ARCHER FM 1954 (1837-01-013)

Items: 124

County: ARCHER
Length: N/A
Highway: FM 1954
District: WICHITA FALLS
Control Number: 1837-01-013
DBE Goal: N/A
Project: STP 2B20(078)
Guaranty: N/A
Time: 212 WORKING DAYS
Engineer's Estimate: $5,174,156.87
Date: 11/05/2020 (5 years ago)
Contract Number: N/A
Type: REALIGN INTERSECTION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$5,174,156.87
$4,925,489.02
Over/Under Est: -4.81% -$248,667.85
$4,971,994.33
Over/Under Est: -3.91% -$202,162.54
Amt Left: 0.94% $46,505.31
$4,986,967.74
Over/Under Est: -3.62% -$187,189.13
Amt Left: 1.25% $61,478.72
Delta: -0.30% -$14,973.41

Bid Items & Bid Tabulations

124 Total 0 of 124
ARCHER  |  FM 1954  |  WICHITA FALLS  |  1837-01-013  |  11/05/2020  |  $5,174,156.87  |  STP 2B20(078)  |  REALIGN INTERS  |  212 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
EUROVIA ATLANTIC COAST LLC
A. L. HELMCAMP, INC.
JAGOE-PUBLIC COMPANY
PREPARING ROW
STA 49.000 $2,286.440 $700.000 $500.000 $491.350
REMOVE STAB BASE & ASPH PAV (13"-18")
SY 7,965.000 $8.000 $8.000 $10.000 $8.420
EXCAVATION (ROADWAY)
CY 4,618.000 $13.000 $28.000 $17.000 $14.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 4,554.000 $8.100 $31.000 $17.000 $14.350
BROADCAST SEED (TEMP) (WARM)
SY 62,720.000 $0.120 $0.180 $0.050 $0.180
BROADCAST SEED (TEMP) (COOL)
SY 62,720.000 $0.110 $0.180 $0.060 $0.180
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 125,442.000 $0.150 $0.150 $0.070 $0.170
VEGETATIVE WATERING
MG 1,053.710 $25.000 $33.000 $15.000 $31.580
CEMENT
TON 467.000 $170.000 $185.000 $165.000 $192.000
CEMENT TREAT (SUBGRADE) (8")
SY 42,250.000 $4.500 $2.850 $2.800 $4.500
PRIME COAT (MC-30)
GAL 10,568.000 $10.000 $4.250 $4.500 $6.300
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 834.000 $56.000 $38.000 $70.000 $35.950
CUT & RESTORE ASPH PAVING
SY 135.000 $78.000 $50.000 $60.000 $81.490
TRENCH EXCAVATION PROTECTION
LF 152.000 $2.500 $10.000 $27.000 $26.320
TEMPORARY SPL SHORING
SF 175.000 $43.000 $60.000 $55.000 $52.640
DRILL SHAFT (TRF SIG POLE) (36 IN)
LF 56.000 $400.000 $500.000 $530.000 $293.810
CL C CONC (COLLAR)
EA 8.000 $1,346.000 $500.000 $1,600.000 $1,579.060
RIPRAP (CONC) (CL B) (4")
CY 16.000 $400.000 $690.000 $600.000 $578.990
RIPRAP (MOW STRIP)(4 IN)
CY 71.000 $417.000 $675.000 $640.000 $508.450
RIPRAP (STONE PROTECTION)(27 IN)
CY 250.000 $130.000 $220.000 $200.000 $156.190
CMP (GAL STL 18 IN)
LF 637.000 $55.250 $40.000 $85.000 $84.220
CONC BOX CULV (3 FT X 2 FT)
LF 101.000 $200.000 $290.000 $350.000 $342.130
CONC BOX CULV (5 FT X 2 FT)
LF 94.000 $225.000 $375.000 $550.000 $547.410
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
LF 15.000 $570.000 $600.000 $450.000 $447.400
CONC BOX CULV (8 FT X 6 FT)(EXTEND)
LF 81.000 $630.000 $1,000.000 $1,000.000 $957.970
RC PIPE (CL III)(18 IN)
LF 683.000 $66.000 $49.000 $85.000 $84.220
RC PIPE (CL III)(24 IN)
LF 521.000 $114.000 $60.000 $125.000 $126.330
RC PIPE (CL III)(30 IN)
LF 310.000 $95.000 $80.000 $165.000 $163.170
JCTBOX(COMPL)(PJB)(6FTX6FT)
EA 1.000 $8,100.000 $10,000.000 $5,500.000 $5,474.090
HEADWALL (CH - PW - 0) (DIA= 30 IN)
EA 2.000 $6,686.000 $6,000.000 $9,200.000 $9,158.570
WINGWALL (PW - 2) (HW=8 FT)
EA 2.000 $20,195.000 $28,000.000 $38,000.000 $37,897.530
SET (TY I)(S= 5 FT)(HW= 2 FT)(3:1) (P)
EA 2.000 $8,200.000 $6,000.000 $6,900.000 $6,842.610
SET (TY I)(S= 5 FT)(HW= 2 FT)(3:1) (C)
EA 3.000 $8,200.000 $8,200.000 $5,800.000 $5,789.900
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 42.000 $850.000 $875.000 $1,200.000 $1,157.980
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 42.000 $964.000 $825.000 $1,200.000 $1,157.980
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 2.000 $1,125.000 $1,165.000 $1,300.000 $1,315.890
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 26.000 $1,134.000 $1,100.000 $1,300.000 $1,263.250
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $1,168.000 $1,100.000 $1,300.000 $1,315.890
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 22.000 $1,508.000 $1,275.000 $2,200.000 $2,105.420
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 10.000 $2,500.000 $2,200.000 $2,600.000 $2,631.770
REMOV STR (SET)
EA 18.000 $400.000 $200.000 $550.000 $526.350
REMOV STR (WINGWALL)
EA 6.000 $1,000.000 $800.000 $1,100.000 $1,052.710
REMOV STR (HEADWALL)
EA 4.000 $1,045.000 $750.000 $1,100.000 $1,052.710
REMOV STR (PIPE)
LF 1,676.000 $15.000 $10.000 $13.000 $12.630
REMOV STR (BOX CULVERT)
LF 17.000 $37.000 $100.000 $70.000 $68.430
MOBILIZATION
LS 1.000 $458,186.090 $450,000.000 $450,000.000 $490,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $10,000.000 $35,500.000 $10,000.000 $4,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 1,091.000 $25.000 $22.890 $22.000 $31.580
ROCK FILTER DAMS (REMOVE)
LF 1,091.000 $10.000 $6.910 $10.500 $9.470
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 224.000 $20.000 $24.700 $21.000 $31.580
CONSTRUCTION EXITS (REMOVE)
SY 224.000 $8.000 $9.750 $5.250 $10.530
TEMP SEDMT CONT FENCE (INSTALL)
LF 6,865.000 $2.500 $2.000 $2.050 $3.160
TEMP SEDMT CONT FENCE (REMOVE)
LF 6,865.000 $1.000 $0.480 $0.650 $1.050
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 2,750.000 $4.000 $3.940 $2.900 $5.260
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,750.000 $0.860 $0.890 $0.550 $1.050
CONSTRUCTING DETOURS
SY 995.000 $75.000 $51.000 $60.000 $51.390
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 120.000 $2,600.000 $121.000 $93.000 $129.570
DRIVEWAYS (ACP)
SY 2,760.000 $30.000 $32.000 $40.000 $41.030
TURNOUTS (ACP)
SY 316.000 $38.000 $50.000 $50.000 $43.970
DRIVEWAYS (BASE)
SY 2,573.000 $20.500 $20.000 $14.000 $32.210
DRIVEWAYS (CONC) (HES)
SY 234.000 $100.000 $129.000 $110.000 $87.370
RUMBLE STRIPS (SHOULDER)
LF 49,073.000 $0.250 $0.250 $0.220 $0.230
RUMBLE STRIPS (CENTERLINE)
LF 22,343.000 $0.250 $0.310 $0.300 $0.470
CONC DIRECTIONAL ISLAND
SY 167.000 $123.000 $125.000 $65.000 $91.470
MTL W-BEAM GD FEN (TIM POST)
LF 800.000 $21.000 $20.250 $18.000 $17.370
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 1.000 $1,850.000 $1,820.000 $1,650.000 $1,658.020
SHORT RADIUS
LF 188.000 $72.000 $38.000 $37.000 $36.840
DRIVEWAY TERMINAL ANCHOR SECTION
EA 1.000 $1,050.000 $910.000 $1,100.000 $1,063.240
GUARDRAIL END TREATMENT (INSTALL)
EA 7.000 $58.000 $2,780.000 $2,500.000 $2,473.870
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 23.000 $200.000 $280.000 $300.000 $378.980
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 2.000 $350.000 $300.000 $320.000 $447.400
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 2.000 $740.000 $580.000 $610.000 $815.850
REMOVE RD IL ASM (TRANS-BASE)
EA 1.000 $500.000 $550.000 $580.000 $851.660
CONDT (PVC) (SCH 80) (3")
LF 87.000 $20.000 $35.000 $37.000 $15.540
CONDT (PVC) (SCH 80) (3") (BORE)
LF 505.000 $25.000 $45.000 $47.000 $24.290
ELEC CONDR (NO.12) INSULATED
LF 1,918.000 $1.500 $1.250 $1.300 $1.510
ELEC CONDR (NO.6) BARE
LF 592.000 $2.000 $1.750 $1.850 $1.290
ELEC CONDR (NO.6) INSULATED
LF 102.000 $2.000 $3.750 $4.000 $1.960
GROUND BOX TY C (162911)W/APRON
EA 4.000 $1,700.000 $1,650.000 $1,700.000 $1,263.610
ELC SRV TY D 120/240 060(NS)SS(E)SP(O)
EA 1.000 $7,000.000 $6,500.000 $6,900.000 $4,737.200
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 3.000 $670.000 $520.000 $550.000 $842.170
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 14.000 $600.000 $610.000 $640.000 $947.440
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 8.000 $650.000 $680.000 $715.000 $947.440
IN SM RD SN SUP&AM TYS80(1)SA(T-2EXT)
EA 4.000 $1,000.000 $860.000 $910.000 $1,210.620
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 4.000 $775.000 $875.000 $920.000 $1,052.710
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 4.000 $800.000 $870.000 $920.000 $1,105.350
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 29.000 $350.000 $380.000 $400.000 $631.630
REMOVE SM RD SN SUP&AM
EA 58.000 $100.000 $90.000 $95.000 $105.270
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 9.000 $28.000 $20.000 $37.000 $35.790
INSTL OM ASSM (OM-2Z)(FLX)GND(BI)
EA 33.000 $82.000 $90.000 $95.000 $152.640
WK ZN PAV MRK REMOV (REFL) TY II-A-A
LF 15,697.000 $0.500 $0.880 $0.900 $0.930
WK ZN PAV MRK REMOV (W)4"(DOT)
LF 154.000 $2.000 $2.000 $2.100 $2.110
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 13,136.000 $1.250 $0.700 $0.750 $0.740
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 203.000 $10.000 $17.250 $18.000 $18.160
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 14,881.000 $0.850 $0.700 $0.750 $0.740
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,015.000 $1.440 $1.250 $0.450 $1.010
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 811.000 $0.850 $0.900 $1.000 $0.950
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 190.000 $6.850 $22.500 $24.000 $23.690
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 49,073.000 $0.400 $0.450 $0.470 $0.470
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 7,932.000 $0.400 $0.450 $0.470 $0.470
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 11,439.000 $0.330 $0.450 $0.470 $0.470
PREFAB PAV MRK TY C (W) (ARROW)
EA 6.000 $228.500 $300.000 $315.000 $315.810
PREFAB PAV MRK TY C (W) (WORD)
EA 6.000 $250.000 $400.000 $420.000 $421.080
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 13.000 $35.000 $60.000 $63.000 $63.160
REFL PAV MRKR TY I-C
EA 42.000 $5.000 $3.500 $3.700 $3.680
REFL PAV MRKR TY II-A-A
EA 252.000 $4.000 $3.500 $3.700 $3.680
ELIM EXT PAV MRK & MRKS (4")
LF 24,917.000 $0.750 $1.750 $0.400 $4.210
ELIM EXT PAV MRK & MRKS (24")
LF 171.000 $3.000 $10.000 $1.000 $10.530
INSTALL HWY TRF SIG (FLASH BEACON)
EA 1.000 $7,500.000 $4,500.000 $4,800.000 $7,307.280
VEH SIG SEC (12")LED(YEL)
EA 14.000 $500.000 $300.000 $320.000 $251.750
VEH SIG SEC (12")LED(RED)
EA 10.000 $500.000 $300.000 $320.000 $245.240
BACK PLATE (12")(2 SEC)
EA 12.000 $80.000 $75.000 $79.000 $86.740
TRF SIG CBL (TY A)(14 AWG)(3 CONDR)
LF 648.000 $3.500 $2.000 $2.200 $1.910
TRF SIG CBL (TY A)(14 AWG)(10 CONDR)
LF 913.000 $4.000 $4.000 $4.300 $4.390
INS TRF SIG PL AM(S)1 ARM(40')LUM
EA 1.000 $11,000.000 $14,000.000 $15,000.000 $10,455.030
INS TRF SIG PL AM(S)1 ARM(44')LUM
EA 1.000 $13,000.000 $14,250.000 $15,000.000 $9,506.560
INS TRF SIG PL AM(S)1 ARM(48')LUM
EA 2.000 $14,000.000 $16,000.000 $17,000.000 $10,453.680
D-GR HMA TY-B PG64-22
TON 12,631.000 $80.000 $70.000 $82.000 $74.250
D-GR HMA TY-D PG70-28
TON 10,046.000 $85.000 $75.000 $90.000 $81.000
D-GR HMA TY-D PG70-28 (LEVEL-UP)
TON 1,266.000 $90.000 $84.000 $103.000 $85.000
BONDING COURSE
GAL 10,189.000 $3.500 $3.500 $2.500 $3.960
PORTABLE CHANGEABLE MESSAGE SIGN
EA 5.000 $19,800.000 $15,000.000 $10,000.000 $1,930.820
TMA (STATIONARY)
DAY 209.000 $272.000 $275.000 $200.000 $220.870
TMA (MOBILE OPERATION)
DAY 59.000 $314.000 $650.000 $50.000 $1,297.330
Totals: $5,174,156.870 $4,925,489.020 $4,971,994.330 $4,986,967.742