Show Job Controls
Bid Cobra

BELL US 190 (0185-05-003)

Items: 32

County: BELL
Length: N/A
Highway: US 190
District: WACO
Control Number: 0185-05-003
DBE Goal: N/A
Project: STP 2023(717)HES
Guaranty: N/A
Time: 60 WORKING DAYS
Engineer's Estimate: $4,361,713.62
Date: 05/04/2023 (3 years ago)
Contract Number: N/A
Type: INSTALL MEDIAN BARRIER
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$4,361,713.62
$4,600,000.00
Over/Under Est: 5.46% $238,286.38
Over/Under Est: 12.34% $538,068.29
Amt Left: 6.52% $299,781.91
Over/Under Est: 14.46% $630,895.39
Amt Left: 8.53% $392,609.01
Delta: -1.89% -$92,827.10
$5,736,771.00
Over/Under Est: 31.53% $1,375,057.38
Amt Left: 24.71% $1,136,771.00
Delta: -14.91% -$744,161.99

Bid Items & Bid Tabulations

32 Total 0 of 32
BELL  |  US 190  |  WACO  |  0185-05-003  |  05/04/2023  |  $4,361,713.62  |  STP 2023(717)HES  |  INSTL MEDIAN BARRIER  |  60 WORKING DAYS
Alt
Item Code
Description
Unit
Quantity
Engineer's Estimate
JAMES CONSTRUCTION GROUP, LLC
MB WESTERN INDUSTRIAL CONTRACTING COMPANY
SCR CIVIL CONSTRUCTION, LLC
FNH CONSTRUCTION, LLC
SUBGRADE WIDENING (ORD COMP)
STA 245.000 $245.880 $500.000 $500.000 $1,270.000 $450.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 2,763.000 $50.000 $45.000 $50.000 $68.000 $50.000
BLADING
STA 245.000 $95.000 $300.000 $185.000 $75.000 $250.000
FURNISHING AND PLACING TOPSOIL (4")
SY 68,153.000 $1.500 $0.200 $4.000 $2.270 $6.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 68,153.000 $1.100 $0.220 $0.250 $0.250 $1.000
BROADCAST SEED (TEMP)(WARM OR COOL)
SY 68,153.000 $0.300 $0.170 $0.200 $0.150 $1.000
VEGETATIVE WATERING
MG 1,107.000 $31.000 $28.000 $30.000 $90.000 $50.000
CL B CONC (MISC)
CY 30.000 $1,025.000 $1,000.000 $802.000 $2,300.000 $2,000.000
CONCRETE PAINT FINISH
SF 188,400.000 $1.960 $1.750 $2.410 $1.750 $3.500
RIPRAP (MOW STRIP)(4 IN)
CY 428.000 $508.190 $500.000 $571.000 $660.000 $550.000
MOBILIZATION
LS 1.000 $436,115.240 $432,547.230 $500,000.000 $162,000.000 $500,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $4,000.000 $27,500.000 $7,290.000 $5,000.000 $8,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 150.000 $4.690 $3.000 $5.000 $9.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 150.000 $1.760 $1.500 $3.000 $1.100 $2.000
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
LF 23,550.000 $16.000 $35.000 $25.000 $35.000 $30.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 4,500.000 $8.000 $10.000 $20.000 $44.000 $30.000
MTL W-BEAM GD FEN (STEEL POST)
LF 3,713.000 $35.110 $35.000 $32.810 $30.000 $40.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 32.000 $2,025.200 $2,620.000 $2,612.000 $2,715.000 $2,000.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 9.000 $1,382.000 $1,440.000 $1,215.000 $1,250.000 $2,000.000
REMOVE METAL BEAM GUARD FENCE
LF 3,609.000 $3.630 $4.500 $3.000 $3.500 $3.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 28.000 $232.780 $200.000 $303.750 $350.000 $500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 15.000 $2,734.700 $3,375.000 $3,432.380 $2,850.000 $3,250.000
GUARDRAIL END TREATMENT (REMOVE)
EA 15.000 $388.000 $290.000 $303.750 $600.000 $1,500.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 14.000 $29,545.000 $33,000.000 $31,500.000 $33,700.000 $30,000.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 24.000 $442.880 $760.000 $550.000 $863.000 $1,100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 104.000 $26.760 $44.000 $42.530 $16.000 $100.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
EA 239.000 $21.670 $15.000 $24.300 $20.000 $100.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 3.000 $5,265.000 $16,200.000 $10,000.000 $6,800.000 $12,500.000
TMA (STATIONARY)
DAY 60.000 $189.510 $750.000 $250.000 $475.000 $250.000
1
D-GR HMA TY-B PG64-22
TON 11,532.000 $145.000 $115.000 $131.370 $127.000 $140.000
1
TACK COAT
GAL 2,107.000 $9.060 $5.000 $4.560 $5.000 $10.000
1A
RIPRAP CONC (8 IN)
CY 4,654.320 $363.370 $0.000 $0.000 $0.000 $0.000
Totals: $6,052,951.768 $4,600,000.000 $4,899,781.910 $4,992,609.010 $5,736,771.000