BASTROP FM 20 (0115-04-055)
Items: 75
County: BASTROP
Length: N/A
Highway: FM 20
District: AUSTIN
Control Number: 0115-04-055
DBE Goal: N/A
Project: BR 2022(642)
Guaranty: N/A
Time: 153 WORKING DAYS
Engineer's Estimate: $1,662,058.34
Date: 06/02/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
DIANA SCHULZE
TANLI SUN
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,662,058.34 | |||
| $2,547,556.20 |
53.28%
$885,497.86
|
|||
| $2,549,144.60 |
53.37%
$887,086.26
|
0.06%
$1,588.40
|
||
| $2,595,807.15 |
56.18%
$933,748.81
|
1.89%
$48,250.95
|
-1.83%
-$46,662.55
|
|
| $2,669,802.31 |
60.63%
$1,007,743.97
|
4.8%
$122,246.11
|
-2.85%
-$73,995.16
|
|
| $2,698,375.65 |
62.35%
$1,036,317.31
|
5.92%
$150,819.45
|
-1.07%
-$28,573.34
|
|
| $2,847,366.61 |
71.32%
$1,185,308.27
|
11.77%
$299,810.41
|
-5.52%
-$148,990.96
|
|
| $3,154,265.57 |
89.78%
$1,492,207.23
|
23.82%
$606,709.37
|
-10.78%
-$306,898.96
|
E
Engineer's Estimate
$1,662,058.34
1
Awarded
$2,547,556.20
Over/Under Est:
53.28%
$885,497.86
$2,549,144.60
Over/Under Est:
53.37%
$887,086.26
Amt Left:
0.06%
$1,588.40
$2,595,807.15
Over/Under Est:
56.18%
$933,748.81
Amt Left:
1.89%
$48,250.95
Delta:
-1.83%
-$46,662.55
$2,669,802.31
Over/Under Est:
60.63%
$1,007,743.97
Amt Left:
4.8%
$122,246.11
Delta:
-2.85%
-$73,995.16
$2,698,375.65
Over/Under Est:
62.35%
$1,036,317.31
Amt Left:
5.92%
$150,819.45
Delta:
-1.07%
-$28,573.34
$2,847,366.61
Over/Under Est:
71.32%
$1,185,308.27
Amt Left:
11.77%
$299,810.41
Delta:
-5.52%
-$148,990.96
$3,154,265.57
Over/Under Est:
89.78%
$1,492,207.23
Amt Left:
23.82%
$606,709.37
Delta:
-10.78%
-$306,898.96