ARCHER FM0368 (6346-78-001)

Items: 36

County: ARCHER
Length: N/A
Highway: FM0368
District: WICHITA FALLS
Control Number: 6346-78-001
DBE Goal: N/A
Project: RMC - 634678001
Guaranty: N/A
Time: 62 W
Engineer's Estimate: $577,773.98
Date: 12/04/2019 (6 years ago)
Contract Number: N/A
Type: CULVERT REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$577,773.98
$587,035.21
Over/Under Est: 1.6% $9,261.23
$726,918.21
Over/Under Est: 25.81% $149,144.23
Amt Left: 23.83% $139,883.00
Over/Under Est: 26.02% $150,341.37
Amt Left: 24.03% $141,080.14
Delta: -0.16% -$1,197.14
Over/Under Est: 28.95% $167,260.52
Amt Left: 26.91% $157,999.29
Delta: -2.32% -$16,919.15
Over/Under Est: 30.95% $178,829.77
Amt Left: 28.89% $169,568.54
Delta: -1.55% -$11,569.25

Bid Items & Bid Tabulations

36 Total 0 of 36
ARCHER  |  FM0368  |  WICHITA FALLS  |  6346-78-001  |  12/04/2019  |  $577,773.98  |  RMC - 634678001  |  CULVERT REPL  |  62 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
BEAR CREEK CONTRACTING, LLC
ROAD DOCTORS LLC
FNH CONSTRUCTION, LLC
HIGHWAY 19 CONSTRUCTION LLC
EARTH BUILDERS, L.P.
EXCAVATION (CHANNEL)
CY 78.000 $20.000 $7.000 $36.000 $100.000 $100.000 $50.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 350.000 $50.000 $60.000 $70.000 $50.000 $65.000 $60.000
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 2,825.000 $3.000 $4.000 $4.000 $2.000 $1.000 $2.000
VEGETATIVE WATERING
MG 26.000 $30.000 $3.000 $200.000 $500.000 $10.000 $150.000
CEM STABIL BKFL
CY 171.080 $220.000 $193.000 $200.000 $350.000 $50.000 $300.000
CUT & RESTORING PAV
SY 192.660 $150.000 $308.000 $256.000 $200.000 $250.000 $400.000
TRENCH EXCAVATION PROTECTION
LF 44.000 $30.000 $7.000 $350.000 $15.000 $50.000 $40.000
TEMPORARY SPL SHORING
SF 659.330 $30.000 $26.000 $50.000 $90.000 $100.000 $25.000
RIPRAP (CONC)(5 IN)
CY 5.000 $500.000 $500.000 $500.000 $650.000 $1,000.000 $1,000.000
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 28.090 $300.000 $199.000 $275.000 $285.000 $250.000 $250.000
CONC BOX CULV (10 FT X 8 FT)(EXTEND)
LF 14.000 $1,200.000 $1,440.000 $1,060.000 $2,500.000 $1,500.000 $2,500.000
RC PIPE (CL III)(24 IN)
LF 344.000 $109.000 $97.000 $140.000 $105.000 $110.000 $200.000
RC PIPE (CL III)(30 IN)
LF 112.000 $150.000 $122.000 $200.000 $125.000 $150.000 $225.000
RC PIPE (CL III)(36 IN)
LF 44.000 $200.000 $163.000 $375.000 $150.000 $200.000 $275.000
RC PIPE (CL III)(48 IN)
LF 96.000 $275.000 $285.000 $385.000 $350.000 $350.000 $325.000
HEADWALL (CH - FW - 0) (DIA= 24 IN)
EA 12.000 $4,500.000 $7,375.000 $5,600.000 $2,000.000 $4,500.000 $5,000.000
HEADWALL (CH - FW - 0) (DIA= 36 IN)
EA 2.000 $6,500.000 $7,726.000 $6,200.000 $3,500.000 $8,000.000 $6,000.000
HEADWALL (CH - FW - 15) (DIA= 30 IN)
EA 2.000 $6,000.000 $7,237.000 $5,900.000 $5,000.000 $7,500.000 $6,000.000
HEADWALL (CH - PW - 0) (DIA= 48 IN)
EA 4.000 $10,000.000 $10,507.000 $8,800.000 $6,000.000 $12,000.000 $8,000.000
WINGWALL (FW - S) (HW=9 FT)
EA 1.000 $40,000.000 $13,603.000 $14,600.000 $25,000.000 $39,000.000 $17,500.000
WINGWALL (PW - 2) (HW=9 FT)
EA 1.000 $25,000.000 $15,538.000 $17,200.000 $40,000.000 $39,000.000 $25,000.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 1.000 $2,000.000 $1,078.000 $2,900.000 $1,850.000 $1,200.000 $2,500.000
SET (TY II) (24 IN) (RCP) (4: 1) (P)
EA 1.000 $2,000.000 $1,078.000 $2,900.000 $2,250.000 $1,000.000 $3,000.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 2.000 $3,000.000 $1,392.000 $4,400.000 $3,500.000 $2,900.000 $3,500.000
CLEAN EXIST CULVERTS
EA 3.000 $2,500.000 $926.000 $2,300.000 $4,500.000 $2,000.000 $15,000.000
REMOV STR (SET)
EA 2.000 $1,000.000 $710.000 $570.000 $1,000.000 $500.000 $1,000.000
REMOV STR (WINGWALL)
EA 2.000 $1,000.000 $1,183.000 $1,200.000 $2,500.000 $1,000.000 $5,000.000
REMOV STR (PIPE)
LF 592.000 $50.000 $10.000 $21.000 $40.000 $20.000 $25.000
MOBILIZATION
LS 1.000 $49,979.480 $76,246.000 $87,000.000 $72,000.000 $150,000.000 $75,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $7,000.000 $3,072.000 $10,000.000 $8,500.000 $5,000.000 $8,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 700.000 $5.000 $7.000 $5.000 $4.000 $3.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 700.000 $1.000 $3.000 $2.000 $2.000 $1.000 $2.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 650.000 $2.500 $14.000 $6.000 $18.000 $5.000 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 650.000 $1.000 $4.000 $2.000 $12.000 $1.000 $2.000
INSTL OM ASSM (OM-2Z)(FLX)SRF(BI)
EA 27.000 $85.000 $268.000 $250.000 $100.000 $35.000 $100.000
TMA (STATIONARY)
DAY 130.000 $175.000 $100.000 $480.000 $550.000 $300.000 $200.000
Totals: $577,773.980 $587,035.210 $726,918.210 $728,115.350 $745,034.500 $756,603.750