AUSTIN SH 36 (0187-02-074)

Items: 19

County: AUSTIN
Length: 3.4280 MILES
Highway: SH 36
District: YOAKUM
Control Number: 0187-02-074
DBE Goal: 0.0%
Project: STP 2026(574)HES
Guaranty: $14,000.00
Time: 25 WORKING DAYS
Engineer's Estimate: $652,746.15
Date: 05/07/2026 (4 weeks ago) Changed
Contract Number: 5263034
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00206480
Contract Type: Federal
Project Description: INSTALL MEDIAN BARRIER - HSIP
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
RYAN SIMPER
JEFFREY KALINA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$652,746.15
$559,612.36
Over/Under Est: -14.27% -$93,133.79
Over/Under Est: -7.05% -$46,025.71
Amt Left: 8.42% $47,108.08
$628,004.20
Over/Under Est: -3.79% -$24,741.95
Amt Left: 12.22% $68,391.84
Delta: -3.51% -$21,283.76
Over/Under Est: -0.69% -$4,517.55
Amt Left: 15.84% $88,616.24
Delta: -3.22% -$20,224.40

Bid Items & Bid Tabulations

19 Total 0 of 19
AUSTIN  |  SH 36  |  YOAKUM  |  0187-02-074  |  05/07/2026  |  $652,746.15  |  STP 2026(574)HES  |  HAZARD ELIM & SAFETY  |  25 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ROADWAY SPECIALTIES, INC.
SCR CIVIL CONSTRUCTION, LLC
HJC FARMS, INC.
GRATIOT CONSTRUCTION, LTD.
EMBANK (VEH)(OC)(TY C)
CY 250.000 $50.000 $50.710 $26.000 $100.000 $21.000
BLADING
HR 12.000 $150.000 $221.250 $550.000 $400.000 $70.000
BROADCAST SEED (PERM_RURAL_CLAY)
AC 6.340 $1,500.000 $1,169.700 $1,880.000 $750.000 $250.000
BROADCAST SEED (TEMP_WARM)
AC 1.590 $1,200.000 $997.460 $1,200.000 $200.000 $100.000
BROADCAST SEED (TEMP_COOL)
AC 1.590 $1,200.000 $982.990 $1,000.000 $200.000 $100.000
VEGETATIVE WATERING
TGL 172.460 $40.000 $84.700 $61.000 $50.000 $5.000
RIPRAP (MOW STRIP)(4 IN)
CY 681.390 $450.000 $302.130 $410.000 $480.000 $470.000
MOBILIZATION
LS 1.000 $65,000.000 $83,502.500 $60,600.000 $42,800.000 $55,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $3,500.000 $2,703.120 $6,000.000 $3,100.000 $10,000.000
TMA (STATIONARY)
DAY 20.000 $250.000 $250.000 $340.000 $150.000 $100.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 445.000 $7.000 $3.030 $6.000 $8.000 $8.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 445.000 $1.250 $0.440 $2.300 $1.000 $2.000
CABLE BARRIER SYSTEM (INSTALL)(TL-4)
LF 13,198.000 $12.500 $11.240 $11.110 $12.500 $15.000
CABLE BARRIER TERM SEC (INSTL)(TL-4)
EA 12.000 $2,500.000 $2,749.360 $2,600.000 $3,000.000 $2,250.000
REPLACE POSTS (TL-4)(GIBRALTAR)
EA 100.000 $150.000 $66.240 $230.000 $1.000 $50.000
CABLE SPLICE / TURNBUCKLE (TL-4)
EA 6.000 $950.000 $265.050 $115.000 $1.000 $200.000
REPAIR CONCRETE FOUNDATION (TL-4)
EA 6.000 $650.000 $738.940 $100.000 $1.000 $200.000
REPR OR REPLC CABLE BARR TERM SEC(TL-4)
EA 6.000 $1,750.000 $3,316.610 $500.000 $1.000 $850.000
REPLACE CABLE (TL-4)
LF 100.000 $8.500 $39.010 $1.000 $0.250 $2.000
Totals: $652,746.150 $559,612.366 $606,720.440 $628,004.200 $648,228.600
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $500.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
Total: $11,500.00