Bid Cobra

ATASCOSA US0281 (6376-06-001)

Items: 21

County: ATASCOSA
Length: N/A
Highway: US0281
District: SAN ANTONIO
Control Number: 6376-06-001
DBE Goal: N/A
Project: BPM - 637606001
Guaranty: N/A
Time: 19 WORKING DAYS
Engineer's Estimate: $109,614.15
Date: 03/17/2021 (5 years ago)
Contract Number: N/A
Type: RIPRAP REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (13)
E
Engineer's Estimate
$109,614.15
$99,804.00
Over/Under Est: -8.95% -$9,810.15
Over/Under Est: -5.08% -$5,564.15
Amt Left: 4.25% $4,246.00
$104,066.24
Over/Under Est: -5.06% -$5,547.91
Amt Left: 4.27% $4,262.24
Delta: -0.02% -$16.24
$105,304.00
Over/Under Est: -3.93% -$4,310.15
Amt Left: 5.51% $5,500.00
Delta: -1.19% -$1,237.76
Over/Under Est: -1.66% -$1,819.15
Amt Left: 8.01% $7,991.00
Delta: -2.37% -$2,491.00
Over/Under Est: -0.16% -$172.40
Amt Left: 9.66% $9,637.75
Delta: -1.53% -$1,646.75
Over/Under Est: 0.56% $609.85
Amt Left: 10.44% $10,420.00
Delta: -0.71% -$782.25
Over/Under Est: 1.83% $2,003.45
Amt Left: 11.84% $11,813.60
Delta: -1.26% -$1,393.60
Over/Under Est: 14.56% $15,964.85
Amt Left: 25.83% $25,775.00
Delta: -12.51% -$13,961.40
Over/Under Est: 20.54% $22,511.85
Amt Left: 32.39% $32,322.00
Delta: -5.21% -$6,547.00
Over/Under Est: 47.88% $52,482.85
Amt Left: 62.42% $62,293.00
Delta: -22.68% -$29,971.00
Over/Under Est: 62.82% $68,863.61
Amt Left: 78.83% $78,673.76
Delta: -10.11% -$16,380.76
Over/Under Est: 85.49% $93,709.85
Amt Left: 103.72% $103,520.00
Delta: -13.92% -$24,846.24

Bid Items & Bid Tabulations

21 Total 0 of 21
ATASCOSA  |  US0281  |  SAN ANTONIO  |  6376-06-001  |  03/17/2021  |  $109,614.15  |  BPM - 637606001  |  RIPRAP REPAIR  |  19 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DBI SERVICES, LLC
DELGADO'S CONTRACTORS, LLC
MPB, INC.
3LW CIVIL LLC
BLACKSMITH VENTURES LLC
K-BAR SERVICES, INC.
SJ&J CONSTRUCTION, LLC
TASCOSA BRIDGE CO., LC
DOUBLE L CONTRACTING, LLC
BECK-REIT & SONS, LTD.
TIERRA LEASE SERVICE, LLC
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 1.000 $2,000.000 $2,000.000 $1,500.000 $1,650.000 $1,500.000 $2,000.000 $1,000.000 $1,500.000 $8,500.000 $10,000.000 $7,500.000 $3,000.000 $4,945.830 $15,000.000
REMOVING CONC (RIPRAP)
CY 6.000 $85.000 $300.000 $150.000 $100.000 $145.000 $170.000 $60.000 $100.000 $75.000 $1,250.000 $500.000 $250.000 $258.870 $350.000
EMBANKMENT (ORIGINAL)(ORD COMP)(TY B)
CY 20.000 $30.000 $50.000 $25.000 $95.000 $30.000 $50.000 $5.000 $25.000 $150.000 $175.000 $100.000 $100.000 $244.590 $150.000
COMPOST MANUF TOPSOIL (4")
SY 420.000 $1.250 $5.000 $3.000 $4.500 $4.250 $4.000 $4.000 $4.000 $2.500 $12.000 $7.000 $10.000 $4.910 $25.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 420.000 $1.000 $1.000 $1.500 $1.600 $1.500 $4.000 $4.000 $1.000 $3.000 $0.500 $2.500 $4.000 $1.880 $3.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 420.000 $2.000 $10.000 $2.000 $2.400 $2.250 $4.000 $6.000 $3.500 $2.200 $6.500 $5.000 $4.000 $4.820 $6.500
FLOWABLE BACKFILL
CY 290.000 $190.000 $105.000 $145.000 $165.000 $140.000 $130.000 $103.000 $160.000 $145.000 $110.000 $155.000 $275.000 $204.800 $250.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 19.000 $485.000 $450.000 $500.000 $400.000 $570.000 $600.000 $405.000 $500.000 $500.000 $600.000 $1,000.000 $650.000 $1,273.320 $650.000
RIPRAP (MOW STRIP)(4 IN)
CY 18.000 $435.000 $400.000 $430.000 $550.000 $440.000 $600.000 $405.000 $500.000 $525.000 $600.000 $1,000.000 $675.000 $1,217.340 $650.000
MOBILIZATION
LS 1.000 $6,608.400 $25,000.000 $15,000.000 $5,000.000 $15,000.000 $11,000.000 $16,455.000 $13,000.000 $8,346.000 $10,000.000 $15,000.000 $15,000.000 $19,208.250 $20,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $4,300.000 $1,500.000 $1,500.000 $3,000.000 $2,600.000 $3,000.000 $4,150.000 $5,000.000 $3,040.000 $500.000 $200.000 $4,000.000 $955.900 $8,500.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 542.000 $4.000 $6.000 $5.000 $3.670 $3.500 $4.000 $7.000 $3.000 $5.500 $1.000 $2.000 $8.000 $4.030 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 542.000 $2.000 $1.000 $2.000 $1.050 $1.000 $1.000 $0.750 $1.500 $1.000 $1.000 $1.000 $3.000 $1.280 $9.000
MTL W-BEAM GD FEN (TIM POST)
LF 125.000 $15.000 $27.000 $32.000 $25.200 $24.000 $35.000 $30.000 $31.000 $31.460 $125.000 $28.000 $24.000 $27.190 $25.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 1.000 $1,500.000 $2,000.000 $2,500.000 $2,027.000 $1,930.000 $1,600.000 $1,400.000 $1,900.000 $1,810.500 $500.000 $3,500.000 $1,750.000 $2,221.560 $1,850.000
MTL BM GD FEN TRANS (ANCHOR PLATE)
EA 1.000 $500.000 $850.000 $700.000 $1,000.000 $950.000 $1,000.000 $56.000 $830.000 $960.000 $500.000 $500.000 $1,200.000 $1,143.560 $1,850.000
REMOVE METAL BEAM GUARD FENCE
LF 125.000 $2.750 $5.000 $3.000 $2.100 $2.000 $4.000 $4.250 $2.000 $1.000 $62.000 $8.000 $7.000 $2.990 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $145.000 $400.000 $261.000 $157.500 $150.000 $250.000 $54.000 $160.000 $100.000 $1,000.000 $400.000 $700.000 $263.560 $500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $2,550.000 $3,000.000 $3,500.000 $2,841.000 $2,705.000 $3,000.000 $3,400.000 $2,700.000 $2,756.600 $5,000.000 $2,800.000 $700.000 $3,074.060 $2,850.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 20.000 $100.000 $1.000 $75.000 $100.000 $200.000 $120.000 $55.000 $100.000 $90.000 $1.000 $133.000 $55.000 $129.710 $150.000
TMA (STATIONARY)
DAY 20.000 $260.000 $1.000 $225.000 $300.000 $200.000 $300.000 $900.000 $100.000 $300.000 $1.000 $10.000 $275.000 $982.300 $350.000
Totals: $109,614.150 $99,804.000 $104,050.000 $104,066.240 $105,304.000 $107,795.000 $109,441.750 $110,224.000 $111,617.600 $125,579.000 $132,126.000 $162,097.000 $178,477.760 $203,324.000