ATASCOSA SH 16 (0613-02-063)

Items: 96

County: ATASCOSA
Length: N/A
Highway: SH 16
District: SAN ANTONIO
Control Number: 0613-02-063
DBE Goal: N/A
Project: C 613-2-63
Guaranty: N/A
Time: 252 WORKING DAYS
Engineer's Estimate: $5,215,909.88
Date: 05/02/2018 (8 years ago)
Contract Number: N/A
Type: REPLACE EXISTING BRIDGE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (11)
E
Engineer's Estimate
$5,215,909.88
$5,704,330.28
Over/Under Est: 9.36% $488,420.40
$5,734,991.80
Over/Under Est: 9.95% $519,081.92
Amt Left: 0.54% $30,661.52
$5,755,176.68
Over/Under Est: 10.34% $539,266.80
Amt Left: 0.89% $50,846.40
Delta: -0.35% -$20,184.88
Over/Under Est: 10.67% $556,626.38
Amt Left: 1.2% $68,205.98
Delta: -0.30% -$17,359.58
$5,846,460.94
Over/Under Est: 12.09% $630,551.06
Amt Left: 2.49% $142,130.66
Delta: -1.28% -$73,924.68
$6,096,562.73
Over/Under Est: 16.88% $880,652.85
Amt Left: 6.88% $392,232.45
Delta: -4.28% -$250,101.79
Over/Under Est: 33.43% $1,743,767.79
Amt Left: 22.01% $1,255,347.39
Delta: -14.16% -$863,114.94
Over/Under Est: 36.04% $1,880,033.16
Amt Left: 24.4% $1,391,612.76
Delta: -1.96% -$136,265.37
Over/Under Est: 36.72% $1,915,380.37
Amt Left: 25.02% $1,426,959.97
Delta: -0.50% -$35,347.21
Over/Under Est: 38.64% $2,015,267.55
Amt Left: 26.77% $1,526,847.15
Delta: -1.40% -$99,887.18
Over/Under Est: 43.71% $2,279,892.56
Amt Left: 31.41% $1,791,472.16
Delta: -3.66% -$264,625.01

Bid Items & Bid Tabulations

96 Total 0 of 96
ATASCOSA  |  SH 16  |  SAN ANTONIO  |  0613-02-063  |  05/02/2018  |  $5,215,909.88  |  C 613-2-63  |  REPLACE EXIST BRIDGE  |  252 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HARPER BROTHERS CONSTRUCTION LLC
DAN WILLIAMS COMPANY
J3 COMPANY, LLC
CAPITAL EXCAVATION COMPANY
RELMCO, INC.
SB CONTRACTORS LLC
ANDERSON COLUMBIA CO., INC.
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
JORDAN FOSTER CONSTRUCTION, LLC
ANGEL BROTHERS HOLDINGS CORP.
AUSTIN BRIDGE & ROAD SERVICES, LP
PREPARING ROW
STA 25.200 $500.000 $11,300.000 $2,500.000 $4,000.000 $2,000.000 $1,600.000 $1,000.000 $1,720.000 $576.660 $2,500.000 $13,000.000 $2,540.000
REMOVING CONC (RIPRAP)
SY 1,206.000 $10.000 $2.000 $5.000 $10.000 $8.000 $8.510 $14.000 $10.000 $7.670 $5.000 $9.000 $11.000
OBLITERATING ABANDONED ROAD
STA 21.410 $1,368.000 $1,250.000 $1,150.000 $1,500.000 $1,000.000 $1,402.500 $1,000.000 $260.000 $4,397.250 $1,200.000 $900.000 $2,000.000
EXCAVATION (ROADWAY)
CY 11,216.000 $8.860 $9.000 $7.500 $8.000 $7.000 $5.940 $14.000 $9.000 $5.000 $6.000 $9.000 $9.000
EXCAVATION (CHANNEL)
CY 4,327.000 $13.100 $7.000 $7.500 $10.000 $6.000 $8.110 $5.000 $12.000 $5.520 $11.000 $12.000 $17.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 13,369.000 $9.000 $18.000 $7.500 $5.000 $4.000 $9.240 $12.000 $19.000 $4.170 $7.000 $15.000 $30.000
FURNISHING AND PLACING TOPSOIL (3")
SY 29,501.000 $0.750 $0.600 $1.000 $1.000 $1.000 $0.460 $2.750 $0.320 $2.150 $2.500 $0.900 $2.000
GENERAL USE COMPOST (2")
SY 33,785.000 $1.500 $1.100 $1.100 $1.000 $1.000 $1.250 $1.200 $1.100 $3.190 $2.000 $1.200 $1.100
MULCH SODDING
SY 3,460.000 $4.000 $4.750 $4.800 $4.000 $4.750 $3.140 $7.000 $5.000 $6.770 $4.750 $4.000 $4.750
BROADCAST SEED (PERM) (URBAN) (SANDY)
SY 841.000 $0.500 $0.140 $0.150 $0.160 $0.140 $0.170 $1.140 $0.140 $0.200 $0.200 $0.160 $0.140
STRAW/HAY MLCH SEED(PERM)(RURAL)(SANDY)
SY 18,818.000 $0.260 $0.780 $0.800 $0.800 $0.780 $0.840 $0.900 $0.800 $0.530 $0.800 $0.800 $0.780
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 10,684.000 $0.200 $0.140 $0.150 $0.160 $0.140 $0.170 $0.200 $0.140 $0.210 $0.200 $0.160 $0.140
BROADCAST SEED (TEMP)(WARM OR COOL)
SY 33,785.000 $0.200 $0.120 $0.120 $0.120 $0.120 $0.130 $0.200 $0.120 $0.110 $0.150 $0.120 $0.120
FERTILIZER
AC 7.040 $145.000 $180.000 $180.000 $300.000 $180.000 $315.000 $350.000 $184.000 $498.260 $300.000 $300.000 $180.000
VEGETATIVE WATERING
MG 527.700 $12.000 $20.000 $8.000 $24.970 $5.000 $20.000 $30.000 $26.000 $38.630 $10.000 $18.000 $35.000
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 4,512.000 $0.910 $0.820 $0.850 $1.200 $0.820 $1.260 $1.200 $0.850 $1.530 $1.200 $1.200 $0.820
SOIL RETENTION BLANKETS (CL 1) (TY D)
SY 6,171.000 $1.250 $0.820 $0.850 $1.200 $0.820 $1.260 $1.200 $0.850 $1.820 $1.200 $1.200 $0.820
SOIL RETENTION BLANKETS (CL 2) (TY F)
SY 841.000 $4.230 $1.750 $1.800 $1.650 $1.750 $1.730 $6.500 $2.000 $1.900 $1.700 $1.650 $1.750
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 2,214.000 $30.000 $45.000 $40.000 $42.920 $49.000 $52.420 $50.000 $44.000 $62.530 $59.000 $52.000 $45.000
CEMENT
TON 122.000 $130.000 $162.040 $136.000 $140.000 $130.000 $185.690 $143.000 $150.000 $161.640 $150.000 $180.000 $180.000
CEMENT TREAT (NEW BASE) (7.5")
SY 10,619.000 $2.000 $2.200 $1.850 $3.000 $1.500 $1.500 $4.000 $3.300 $2.730 $4.250 $2.200 $3.000
PRIME COAT (MC-30)
GAL 2,126.000 $3.870 $2.900 $2.900 $2.870 $3.000 $6.450 $4.000 $5.000 $3.800 $3.500 $5.300 $5.500
AGGR (TY-B GR-4)
CY 203.000 $38.000 $75.500 $80.000 $75.500 $79.000 $150.200 $76.000 $100.000 $129.830 $75.000 $120.000 $130.000
ASPH(AC-15P,AC-20-5TR,AC-20XP,AC10-2TR)
GAL 6,377.000 $2.500 $2.600 $2.750 $2.550 $2.750 $3.500 $3.000 $3.500 $3.700 $2.750 $3.500 $3.700
D-GR HMA(SQ)TY-B OR D PG64-22(LVL-UP)
TON 44.000 $85.340 $93.000 $95.000 $100.000 $97.000 $202.830 $100.000 $160.000 $245.730 $105.000 $140.000 $150.000
D-GR HMA TY-B PG64-22
TON 3,429.000 $60.000 $55.000 $60.000 $55.000 $58.000 $77.230 $67.500 $78.000 $87.000 $69.000 $72.000 $74.000
SUPERPAVE MIXTURES SP-C SAC-A PG76-22
TON 2,420.000 $75.000 $73.000 $75.000 $73.000 $77.000 $102.050 $81.000 $85.000 $102.930 $81.000 $90.000 $92.000
PLANE ASPH CONC PAV (2")
SY 10,863.000 $1.000 $2.500 $1.650 $2.500 $2.020 $4.350 $2.100 $2.000 $2.990 $3.000 $1.400 $2.000
CEM STABIL BKFL
CY 41.000 $100.000 $131.000 $145.000 $125.000 $140.000 $103.430 $140.000 $160.000 $113.740 $125.000 $175.000 $200.000
TEMPORARY SPL SHORING
SF 1,785.000 $12.000 $22.000 $8.000 $40.000 $10.000 $25.530 $22.000 $36.000 $22.430 $20.000 $25.000 $1.000
DRILL SHAFT (18 IN)
LF 720.000 $65.000 $47.000 $80.000 $60.000 $76.000 $54.600 $83.000 $46.000 $174.450 $48.500 $100.000 $60.000
DRILL SHAFT (36 IN)
LF 13,123.000 $125.000 $139.780 $145.000 $155.000 $161.000 $157.000 $129.000 $178.000 $171.190 $163.000 $151.000 $180.000
DRILL SHAFT (48 IN)
LF 720.000 $207.950 $235.000 $235.000 $250.000 $249.000 $365.750 $205.000 $275.000 $347.430 $295.000 $350.000 $275.000
CL C CONC (ABUT)
CY 106.000 $800.000 $650.000 $750.000 $750.000 $730.000 $712.470 $550.000 $866.000 $882.110 $780.000 $1,000.000 $1,310.000
CL C CONC (CAP)
CY 59.750 $900.000 $875.000 $850.000 $750.000 $725.000 $788.290 $850.000 $1,080.000 $1,027.910 $1,600.000 $1,000.000 $1,055.000
CL C CONC (COLUMN)
CY 16.000 $870.000 $920.000 $1,000.000 $750.000 $800.000 $1,166.370 $1,200.000 $1,150.000 $1,411.520 $1,300.000 $1,200.000 $1,465.000
REINF CONC SLAB
SF 16,920.000 $12.860 $18.000 $15.250 $15.000 $14.000 $13.740 $15.000 $19.000 $20.380 $19.500 $18.000 $18.000
APPROACH SLAB
CY 153.500 $400.000 $345.000 $385.000 $500.000 $485.000 $635.180 $315.000 $350.000 $541.930 $500.000 $520.000 $500.000
SHEAR KEY
CY 1.900 $281.410 $1,900.000 $650.000 $2,000.000 $1,702.820 $1,025.140 $400.000 $3,900.000 $2,770.040 $375.000 $1,200.000 $1,935.000
RETAINING WALL (DRILL SHAFT) (FACIA)
SF 10,173.000 $49.000 $24.850 $42.000 $40.000 $40.000 $24.230 $50.000 $51.000 $30.780 $69.000 $64.000 $50.000
PRESTR CONC GIRDER (TX54)
LF 2,150.000 $106.000 $215.500 $135.000 $126.000 $136.000 $153.770 $150.000 $150.000 $153.660 $133.500 $170.000 $168.000
RIPRAP (CONC) (CL B) (4")
CY 130.000 $320.000 $366.000 $350.000 $350.000 $370.000 $415.000 $325.000 $440.000 $557.560 $450.000 $440.000 $560.000
RIPRAP (CONC)(CL B)(5 IN)
CY 80.000 $340.000 $350.000 $350.000 $400.000 $375.000 $415.000 $300.000 $450.000 $523.610 $500.000 $440.000 $445.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 880.000 $70.000 $160.000 $105.000 $90.000 $150.000 $93.740 $135.000 $110.000 $110.270 $165.000 $120.000 $210.000
RIPRAP (MOW STRIP)(4 IN)
CY 55.000 $400.000 $470.000 $425.000 $385.000 $470.000 $450.000 $485.000 $450.000 $550.460 $400.000 $460.000 $645.000
RAIL (TY C412)
LF 828.000 $160.000 $110.000 $115.000 $95.000 $135.000 $113.100 $130.000 $257.000 $80.400 $175.000 $170.000 $150.000
SEALED EXPANSION JOINT (5 IN) (SEJ - A)
LF 132.300 $113.520 $100.000 $105.000 $100.000 $104.030 $115.950 $95.000 $107.000 $239.670 $110.000 $90.000 $185.000
CMP (GAL STL 18 IN)
LF 38.000 $50.000 $42.000 $40.000 $40.000 $92.870 $55.260 $40.000 $77.000 $103.120 $70.000 $80.000 $60.000
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 2.000 $1,100.000 $1,700.000 $550.000 $500.000 $1,059.170 $565.500 $900.000 $1,140.000 $465.590 $1,500.000 $1,300.000 $1,450.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $80,000.000 $40,500.000 $50,000.000 $85,000.000 $30,000.000 $37,500.000 $50,000.000 $66,000.000 $72,146.410 $124,250.000 $75,000.000 $79,000.000
REMOV STR (SMALL FENCE)
LF 955.000 $3.000 $4.000 $1.000 $5.000 $1.400 $0.830 $5.000 $3.000 $10.960 $3.000 $1.400 $6.000
MOBILIZATION
LS 1.000 $382,215.550 $57,000.000 $570,000.000 $375,003.000 $426,000.000 $365,000.000 $592,500.000 $520,000.000 $670,291.720 $625,000.000 $700,000.000 $740,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $3,500.000 $2,000.000 $2,800.000 $3,500.000 $1,000.000 $1,204.690 $1,100.000 $2,120.000 $745.650 $12,500.000 $5,000.000 $2,100.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 610.000 $35.000 $45.500 $46.000 $42.000 $45.500 $44.100 $48.000 $42.000 $84.300 $90.000 $42.000 $42.000
ROCK FILTER DAMS (INSTALL) (TY 4)
LF 234.000 $24.000 $28.500 $29.000 $28.900 $28.500 $30.350 $30.000 $30.000 $32.550 $42.000 $29.000 $29.000
ROCK FILTER DAMS (REMOVE)
LF 844.000 $6.000 $12.000 $12.000 $6.000 $12.000 $6.300 $12.000 $6.000 $18.560 $8.000 $6.000 $6.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 666.000 $13.370 $12.500 $13.000 $18.680 $12.500 $19.610 $15.000 $19.000 $14.940 $19.000 $19.000 $19.000
CONSTRUCTION EXITS (REMOVE)
SY 666.000 $4.000 $10.000 $10.000 $8.000 $10.000 $6.300 $5.000 $6.000 $6.360 $6.000 $6.000 $6.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 160.000 $50.000 $55.000 $35.000 $28.380 $59.400 $55.000 $55.000 $72.000 $185.570 $60.000 $75.000 $160.000
CONSTRUCTION PERIMETER FENCE
LF 1,105.000 $2.150 $6.000 $9.000 $2.250 $2.650 $2.360 $3.000 $2.300 $2.880 $4.000 $2.300 $2.250
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,666.000 $1.760 $2.250 $2.300 $2.250 $2.250 $2.360 $3.000 $2.300 $2.480 $2.250 $2.300 $2.250
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,666.000 $0.410 $0.750 $0.750 $0.250 $0.750 $0.260 $0.750 $0.260 $0.280 $0.250 $0.250 $0.250
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 8,239.000 $3.500 $3.750 $3.800 $3.000 $3.750 $3.150 $4.000 $3.000 $6.000 $3.000 $3.000 $3.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 8,239.000 $0.750 $0.750 $0.750 $1.000 $0.750 $1.050 $0.750 $1.000 $1.100 $1.100 $1.000 $1.000
CONSTRUCTING DETOURS
SY 468.000 $36.000 $24.000 $45.000 $55.000 $75.200 $52.830 $52.000 $56.000 $127.070 $55.000 $55.000 $75.000
ONE-WAY TRAF CONT (PILOT CAR)
HR 144.000 $63.500 $85.000 $75.000 $70.000 $109.620 $195.000 $100.000 $158.000 $90.060 $80.000 $86.000 $100.000
PTB (FRN&INSTL)(F SHAPE)(TY 1) OR (STL)
LF 3,600.000 $9.000 $35.000 $15.000 $15.000 $9.000 $9.750 $45.000 $43.000 $32.830 $33.000 $25.000 $12.000
PTB (MOVE)(F SHAPE)(TY 1) OR (STL)
LF 2,910.000 $5.000 $4.500 $3.000 $5.000 $5.000 $4.550 $8.000 $8.000 $7.990 $4.000 $8.000 $8.000
PTB (REMOVE)(F SHAPE)(TY 1) OR (STL)
LF 3,600.000 $8.000 $9.000 $8.000 $10.000 $9.000 $7.020 $10.000 $13.000 $6.680 $7.000 $13.000 $12.000
DRIVEWAYS AND TURNOUTS (SURF TREAT)
SY 617.400 $24.500 $14.000 $24.000 $40.000 $40.000 $25.800 $17.000 $35.000 $54.950 $25.000 $34.000 $45.000
MTL W-BEAM GD FEN (TIM POST)
LF 944.000 $19.540 $21.630 $22.000 $19.750 $22.750 $20.740 $22.750 $20.000 $22.850 $20.000 $22.000 $19.750
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,795.840 $1,616.000 $2,000.000 $1,245.000 $1,845.000 $1,307.250 $1,845.000 $1,780.000 $1,710.730 $1,250.000 $1,700.000 $1,245.000
REMOVE METAL BEAM GUARD FENCE
LF 651.000 $1.100 $2.000 $1.000 $1.000 $2.500 $1.050 $2.000 $1.000 $2.240 $1.000 $1.000 $1.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 4.000 $150.000 $198.000 $150.000 $100.000 $185.000 $105.000 $150.000 $102.000 $214.730 $100.000 $100.000 $100.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,345.670 $2,522.200 $2,500.000 $2,496.000 $2,696.000 $2,620.800 $2,700.000 $2,540.000 $214.730 $2,500.000 $2,800.000 $2,496.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $70.000 $276.000 $200.000 $125.000 $275.000 $131.250 $275.000 $125.000 $2,667.730 $125.000 $140.000 $125.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $758.290 $1,735.000 $500.000 $1,000.000 $2,750.000 $2,739.750 $2,750.000 $1,020.000 $1,842.970 $1,000.000 $1,000.000 $1,000.000
CRASH CUSH ATTEN (REMOVE)
EA 8.000 $208.520 $1,032.000 $400.000 $500.000 $1,000.000 $1,089.080 $1,000.000 $760.000 $1,091.870 $500.000 $500.000 $500.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 8.000 $7,066.250 $9,240.000 $6,000.000 $6,250.000 $9,500.000 $6,500.000 $10,000.000 $6,590.000 $9,754.370 $6,500.000 $6,500.000 $6,250.000
MAILBOX INSTALL-S (TWG-POST) TY 1
EA 2.000 $130.000 $153.000 $200.000 $153.000 $153.000 $185.850 $153.000 $155.000 $179.770 $180.000 $160.000 $153.000
MAILBOX INSTALL-D (TWG-POST) TY 1
EA 1.000 $180.000 $192.000 $255.000 $192.000 $192.000 $236.730 $192.000 $194.000 $234.130 $230.000 $200.000 $192.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 8.000 $400.000 $407.000 $480.000 $407.000 $407.000 $507.830 $407.000 $415.000 $450.570 $485.000 $420.000 $407.000
REMOVE SM RD SN SUP&AM
EA 6.000 $56.790 $75.000 $95.000 $75.000 $75.000 $105.000 $75.000 $76.000 $86.320 $100.000 $75.000 $75.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $22.130 $16.000 $14.000 $16.000 $16.000 $14.180 $16.000 $16.000 $21.420 $13.500 $16.000 $16.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BR)
EA 11.000 $16.000 $18.000 $14.000 $18.000 $18.000 $14.180 $18.000 $18.000 $21.880 $13.500 $18.000 $18.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 4.000 $18.660 $22.000 $17.000 $22.000 $22.000 $16.800 $22.000 $22.000 $29.930 $16.000 $22.000 $22.000
WK ZN PAV MRK REMOV (W)4"(SLD W/MRKR)
LF 19,060.000 $0.500 $0.570 $0.580 $0.570 $0.570 $0.600 $0.570 $0.600 $0.630 $0.600 $0.600 $0.570
WK ZN PAV MRK REMOV (Y)4"(SLD W/MRKR)
LF 22,880.000 $0.500 $0.570 $0.580 $0.570 $0.570 $0.600 $0.570 $0.600 $0.630 $0.600 $0.600 $0.570
PAVEMENT SEALER 4"
LF 22,184.000 $0.070 $0.120 $0.130 $0.120 $0.120 $0.130 $0.120 $0.120 $0.130 $0.150 $0.120 $0.120
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 11,094.000 $0.800 $0.680 $0.690 $0.680 $0.680 $0.710 $0.680 $0.700 $0.750 $0.700 $0.700 $0.680
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 11,094.000 $0.800 $0.680 $0.690 $0.680 $0.680 $0.710 $0.680 $0.700 $0.750 $0.700 $0.700 $0.680
REFL PAV MRKR TY II-A-A
EA 109.000 $3.000 $5.000 $5.100 $5.000 $5.000 $5.250 $5.000 $5.100 $5.710 $5.000 $5.000 $5.000
ELIM EXT PAV MRK & MRKS (4")
LF 10,371.000 $0.590 $0.470 $0.500 $0.470 $0.470 $0.490 $0.470 $0.500 $0.520 $0.500 $0.500 $0.470
PAV SURF PREP FOR MRK (4")
LF 1,776.000 $0.150 $0.200 $0.210 $0.200 $0.200 $0.210 $0.200 $0.200 $0.230 $0.200 $0.200 $0.200
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 196.000 $60.000 $165.000 $80.000 $60.000 $38.270 $115.000 $100.000 $26.000 $262.570 $50.000 $75.000 $100.000
TMA (STATIONARY)
DAY 28.000 $200.000 $380.000 $215.000 $165.000 $65.000 $252.870 $200.000 $190.000 $613.200 $160.000 $250.000 $320.000
Totals: $5,215,909.885 $5,704,330.280 $5,734,991.800 $5,755,176.689 $5,772,536.277 $5,846,460.964 $6,096,562.730 $6,959,677.670 $7,095,943.060 $7,131,290.250 $7,231,177.430 $7,495,802.440