Show Job Controls
Bid Cobra

ATASCOSA IH 35 (0017-04-050)

Items: 7

County: ATASCOSA
Length: 113.6910 MILES
Highway: IH 35
District: SAN ANTONIO
Control Number: 0017-04-050
DBE Goal: 0.0%
Project: STP 2B25(142)HES
Guaranty: $67,000.00
Time: 125 WORKING DAYS
Engineer's Estimate: $3,340,909.76
Date: 09/04/2025 (9 months ago)
Contract Number: 9253020
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00212532
Contract Type: Federal
Project Description: INSTALL CENTERLINE AND EDGELINE RUMBLE STRIPS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ORLANDO GALLEGOS
MICHAEL DONOVAN
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$3,340,909.76
Over/Under Est: -82.55% -$2,758,075.94
Over/Under Est: -81.52% -$2,723,410.89
Amt Left: 5.95% $34,665.05
$646,908.48
Over/Under Est: -80.64% -$2,694,001.28
Amt Left: 10.99% $64,074.66
Delta: -4.76% -$29,409.61
Over/Under Est: -79.1% -$2,642,611.28
Amt Left: 19.81% $115,464.66
Delta: -7.94% -$51,390.00
Over/Under Est: -62.61% -$2,091,657.58
Amt Left: 114.34% $666,418.36
Delta: -78.90% -$550,953.70
Over/Under Est: -60.27% -$2,013,625.31
Amt Left: 127.73% $744,450.63
Delta: -6.25% -$78,032.27
Over/Under Est: -17.37% -$580,165.76
Amt Left: 373.68% $2,177,910.18
Delta: -108.00% -$1,433,459.55

Bid Items & Bid Tabulations

7 Total 0 of 7
ATASCOSA  |  IH 35  |  SAN ANTONIO  |  0017-04-050  |  09/04/2025  |  $3,340,909.76  |  STP 2B25(142)HES  |  HAZARD ELIM & SAFETY  |  125 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TRP INFRASTRUCTURE SERVICES, LLC
SURFACE PREPARATION TECHNOLOGIES, LLC
STRIPE-A-ZONE, LLC
DOUBLE A CONTRACTING, L.P.
PROFESSIONAL TRAFFIC CONTROL LLC
INTERSTATE BARRICADES & MARKINGS, INC.
GREY SKY CONSTRUCTION LLC
MOBILIZATION
LS 1.000 $335,147.910 $7,500.000 $53,915.000 $50,000.000 $26,000.000 $124,000.000 $300,000.000 $200,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $3,000.000 $10.000 $1.000 $200.000 $1.000 $3,500.000 $10,000.000 $20,000.000
TMA (MOBILE OPERATION)
DAY 224.000 $500.000 $5.000 $1.000 $1.000 $1.000 $350.000 $500.000 $550.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 1,163,519.000 $1.100 $0.115 $0.120 $0.135 $0.160 $0.180 $0.200 $1.000
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 303,839.000 $2.250 $0.150 $0.120 $0.135 $0.220 $0.240 $0.250 $1.000
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 146,600.000 $0.750 $0.520 $0.478 $0.490 $0.550 $0.950 $0.650 $1.000
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 663,586.000 $1.200 $0.480 $0.478 $0.490 $0.510 $0.900 $0.650 $1.000
Totals: $3,340,909.760 $582,833.815 $617,498.868 $646,908.470 $698,298.480 $1,249,252.180 $1,327,284.450 $2,760,744.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $2,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $2,000.00
Total: $5,000.00