% -$169,821.19
Over/Under Est: -14.06% -$533,419.11
Amt Left: 9.34% $278,317.92
Delta: -2.82% -$89,522.55
$3,381,522.63
Over/Under Est: -10.84% -$411,240.23
Amt Left: 13.43% $400,496.80
Delta: -3.75% -$122,178.88
Over/Under Est: -5.15% -$195,180.86
Amt Left: 20.68% $616,556.17
Delta: -6.39% -$216,059.37
Over/Under Est: -3.17% -$120,090.86
Amt Left: 23.2% $691,646.17
Delta: -2.09% -$75,090.00
Over/Under Est: -3.04% -$115,362.86
Amt Left: 23.36% $696,374.17
Delta: -0.13% -$4,728.00
$3,823,417.14
Over/Under Est: 0.81% $30,654.28
Amt Left: 28.26% $842,391.31
Delta: -3.97% -$146,017.14
Over/Under Est: 5.31% $201,371.64
Amt Left: 33.99% $1,013,108.67
Delta: -4.47% -$170,717.36
$4,313,616.92
Over/Under Est: 13.73% $520,854.06
Amt Left: 44.7% $1,332,591.09
Delta: -8.00% -$319,482.42

Bid Items & Bid Tabulations

45 Total 0 of 45
BELL  |  IH 14  |  WACO  |  0231-03-156  |  06/03/2026  |  $3,792,762.86  |  STP 2026(492)VRU  |  INSTL ILLUM  |  126 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC
ALBATROSS CONSTRUCTION LLC
E-Z BEL CONSTRUCTION, LLC
VACA UNDERGROUND UTILITIES INC
SICE, INC.
ELECNOR BELCO ELECTRIC, INC.
FLORIDA TRAFFIC CONTROL DEVICES, INC.
CROSS PLUS CONSTRUCTION, LLC
THE LEVY COMPANY, LLC
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., LLC
DIGG COMMERCIAL, LLC
REMOV CONC (MOWSTRIP)
LF 169.000 $60.000 $30.680 $30.702 $4.750 $45.000 $5.631 $5.700 $30.750 $42.000 $31.850 $45.000 $3.000
REMOV CONC (RAIL)
LF 19.500 $80.000 $152.220 $94.248 $100.000 $45.000 $82.973 $32.000 $94.300 $45.000 $127.400 $100.000 $20.000
DRILL SEED (PERM_URBAN_CLAY)
SY 2,200.000 $0.800 $0.470 $4.165 $0.230 $0.350 $0.273 $0.600 $0.300 $0.900 $0.640 $3.000 $1.000
DRILL SEED (TEMP_WARM_COOL)
SY 2,200.000 $0.800 $0.470 $4.165 $0.170 $0.350 $0.202 $0.600 $0.200 $0.900 $1.020 $3.000 $1.000
VEGETATIVE WATERING
TGL 36.000 $100.000 $118.000 $357.000 $250.000 $10.000 $134.142 $591.000 $77.400 $123.000 $25.480 $207.000 $12.000
DRILL SHAFT (HIGH MAST POLE) (54 IN)
LF 668.000 $750.000 $549.940 $664.651 $570.000 $600.000 $832.092 $651.000 $877.000 $952.000 $764.520 $923.000 $650.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 20.000 $500.000 $258.680 $297.429 $400.000 $400.000 $146.479 $432.000 $470.000 $856.000 $394.120 $200.000 $300.000
CL C CONC (WINGWALLS)
CY 0.770 $8,000.000 $4,720.000 $4,069.800 $5,500.000 $2,300.000 $3,122.267 $8,037.000 $4,072.000 $12,000.000 $4,357.260 $6,000.000 $5,000.000
RIPRAP (CONC)(4 IN)
CY 61.000 $1,300.000 $531.000 $1,035.300 $900.000 $550.000 $806.022 $591.000 $1,036.000 $856.000 $733.850 $1,400.000 $584.000
RIPRAP (MOW STRIP)(4 IN)
CY 63.000 $700.000 $767.000 $963.900 $585.000 $550.000 $669.710 $692.000 $965.000 $963.000 $777.170 $900.000 $607.000
MOBILIZATION
LS 1.000 $271,612.060 $243,558.890 $196,025.758 $250,000.000 $125,000.000 $260,910.723 $318,000.000 $365,000.000 $250,091.000 $358,423.120 $250,000.000 $275,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $14,000.000 $2,655.000 $10,776.116 $10,000.000 $3,000.000 $6,002.775 $13,896.000 $10,280.000 $15,000.000 $2,293.300 $6,000.000 $10,238.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,500.000 $8,850.000 $10,710.000 $7,500.000 $7,500.000 $9,845.151 $4,864.000 $170.000 $1,200.000 $18,473.760 $172.000 $8,479.000
TMA (STATIONARY)
DAY 181.000 $300.000 $189.890 $269.047 $375.000 $80.000 $343.478 $139.000 $170.000 $250.000 $216.590 $425.000 $1,000.000
TMA (MOBILE OPERATION)
HR 500.000 $80.000 $83.980 $41.650 $33.000 $80.000 $95.943 $67.000 $170.000 $85.000 $57.330 $150.000 $66.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,800.000 $4.500 $3.540 $5.950 $1.000 $1.000 $3.497 $3.500 $3.500 $1.000 $3.760 $10.000 $4.000
TEMP SDMT CONT FENCE (INLET PROTECTION)
LF 200.000 $6.000 $11.800 $35.700 $1.000 $1.000 $4.742 $4.800 $4.750 $56.000 $5.100 $20.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,000.000 $1.800 $1.770 $2.975 $1.000 $1.000 $1.127 $1.200 $1.150 $1.000 $0.960 $1.500 $1.000
MTL W-BEAM GD FEN (STEEL POST)
LF 850.000 $35.000 $36.580 $36.890 $33.500 $32.000 $39.709 $40.000 $39.900 $45.000 $42.680 $45.000 $28.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 1.000 $2,500.000 $2,596.000 $2,618.000 $2,675.000 $30,000.000 $3,170.747 $3,162.160 $3,185.000 $2,500.000 $2,675.510 $3,200.000 $2,172.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,600.000 $1,416.000 $1,428.000 $1,425.000 $2,000.000 $1,689.090 $1,685.000 $1,700.000 $1,200.000 $1,337.760 $2,000.000 $1,250.000
REMOVE METAL BEAM GUARD FENCE
LF 100.000 $4.750 $3.540 $3.570 $2.000 $4.000 $2.371 $2.400 $3.000 $5.000 $2.550 $20.000 $2.360
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 1.000 $300.000 $177.000 $178.500 $150.000 $175.000 $177.799 $178.000 $180.060 $236.000 $191.110 $300.000 $195.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $4,000.000 $3,540.000 $3,570.000 $3,500.000 $3,500.000 $4,148.640 $4,137.000 $4,165.000 $4,123.000 $3,694.750 $4,300.000 $3,200.000
GUARDRAIL END TREATMENT (REMOVE)
EA 3.000 $400.000 $295.000 $297.500 $150.000 $350.000 $177.799 $178.000 $180.000 $236.000 $191.110 $600.000 $236.000
REMOVE RD IL ASM (BRIDGE MOUNT)
EA 1.000 $550.000 $406.720 $225.779 $800.000 $550.000 $344.525 $464.000 $600.000 $523.000 $271.670 $2,000.000 $873.000
REMOVE RD IL ASM (TRANS-BASE)
EA 37.000 $750.000 $730.640 $225.779 $700.000 $550.000 $359.469 $618.000 $795.000 $1,200.000 $543.350 $600.000 $810.000
IN RD IL (TY SA) 40T-8 (250W EQ) LED
EA 5.000 $5,600.000 $4,991.130 $4,636.954 $5,000.000 $6,000.000 $4,222.771 $5,225.000 $5,860.000 $6,500.000 $5,254.870 $5,300.000 $4,981.000
CONDT (PVC) (SCH 40) (3")
LF 19,529.000 $15.000 $11.160 $10.175 $8.000 $15.000 $12.338 $15.000 $14.000 $15.000 $8.410 $9.000 $21.000
CONDT (PVC) (SCH 80) (3") (BORE)
LF 2,381.000 $28.000 $20.070 $24.883 $30.000 $20.000 $30.460 $30.000 $22.700 $51.000 $34.280 $60.000 $28.000
CONDUIT (PREPARE)
LF 6,822.000 $3.000 $1.010 $1.273 $0.500 $1.000 $1.055 $5.000 $4.500 $14.000 $1.460 $1.500 $3.660
REMOVE GROUND BOX
EA 22.000 $350.000 $531.800 $244.462 $175.000 $400.000 $296.332 $410.000 $325.000 $123.000 $247.570 $95.000 $350.000
INSTL GROUND BOX (W/SECURE LID)
EA 83.000 $2,200.000 $2,533.310 $1,877.320 $1,750.000 $2,250.000 $1,665.517 $1,728.000 $2,500.000 $1,000.000 $2,910.080 $2,800.000 $1,816.000
RETRO GROUND BOX (W/SECURE LID)
EA 35.000 $1,500.000 $1,911.610 $971.100 $845.000 $1,650.000 $1,028.567 $1,847.000 $1,375.000 $1,230.000 $1,123.080 $1,500.000 $164.000
REMOVE ELECTRICAL SERVICES
EA 6.000 $800.000 $1,153.280 $719.486 $550.000 $650.000 $723.573 $1,236.000 $320.000 $521.000 $638.290 $689.000 $565.000
ELC SRV TY A 240/480 060(NS)SS(E)SP(U)
EA 10.000 $8,500.000 $9,124.570 $7,947.855 $7,000.000 $7,500.000 $7,723.184 $9,165.000 $8,665.000 $7,500.000 $5,503.300 $5,800.000 $15,000.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 17.000 $60.000 $53.100 $53.550 $34.000 $85.000 $40.302 $40.000 $40.000 $155.000 $43.320 $45.000 $40.000
REMOVE ABOVE-GROUND CONDUIT
LF 261.000 $15.000 $29.840 $14.030 $10.000 $7.000 $7.112 $5.000 $13.000 $2.000 $7.450 $5.000 $8.000
REMOVE CONDUCTOR
LF 59,901.000 $1.000 $0.400 $0.428 $0.200 $1.000 $0.247 $0.800 $1.300 $0.500 $0.550 $0.500 $0.780
REPLACE FUSE
EA 20.000 $65.000 $45.540 $129.139 $25.000 $60.000 $47.368 $126.000 $60.000 $321.000 $67.320 $50.000 $46.000
REPLACE BREAKAWAY FUSE HOLDER
EA 10.000 $180.000 $155.810 $276.699 $220.000 $210.000 $47.368 $226.000 $230.000 $321.000 $394.240 $200.000 $153.000
GROUND BOX (PREPARE)
EA 3.000 $400.000 $340.640 $432.006 $600.000 $625.000 $237.066 $309.000 $325.000 $1,562.000 $1,399.220 $500.000 $388.000
ALUMINUM ELECTRICAL COND (#6 XHHW)
LF 95,463.000 $1.600 $1.030 $0.928 $0.750 $1.750 $1.089 $1.750 $1.500 $2.000 $1.840 $2.000 $1.740
LED HM(100 FT)(100MPH)(6FIXT)(TY B)
EA 22.000 $62,000.000 $48,944.640 $48,396.015 $62,000.000 $60,000.000 $58,468.145 $59,530.000 $51,675.000 $52,000.000 $70,759.490 $67,000.000 $81,000.000
LED HM(100 FT)(100MPH)(6FIXT)(TY B)SHLD
EA 3.000 $63,000.000 $51,726.650 $49,363.485 $62,750.000 $60,000.000 $58,776.095 $54,158.000 $52,700.000 $52,000.000 $71,495.640 $69,000.000 $86,000.000
Totals: $3,792,762.860 $2,981,025.830 $2,999,999.988 $3,169,821.200 $3,259,343.750 $3,381,522.605 $3,597,582.000 $3,672,672.000 $3,677,400.000 $3,823,417.140 $3,994,134.500 $4,313,616.920
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $15,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $30,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $15,000.00
Total: $60,000.00