BELL IH 14 (0231-03-154)

Items: 19

County: BELL
Length: N/A
Highway: IH 14
District: WACO
Control Number: 0231-03-154
DBE Goal: N/A
Project: C 231-3-154
Guaranty: N/A
Time: 234 WORKING DAYS
Engineer's Estimate: $4,936,773.45
Date: 05/04/2023 (3 years ago)
Contract Number: N/A
Type: HIGHWAY IMPROVEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$4,936,773.45
$4,494,840.00
Over/Under Est: -8.95% -$441,933.45
$4,788,408.00
Over/Under Est: -3.01% -$148,365.45
Amt Left: 6.53% $293,568.00
Over/Under Est: 9.49% $468,416.55
Amt Left: 20.25% $910,350.00
Delta: -12.88% -$616,782.00
Over/Under Est: 22.1% $1,091,136.55
Amt Left: 34.11% $1,533,070.00
Delta: -11.52% -$622,720.00
Over/Under Est: 30.78% $1,519,556.14
Amt Left: 43.64% $1,961,489.59
Delta: -7.11% -$428,419.59
Over/Under Est: 32.19% $1,588,944.55
Amt Left: 45.18% $2,030,878.00
Delta: -1.07% -$69,388.41
$6,717,214.00
Over/Under Est: 36.06% $1,780,440.55
Amt Left: 49.44% $2,222,374.00
Delta: -2.93% -$191,496.00
Subcontractor Percentage Amount
JB PINNACLE GROUP, LLC 36.60% $1,645,111.44
J. H. ODEN CONTRACTING COMPANY 2.35% $105,628.74
J.H. PAINTING COMPANY 1.01% $45,397.88
TRAFFIC HIGHWAY MAINTENANCE, LLC 0.48% $21,575.23
HERMANOS STEEL, LLC 0.00% $0.00
Total: 40.44% $1,817,713.29

Bid Items & Bid Tabulations

19 Total 0 of 19
BELL  |  IH 14  |  WACO  |  0231-03-154  |  05/04/2023  |  $4,936,773.45  |  C 231-3-154  |  HWY IMPRV  |  234 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SCR CIVIL CONSTRUCTION, LLC
MIJELUM, L.L.C.
JAMES CONSTRUCTION GROUP, LLC
AARON CONCRETE CONTRACTORS, LLC
ROADWAY SPECIALTIES, INC.
CROSS PLUS CONSTRUCTION, LLC
FNH CONSTRUCTION, LLC
REMOVING CONCRETE(MOW STRIP)
LF 13,329.000 $12.500 $16.000 $10.000 $8.000 $10.000 $10.120 $35.000 $20.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 1,481.000 $26.000 $24.000 $50.000 $45.000 $70.000 $37.430 $35.000 $35.000
BLADING
STA 129.400 $120.000 $140.000 $1,000.000 $612.000 $350.000 $100.000 $250.000 $250.000
ROLL SODDING
SY 17,677.000 $4.200 $7.000 $10.000 $6.500 $8.500 $9.550 $9.000 $10.000
CL C CONC (RAIL FOUNDATION)
CY 1,292.000 $900.000 $725.000 $998.000 $677.000 $590.000 $594.240 $689.000 $1,000.000
MOBILIZATION
LS 1.000 $400,831.050 $200,000.000 $15,000.000 $539,694.700 $550,000.000 $750,000.000 $400,000.000 $600,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $8,000.000 $7,500.000 $10,000.000 $38,500.000 $1,500.000 $1,584.800 $8,963.000 $8,500.000
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
LF 19,470.000 $12.000 $9.000 $15.000 $10.000 $26.000 $31.870 $29.000 $30.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 14,220.000 $6.000 $5.000 $15.000 $10.000 $18.000 $19.760 $29.000 $30.000
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 19,740.000 $12.000 $9.000 $20.000 $10.000 $25.000 $31.870 $29.000 $30.000
PERM CTB (SGL SLOPE) (TY 1) (42 )
LF 12,922.000 $110.000 $92.000 $55.000 $81.000 $105.000 $102.980 $50.000 $90.000
REMOVE METAL BEAM GUARD FENCE
LF 1,223.000 $2.500 $25.000 $10.000 $6.000 $3.500 $4.000 $20.000 $3.000
REMOVE CABLE BARRIER
LF 12,132.000 $4.500 $4.000 $10.000 $6.000 $3.500 $13.500 $5.000 $20.000
REMOVE CABLE BARRIER TERMINAL SECTION
EA 12.000 $500.000 $800.000 $1,000.000 $800.000 $450.000 $325.730 $562.000 $500.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 4.000 $2,250.000 $3,000.000 $1,000.000 $2,600.000 $3,000.000 $2,822.350 $3,500.000 $5,000.000
CRASH CUSH ATTEN (STKPL)
EA 1.000 $1,250.000 $6,000.000 $1,000.000 $1,000.000 $1,100.000 $2,500.000 $5,000.000 $2,500.000
CRASH CUSH ATTEN (INSTL)(R)(N)(70)
EA 1.000 $34,000.000 $32,000.000 $25,000.000 $30,000.000 $36,000.000 $32,340.660 $10,000.000 $21,000.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 129.000 $11.000 $30.000 $70.000 $25.000 $29.000 $14.370 $100.000 $100.000
PEDESTRIAN BARRIER (FURN & INSTALL)
LF 32,274.000 $28.000 $35.000 $33.000 $46.000 $48.000 $45.460 $65.000 $35.000
Totals: $4,936,773.450 $4,494,840.000 $4,788,408.000 $5,405,190.000 $6,027,910.000 $6,456,329.590 $6,525,718.000 $6,717,214.000