Show Job Controls
Bid Cobra

ARMSTRONG SH 207 (0357-05-025)

Items: 18

County: ARMSTRONG
Length: N/A
Highway: SH 207
District: AMARILLO
Control Number: 0357-05-025
DBE Goal: N/A
Project: STP 1802(471)HES
Guaranty: N/A
Time: 96 WORKING DAYS
Engineer's Estimate: $2,343,863.70
Date: 07/11/2018 (7 years ago)
Contract Number: N/A
Type: GUARDRAIL IMPROVEMENTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$2,343,863.70
$2,257,957.00
Over/Under Est: -3.67% -$85,906.70
$2,344,139.50
Over/Under Est: 0.01% $275.80
Amt Left: 3.82% $86,182.50
$2,765,906.69
Over/Under Est: 18.01% $422,042.99
Amt Left: 22.5% $507,949.69
Delta: -17.99% -$421,767.19
$2,875,481.00
Over/Under Est: 22.68% $531,617.30
Amt Left: 27.35% $617,524.00
Delta: -3.96% -$109,574.31
$3,470,461.50
Over/Under Est: 48.07% $1,126,597.80
Amt Left: 53.7% $1,212,504.50
Delta: -20.69% -$594,980.50

Bid Items & Bid Tabulations

18 Total 0 of 18
ARMSTRONG  |  SH 207  |  AMARILLO  |  0357-05-025  |  07/11/2018  |  $2,343,863.70  |  STP 1802(471)HES  |  GUARDRAIL IMPRVS  |  96 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HJC FARMS, INC.
GILVIN-TERRILL, LTD.
3LW CIVIL LLC
EARTH BUILDERS, L.P.
VANN/ELLI, INC.
CURB (TYPE II - A)
LF 72.000 $40.000 $18.000 $75.000 $55.000 $30.000 $48.000
CL C CONC (RAIL FOUNDATION)
CY 18.200 $1,000.000 $800.000 $2,000.000 $1,500.000 $600.000 $1,575.000
RIPRAP (CONC)(4 IN)
CY 10.300 $450.000 $800.000 $1,650.000 $651.250 $650.000 $750.000
RAIL (TY T221)
LF 192.000 $175.000 $150.000 $200.000 $250.000 $250.000 $370.000
REMOV STR (WINGWALL)
EA 8.000 $2,000.000 $1,750.000 $500.000 $1,707.650 $2,000.000 $5,500.000
MOBILIZATION
LS 1.000 $200,000.000 $100,000.000 $230,000.000 $300,000.000 $290,000.000 $250,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $6,000.000 $2,000.000 $15,000.000 $10,000.000 $12,000.000 $16,000.000
MTL W-BEAM GD FEN (STEEL POST)
LF 50,350.000 $25.000 $24.500 $20.000 $30.000 $33.000 $37.540
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 16.000 $1,900.000 $2,200.000 $2,000.000 $1,736.690 $2,000.000 $3,300.000
MTL BEAM GD FEN TRANS (T101)
EA 12.000 $1,200.000 $1,215.000 $1,000.000 $916.060 $1,500.000 $1,462.000
REMOVE METAL BEAM GUARD FENCE
LF 47,077.000 $3.100 $3.000 $3.500 $4.000 $3.000 $2.500
REMOVE TERMINAL ANCHOR SECTION
EA 182.000 $250.000 $200.000 $400.000 $225.000 $300.000 $300.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 8.000 $270.000 $200.000 $500.000 $265.000 $250.000 $300.000
GUARDRAIL END TREATMENT (INSTALL)
EA 190.000 $2,400.000 $2,750.000 $2,500.000 $2,500.000 $2,500.000 $3,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 8.000 $300.000 $200.000 $750.000 $285.000 $300.000 $300.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 575.000 $40.000 $25.000 $25.000 $31.600 $19.000 $40.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $20,000.000 $15,000.000 $10,000.000 $12,000.000 $20,000.000
TMA (STATIONARY)
EA 2.000 $20,000.000 $20,000.000 $60,000.000 $10,084.930 $10,000.000 $60,000.000
Totals: $2,343,863.700 $2,257,957.000 $2,344,139.500 $2,765,906.695 $2,875,481.000 $3,470,461.500