ARCHER FM 1954 (1837-02-017)

Items: 97

County: ARCHER
Length: N/A
Highway: FM 1954
District: WICHITA FALLS
Control Number: 1837-02-017
DBE Goal: N/A
Project: F 2023(091)
Guaranty: N/A
Time: 221 WORKING DAYS
Engineer's Estimate: $7,363,920.25
Date: 09/08/2022 (3 years ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
ZACHARY HUSEN
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$7,363,920.25
$7,814,963.76
Over/Under Est: 6.13% $451,043.51
$8,791,999.55
Over/Under Est: 19.39% $1,428,079.30
Amt Left: 12.5% $977,035.79
$9,484,502.69
Over/Under Est: 28.8% $2,120,582.44
Amt Left: 21.36% $1,669,538.93
Delta: -7.88% -$692,503.14
Over/Under Est: 29.16% $2,147,628.18
Amt Left: 21.71% $1,696,584.67
Delta: -0.29% -$27,045.74
Subcontractor Percentage Amount
W. S. CONSTRUCTION COMPANY 16.23% $1,625,719.32
LANCO TURF & SEEDING, INC. 1.30% $130,217.81
DUSTIN ALLEN, INC. 0.81% $81,135.71
TRAFFIC HIGHWAY MAINTENANCE, LLC 0.67% $67,112.26
MARCOM'S MOWING SERVICE, LLC 0.49% $49,082.10
BARRICADES UNLIMITED 0.21% $21,035.19
Total: 19.71% $1,974,302.39

Bid Items & Bid Tabulations

97 Total 0 of 97
ARCHER  |  FM 1954  |  WICHITA FALLS  |  1837-02-017  |  09/08/2022  |  $7,363,920.25  |  F 2023(091)  |  SURF/ROADWAY RESTOR  |  221 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
A. L. HELMCAMP, INC.
ZACK BURKETT CO.
DUININCK, INC.
EUROVIA ATLANTIC COAST LLC
PREPARING ROW
STA 23.000 $4,000.000 $1,700.000 $2,750.000 $1,800.000 $1,350.000
EXCAVATION (ROADWAY)
CY 27,911.000 $9.000 $4.000 $25.000 $18.000 $17.650
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 13,174.000 $28.000 $18.000 $21.250 $21.500 $22.000
BROADCAST SEED (TEMP) (WARM)
SY 61,520.000 $0.250 $0.090 $0.120 $0.130 $0.120
BROADCAST SEED (TEMP) (COOL)
SY 61,520.000 $0.250 $0.120 $0.140 $0.130 $0.120
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 123,033.000 $0.250 $0.120 $0.150 $0.160 $0.150
VEGETATIVE WATERING
MG 1,046.000 $25.000 $8.000 $40.000 $30.500 $40.000
CEMENT
TON 558.000 $200.000 $227.000 $275.000 $235.000 $275.000
CEMENT TREAT (SUBGRADE) (8")
SY 50,779.000 $3.000 $2.900 $4.500 $6.200 $4.150
PRIME COAT (MC-30)
GAL 12,697.000 $4.000 $6.000 $5.000 $5.650 $6.500
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 3,203.000 $41.000 $60.000 $45.500 $57.000 $59.000
CUT & RESTORING PAV
SY 194.000 $77.000 $78.750 $52.650 $78.000 $165.000
TRENCH EXCAVATION PROTECTION
LF 364.000 $3.000 $5.300 $17.550 $5.200 $5.000
CL C CONC (COLLAR)
EA 19.000 $1,030.000 $1,300.000 $877.500 $1,300.000 $1,200.000
RIPRAP (CONC)(CL B)(5 IN)
CY 76.000 $458.000 $580.000 $819.000 $575.000 $705.000
RIPRAP (STONE TY R)(DRY)(12 IN)
CY 303.000 $280.000 $263.000 $75.000 $260.000 $346.000
RIPRAP (MOW STRIP)(4 IN)
CY 131.000 $541.000 $580.000 $789.750 $575.000 $620.000
CMP (GAL STL 18 IN)
LF 319.000 $57.000 $84.000 $87.750 $83.500 $80.000
CMP (GAL STL 24 IN)
LF 366.000 $76.000 $103.000 $105.300 $100.000 $96.000
CONC BOX CULV (4 FT X 2 FT)
LF 192.000 $200.000 $452.000 $526.500 $450.000 $330.000
CONC BOX CULV (5 FT X 2 FT)(EXTEND)
LF 38.000 $657.000 $540.000 $702.000 $530.000 $510.000
CONC BOX CULV (6 FT X 3 FT)(EXTEND)
LF 277.000 $545.000 $680.000 $918.450 $675.000 $590.000
CONC BOX CULV (6 FT X 4 FT)(EXTEND)
LF 31.000 $700.000 $720.000 $1,041.300 $720.000 $690.000
CONC BOX CULV (6 FT X 6 FT)(EXTEND)
LF 45.000 $562.000 $840.000 $1,170.000 $835.000 $800.000
CONC BOX CULV (7 FT X 3 FT)(EXTEND)
LF 47.000 $534.000 $710.000 $1,053.000 $705.000 $675.000
CONC BOX CULV (7 FT X 6 FT)(EXTEND)
LF 32.000 $720.000 $920.000 $1,287.000 $915.000 $880.000
CONC BOX CULV (8 FT X 5 FT)(EXTEND)
LF 60.000 $612.000 $870.000 $1,146.600 $865.000 $830.000
RC PIPE (CL III)(18 IN)
LF 501.000 $67.000 $61.000 $93.600 $60.500 $58.000
RC PIPE (CL III)(24 IN)
LF 468.000 $65.000 $84.000 $134.550 $83.500 $80.000
RC PIPE (CL III)(30 IN)
LF 40.000 $89.000 $105.000 $187.200 $105.000 $100.000
RC PIPE (CL III)(36 IN)
LF 48.000 $108.000 $158.000 $269.100 $155.000 $150.000
RC PIPE (CL III)(48 IN)
LF 38.000 $190.000 $263.000 $456.300 $260.000 $250.000
HEADWALL (CH - PW - S) (DIA= 48 IN)
EA 2.000 $15,455.000 $23,100.000 $27,846.000 $23,000.000 $19,000.000
WINGWALL (FW - S) (HW=4 FT)
EA 2.000 $9,749.000 $6,100.000 $9,348.300 $6,000.000 $5,800.000
WINGWALL (PW - 2) (HW=4 FT)
EA 4.000 $11,313.000 $7,400.000 $12,331.800 $7,300.000 $7,050.000
WINGWALL (PW - 2) (HW=5 FT)
EA 1.000 $17,057.000 $10,100.000 $15,912.000 $10,000.000 $9,600.000
WINGWALL (PW - 2) (HW=6 FT)
EA 2.000 $21,490.000 $26,300.000 $34,409.700 $26,000.000 $20,500.000
WINGWALL (PW - 2) (HW=7 FT)
EA 4.000 $23,230.000 $29,400.000 $32,719.050 $29,000.000 $19,700.000
SET (TY I)(S= 4 FT)(HW= 3 FT)(4:1) (C)
EA 8.000 $5,946.000 $2,400.000 $6,435.000 $2,300.000 $2,240.000
SET (TY I)(S= 5 FT)(HW= 3 FT)(4:1) (C)
EA 2.000 $6,583.000 $8,600.000 $10,588.500 $8,500.000 $8,200.000
SET (TY I)(S= 6 FT)(HW= 5 FT)(4:1) (C)
EA 1.000 $11,872.000 $16,100.000 $23,318.100 $16,000.000 $15,300.000
SET (TY I)(S= 8 FT)(HW= 7 FT)(4:1) (C)
EA 2.000 $21,700.000 $23,500.000 $33,029.100 $23,500.000 $22,400.000
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 22.000 $1,012.000 $1,600.000 $1,170.000 $1,600.000 $1,500.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 42.000 $960.000 $1,500.000 $1,287.000 $1,500.000 $1,400.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 28.000 $1,278.000 $2,200.000 $1,755.000 $2,200.000 $2,065.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 12.000 $1,451.000 $1,500.000 $1,462.500 $1,500.000 $1,450.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 16.000 $1,381.000 $1,800.000 $1,521.000 $1,800.000 $1,750.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 10.000 $2,300.000 $3,400.000 $3,276.000 $3,300.000 $3,210.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 4.000 $3,300.000 $3,700.000 $4,095.000 $3,600.000 $3,500.000
REMOV & RE - LAY PIPE (24 IN)
LF 27.000 $41.000 $63.000 $70.200 $62.500 $60.000
REMOV STR (SET)
EA 2.000 $230.000 $210.000 $585.000 $210.000 $200.000
REMOV STR (HEADWALL)
EA 41.000 $1,094.000 $790.000 $585.000 $780.000 $750.000
REMOV STR (PIPE)
LF 1,042.000 $14.000 $9.500 $14.040 $9.400 $9.000
MOBILIZATION
LS 1.000 $677,744.500 $600,000.000 $450,000.000 $810,000.000 $700,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $10,000.000 $10,000.000 $6,550.000 $21,500.000 $23,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 3,053.000 $33.000 $38.900 $45.000 $38.500 $37.000
ROCK FILTER DAMS (REMOVE)
LF 3,053.000 $8.000 $10.500 $10.000 $10.500 $10.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 668.000 $21.000 $31.500 $30.000 $31.500 $30.000
CONSTRUCTION EXITS (REMOVE)
SY 668.000 $8.000 $10.500 $10.000 $10.500 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 15,122.000 $3.000 $3.400 $2.810 $3.650 $3.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 15,122.000 $1.000 $1.100 $1.170 $0.260 $0.250
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 7,467.000 $3.000 $4.700 $3.630 $6.250 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 7,467.000 $1.500 $0.800 $1.170 $1.050 $1.000
DRIVEWAYS (ACP)
SY 3,832.000 $45.000 $41.300 $39.000 $82.500 $66.000
TURNOUTS (ACP)
SY 275.000 $38.000 $58.000 $30.000 $88.500 $135.000
DRIVEWAYS (BASE)
SY 3,329.000 $24.000 $14.300 $22.000 $22.000 $43.000
DRIVEWAYS (CONC) (HES)
SY 509.000 $82.000 $121.000 $117.000 $120.000 $126.000
RUMBLE STRIPS (CENTERLINE)
LF 37,766.000 $0.250 $0.240 $0.360 $0.320 $0.310
MTL W-BEAM GD FEN (TIM POST)
LF 1,525.000 $24.000 $25.200 $33.930 $26.000 $29.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 50.000 $54.000 $102.000 $87.750 $78.000 $75.000
REMOVE METAL BEAM GUARD FENCE
LF 400.000 $3.000 $5.300 $4.100 $2.100 $3.500
GUARDRAIL END TREATMENT (INSTALL)
EA 12.000 $2,900.000 $3,100.000 $4,241.250 $2,900.000 $3,625.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $238.000 $420.000 $409.500 $210.000 $350.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 20.000 $220.000 $263.000 $409.500 $315.000 $575.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 1.000 $320.000 $299.000 $468.000 $365.000 $610.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 7.000 $628.000 $680.000 $1,170.000 $640.000 $650.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 10.000 $861.000 $850.000 $1,404.000 $850.000 $810.000
IN SM RD SN SUP&AM TYS80(1)SA(T-2EXT)
EA 1.000 $990.000 $990.000 $1,462.500 $925.000 $940.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 1.000 $1,100.000 $990.000 $1,521.000 $955.000 $940.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 39.000 $370.000 $394.000 $906.750 $520.000 $375.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 16.000 $430.000 $431.000 $994.500 $575.000 $410.000
REMOVE SM RD SN SUP&AM
EA 71.000 $88.000 $105.000 $117.000 $21.000 $100.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 19.000 $22.000 $49.400 $23.400 $21.000 $33.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 16.000 $105.000 $78.750 $175.500 $105.000 $75.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,719.000 $1.000 $1.100 $1.000 $1.050 $1.240
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 114.000 $7.000 $10.500 $8.830 $7.850 $7.550
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 6,574.000 $0.500 $0.470 $0.750 $0.670 $0.640
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 37,226.000 $0.500 $0.430 $0.590 $0.520 $0.500
RE PROF PM (W)4"(SLD) RAISD PROF ONLY
LF 75,888.000 $0.250 $0.500 $0.530 $0.470 $0.450
REFL PAV MRKR TY II-A-A
EA 805.000 $3.500 $5.300 $5.850 $5.200 $5.000
ELIM EXT PAV MRK & MRKS (4")
LF 113,800.000 $0.500 $0.500 $0.470 $0.420 $0.700
D-GR HMA TY-B PG64-22
TON 16,757.000 $90.000 $101.000 $101.000 $115.000 $111.000
D-GR HMA TY-D PG70-28
TON 15,342.000 $95.000 $111.000 $118.000 $125.130 $141.000
D-GR HMA TY-D PG70-28 (LEVEL-UP)
TON 1,456.000 $95.000 $140.000 $131.250 $150.000 $170.000
BONDING COURSE
GAL 11,425.000 $4.000 $4.200 $5.500 $3.750 $4.000
TMA (STATIONARY)
DAY 344.000 $180.000 $250.000 $100.000 $260.000 $325.000
TMA (MOBILE OPERATION)
DAY 54.000 $323.000 $150.000 $1.000 $940.000 $600.000
Totals: $7,363,920.250 $7,814,963.760 $8,791,999.550 $9,484,502.690 $9,511,548.430