BASTROP VARIOUS (0914-18-119)

Items: 30

County: BASTROP
Length: 0.0000 MILES
Highway: VARIOUS
District: AUSTIN
Control Number: 0914-18-119
DBE Goal: 0.0%
Project: C 914-18-119
Guaranty: $18,000.00
Time: 72 WORKING DAYS
Engineer's Estimate: $880,992.30
Date: 10/09/2025 (8 months ago)
Contract Number: 10253226
Type: DRAINAGE IMPROVEMENTS
Project ID: A00185000
Project Description: REPAIR LOW WATER CROSSINGS AT VARIOUS LOCATIONS IN BASTROP STATE PARK
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DIANA SCHULZE
SHANE SWIMM
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (8)
E
Engineer's Estimate
$880,992.30
1
Awarded
$846,903.00
Over/Under Est: -3.87% -$34,089.30
Over/Under Est: -3.1% -$27,295.86
Amt Left: 0.8% $6,793.44
$855,910.35
Over/Under Est: -2.85% -$25,081.95
Amt Left: 1.06% $9,007.35
Delta: -0.26% -$2,213.91
$862,932.63
Over/Under Est: -2.05% -$18,059.67
Amt Left: 1.89% $16,029.63
Delta: -0.82% -$7,022.28
Over/Under Est: 3.93% $34,630.70
Amt Left: 8.11% $68,720.00
Delta: -6.11% -$52,690.37
$1,012,867.00
Over/Under Est: 14.97% $131,874.70
Amt Left: 19.6% $165,964.00
Delta: -10.62% -$97,244.00
Over/Under Est: 23.32% $205,478.50
Amt Left: 28.29% $239,567.80
Delta: -7.27% -$73,603.80
Over/Under Est: 30.31% $267,063.70
Amt Left: 35.56% $301,153.00
Delta: -5.67% -$61,585.20

Bid Items & Bid Tabulations

30 Total 0 of 30
BASTROP  |  VARIOUS  |  AUSTIN  |  0914-18-119  |  10/09/2025  |  $880,992.30  |  C 914-18-119  |  DRAINAGE IMPRVS  |  72 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STX CIVIL
BECK-REIT & SONS, LTD.
RELMCO, INC.
C. E. BARKER, LTD.
DAN WILLIAMS COMPANY
AAD CONTRACTING INC.
AARON CONCRETE CONTRACTORS, LLC
GARRET SHIELDS INFRASTRUCTURE
PREPARING ROW
AC 8.700 $20,000.000 $19,200.000 $4,200.000 $10,000.000 $9,750.000 $6,000.000 $10,000.000 $10,000.000 $5,000.000
REMOV CONC (WINGWALL)
CY 7.000 $550.000 $750.000 $400.000 $800.000 $504.000 $450.000 $2,000.000 $330.000 $1,000.000
REMOV CONC (INTER ART CONC BLOCKS)
SY 1,081.000 $7.300 $5.000 $11.000 $15.000 $19.600 $35.000 $28.000 $22.000 $30.000
EXCAV (ROADWAY)
CY 355.700 $40.000 $30.000 $35.000 $80.000 $35.000 $90.000 $20.000 $65.000 $40.000
EMBANK (FNL)(OC)(TY C)
CY 330.700 $60.000 $40.000 $45.000 $80.000 $35.000 $175.000 $60.000 $144.000 $40.000
FURN & PLACE TOPSOIL (4")
SY 1,455.000 $5.000 $4.000 $7.770 $8.000 $3.920 $3.500 $10.000 $25.000 $6.000
BROADCAST SEED (PERM_RURAL_SAND)
SY 1,455.000 $1.000 $3.000 $1.770 $2.200 $2.240 $2.000 $2.000 $2.400 $3.000
SOIL RET BLKT(SL_MOD_SAND_WLDLFE)
SY 1,455.000 $2.000 $6.000 $5.000 $5.750 $5.600 $5.300 $5.000 $6.200 $3.000
FLOWABLE BACKFILL
CY 9.000 $550.000 $375.000 $600.000 $300.000 $198.800 $550.000 $300.000 $320.000 $500.000
TRENCH EXCAVATION PROTECTION
LF 80.000 $25.000 $25.000 $1.000 $30.000 $61.600 $2.000 $30.000 $13.000 $10.000
RIPRAP (STONE COMMON)(DRY)(8 IN)
CY 659.100 $170.000 $180.000 $155.000 $165.000 $194.600 $235.000 $180.000 $215.000 $200.000
GABIONS (GALV)
CY 20.600 $600.000 $560.000 $210.000 $350.000 $591.920 $700.000 $300.000 $475.000 $300.000
CONC BOX CULV (3 FT X 3 FT)
LF 72.000 $450.000 $500.000 $488.000 $796.600 $543.480 $600.000 $500.000 $600.000 $600.000
CONC BOX CULV (4 FT X 2 FT)
LF 62.000 $475.000 $520.000 $710.000 $784.000 $537.990 $600.000 $600.000 $620.000 $700.000
CONC BOX CULV (6 FT X 5 FT)
LF 50.000 $800.000 $850.000 $1,077.000 $882.000 $838.260 $1,180.000 $1,000.000 $1,200.000 $1,500.000
RC PIPE (CL III)(18 IN)
LF 123.000 $120.000 $125.000 $118.000 $140.000 $164.080 $175.000 $90.000 $374.000 $100.000
RC PIPE (CL III)(24 IN)
LF 42.000 $185.000 $140.000 $124.000 $172.200 $177.300 $215.000 $110.000 $455.000 $150.000
WINGWALL (FW - 0) (HW=7 FT)
EA 2.000 $22,500.000 $17,000.000 $13,000.000 $12,500.000 $32,816.000 $17,500.000 $25,000.000 $14,000.000 $15,000.000
WINGWALL (SW - 0) (HW=6 FT)
EA 2.000 $17,300.000 $15,000.000 $12,000.000 $12,500.000 $32,480.000 $17,500.000 $20,000.000 $14,000.000 $15,000.000
CLEAN EXIST CULVERTS
EA 12.000 $3,000.000 $3,500.000 $300.000 $3,500.000 $1,176.000 $1,300.000 $2,000.000 $1,800.000 $5,000.000
REMOV STR (PIPE)
LF 165.000 $28.000 $18.000 $30.000 $30.000 $44.800 $35.000 $90.000 $152.000 $50.000
REMOV STR (BOX CULVERT)
LF 184.000 $165.000 $100.000 $50.000 $50.000 $64.400 $45.000 $75.000 $205.000 $50.000
REMOVE STR (GABION)
LF 100.000 $125.000 $30.000 $35.000 $40.000 $35.000 $12.000 $60.000 $73.000 $80.000
MOBILIZATION
LS 1.000 $86,000.000 $65,000.000 $67,000.000 $75,000.000 $76,500.000 $90,000.000 $50,000.000 $100,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $2,000.000 $4,000.000 $1,100.000 $4,000.000 $8,120.000 $7,500.000 $10,000.000 $760.000 $5,000.000
ROCK FILTER DAMS (INSTALL) (TY 4)
LF 600.000 $52.000 $50.000 $22.000 $60.500 $56.000 $55.000 $24.000 $65.000 $40.000
ROCK FILTER DAMS (REMOVE)
LF 600.000 $12.000 $10.000 $5.000 $13.200 $22.400 $12.000 $1.000 $14.000 $10.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,020.000 $6.600 $8.000 $4.000 $6.050 $22.400 $5.500 $4.500 $6.500 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,020.000 $2.000 $2.000 $1.000 $1.100 $11.200 $1.000 $1.000 $1.200 $1.000
INTRLCK ART CONC BLKS
SF 9,728.000 $9.000 $10.000 $33.330 $12.000 $5.880 $10.000 $30.000 $19.000 $40.000
Totals: $880,992.300 $846,903.000 $853,696.440 $855,910.350 $862,932.632 $915,623.000 $1,012,867.000 $1,086,470.800 $1,148,056.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,000.00
Total: $2,000.00