ATASCOSA US0281 (6477-02-001)
Items: 7
County: ATASCOSA
Length: 0.0100 MILES
Highway: US0281
District: SAN ANTONIO
Control Number: 6477-02-001
DBE Goal: N/A
Project: BPM - A00212920
Guaranty: $2,000.00
Time: 48 WORKING DAYS
Engineer's Estimate: $105,150.00
Date: 02/20/2025 (1 year ago)
Contract Number: 2251514
Type: BRIDGE PREVENTATIVE MAINTENANCE
Project ID: A00212920
Project Description: CONCRETE REPAIR ON VARIOUS BRIDGE AND BRIDGE CLASS CULVERTS IN ATASCOSA COUNTY.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: MAINTENANCE CONTRACT OFFICE
4615 NW LOOP 410, SAN ANTONIO, TX 78229
HENRY FOJTIK
ATASCOSA US0281 (6477-02-001)
Project Name: N/A
Project: BPM - A00212920
Length: 0.0100 MILES
Project Type: MAINTENANCE
Limits From: US 281, ETC
Limits To: IH 37, ETC
Project Description: CONCRETE REPAIR ON VARIOUS BRIDGE AND BRIDGE CLASS CULVERTS IN ATASCOSA COUNTY.
Informational
Bidders (14)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$105,150.00 | |||
| $67,357.00 |
-35.94%
-$37,793.00
|
|||
| $84,682.00 |
-19.47%
-$20,468.00
|
25.72%
$17,325.00
|
||
| $86,555.00 |
-17.68%
-$18,595.00
|
28.5%
$19,198.00
|
-2.21%
-$1,873.00
|
|
| $95,631.00 |
-9.05%
-$9,519.00
|
41.98%
$28,274.00
|
-10.49%
-$9,076.00
|
|
| $105,060.00 |
-0.09%
-$90.00
|
55.97%
$37,703.00
|
-9.86%
-$9,429.00
|
|
| $117,800.00 |
12.03%
$12,650.00
|
74.89%
$50,443.00
|
-12.13%
-$12,740.00
|
|
| $118,550.00 |
12.74%
$13,400.00
|
76%
$51,193.00
|
-0.64%
-$750.00
|
|
| $129,460.00 |
23.12%
$24,310.00
|
92.2%
$62,103.00
|
-9.20%
-$10,910.00
|
|
| $134,180.00 |
27.61%
$29,030.00
|
99.21%
$66,823.00
|
-3.65%
-$4,720.00
|
|
| $134,323.00 |
27.74%
$29,173.00
|
99.42%
$66,966.00
|
-0.11%
-$143.00
|
|
| $140,225.00 |
33.36%
$35,075.00
|
108.18%
$72,868.00
|
-4.39%
-$5,902.00
|
|
| $141,638.00 |
34.7%
$36,488.00
|
110.28%
$74,281.00
|
-1.01%
-$1,413.00
|
|
|
13
|
$172,630.00 |
64.17%
$67,480.00
|
156.29%
$105,273.00
|
-21.88%
-$30,992.00
|
|
14
|
$211,400.00 |
101.05%
$106,250.00
|
213.85%
$144,043.00
|
-22.46%
-$38,770.00
|
E
Engineer's Estimate
$105,150.00
1
Awarded
$67,357.00
Over/Under Est:
-35.94%
-$37,793.00
$84,682.00
Over/Under Est:
-19.47%
-$20,468.00
Amt Left:
25.72%
$17,325.00
$86,555.00
Over/Under Est:
-17.68%
-$18,595.00
Amt Left:
28.5%
$19,198.00
Delta:
-2.21%
-$1,873.00
$95,631.00
Over/Under Est:
-9.05%
-$9,519.00
Amt Left:
41.98%
$28,274.00
Delta:
-10.49%
-$9,076.00
$105,060.00
Over/Under Est:
-0.09%
-$90.00
Amt Left:
55.97%
$37,703.00
Delta:
-9.86%
-$9,429.00
$117,800.00
Over/Under Est:
12.03%
$12,650.00
Amt Left:
74.89%
$50,443.00
Delta:
-12.13%
-$12,740.00
$118,550.00
Over/Under Est:
12.74%
$13,400.00
Amt Left:
76%
$51,193.00
Delta:
-0.64%
-$750.00
$129,460.00
Over/Under Est:
23.12%
$24,310.00
Amt Left:
92.2%
$62,103.00
Delta:
-9.20%
-$10,910.00
$134,180.00
Over/Under Est:
27.61%
$29,030.00
Amt Left:
99.21%
$66,823.00
Delta:
-3.65%
-$4,720.00
$134,323.00
Over/Under Est:
27.74%
$29,173.00
Amt Left:
99.42%
$66,966.00
Delta:
-0.11%
-$143.00
$140,225.00
Over/Under Est:
33.36%
$35,075.00
Amt Left:
108.18%
$72,868.00
Delta:
-4.39%
-$5,902.00
$141,638.00
Over/Under Est:
34.7%
$36,488.00
Amt Left:
110.28%
$74,281.00
Delta:
-1.01%
-$1,413.00
13
$172,630.00
Over/Under Est:
64.17%
$67,480.00
Amt Left:
156.29%
$105,273.00
Delta:
-21.88%
-$30,992.00
14
$211,400.00
Over/Under Est:
101.05%
$106,250.00
Amt Left:
213.85%
$144,043.00
Delta:
-22.46%
-$38,770.00
| Subcontractor | Percentage | Amount |
|---|---|---|
| W-TEX SERVICES LLC | 0.00% | $0.00 |
| Total: | 0.00% | $0.00 |
Bid Items & Bid Tabulations
7
Total
0 of 7