ARCHER SH 79 (0283-03-024)

Items: 66

County: ARCHER
Length: 0.0000 MILES
Highway: SH 79
District: WICHITA FALLS
Control Number: 0283-03-024
DBE Goal: 0.0%
Project: BR 2025(328)
Guaranty: $68,000.00
Time: 132 WORKING DAYS
Engineer's Estimate: $3,410,628.65
Date: 01/07/2025 (1 year ago)
Contract Number: 1253026
Type: BRIDGE REPLACEMENT
Project ID: A00211383
Contract Type: Federal
Project Description: REPLACE BRIDGE CLASS CULVERT
Mail/Deliver Bids To: N/A
ZACHARY HUSEN
CHRISTIAN SIERRA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$3,410,628.65
$3,345,238.25
Over/Under Est: -1.92% -$65,390.40
$3,433,345.81
Over/Under Est: 0.67% $22,717.16
Amt Left: 2.63% $88,107.56
$3,812,320.00
Over/Under Est: 11.78% $401,691.35
Amt Left: 13.96% $467,081.75
Delta: -11.04% -$378,974.19
$3,854,655.00
Over/Under Est: 13.02% $444,026.35
Amt Left: 15.23% $509,416.75
Delta: -1.11% -$42,335.00
Over/Under Est: 20.22% $689,492.50
Amt Left: 22.57% $754,882.90
Delta: -6.37% -$245,466.15
Over/Under Est: 20.23% $689,959.35
Amt Left: 22.58% $755,349.75
Delta: -0.01% -$466.85
Subcontractor Percentage Amount
PEACHTREE CONSTRUCTION, LTD. 15.03% $502,789.31
MORRIS COUNTY CONTRACTORS, L.L.C. 3.37% $112,734.53
STRIPING TECHNOLOGY, L.P. 1.85% $61,886.91
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.64% $21,409.52
DUSTROL, INC. 0.28% $9,366.67
FC TRAFFIC CONTROL, INC. 0.23% $7,694.05
WEST TEXAS ROCK RESOURCES, LLC 0.22% $7,359.52
Total: 21.62% $723,240.51

Bid Items & Bid Tabulations

66 Total 0 of 66
ARCHER  |  SH 79  |  WICHITA FALLS  |  0283-03-024  |  01/07/2025  |  $3,410,628.65  |  BR 2025(328)  |  BRIDGE REPL  |  132 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SKYLINE BRIDGE LLC
ALTUS CONSTRUCTION LLC
IBCTX, LLC
EARTH BUILDERS, L.P.
COPPELL CONSTRUCTION CO., INC.
HODGES AND SON CONSTRUCTION COMPANY, INC.
PREPARING ROW
STA 5.000 $10,000.000 $10,000.000 $68,455.910 $5,000.000 $30,000.000 $7,250.000 $6,000.000
REMOV CONC (MOWSTRIP)
LF 1,480.000 $10.000 $20.000 $8.980 $12.000 $8.000 $5.000 $5.000
EXCAV (ROADWAY)
CY 910.000 $30.000 $20.000 $15.860 $55.000 $25.000 $55.000 $35.000
EMBANK (FNL)(DC)(TY A)
CY 4,146.000 $25.000 $30.000 $46.750 $80.000 $32.000 $25.000 $30.000
BROADCAST SEED (PERM_RURAL_SAND)
SY 9,000.000 $0.500 $0.500 $0.750 $1.000 $0.400 $0.700 $0.500
BROADCAST SEED (TEMP_WARM)
SY 4,501.000 $0.400 $0.750 $0.750 $1.000 $0.400 $0.700 $1.000
BROADCAST SEED (TEMP_COOL)
SY 4,501.000 $0.300 $0.750 $0.750 $1.000 $0.400 $0.700 $1.000
VEGETATIVE WATERING
TGL 151.000 $60.000 $1.000 $29.710 $1.000 $50.000 $20.000 $1.000
CEMENT
TON 72.000 $320.000 $375.000 $224.920 $330.000 $550.000 $300.000 $350.000
CEMENT TRT (NEW BASE)(8")
SY 4,874.000 $8.000 $14.350 $10.600 $16.000 $15.000 $28.000 $8.000
PRIME COAT (MC-30)
GAL 1,184.000 $10.000 $25.000 $5.940 $22.000 $22.000 $14.000 $20.000
D-GR HMA TY-B PG64-22
TON 1,042.000 $115.000 $200.000 $279.090 $200.000 $200.000 $175.000 $180.000
D-GR HMA TY-D PG70-28
TON 1,120.000 $130.000 $220.000 $279.010 $225.000 $225.000 $225.000 $215.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 414.000 $49.000 $150.000 $84.310 $130.000 $140.000 $240.000 $75.000
PLANE ASPH CONC PAV(0" TO 2")
SY 1,956.000 $4.450 $10.000 $4.810 $8.000 $12.000 $2.500 $20.000
CUT & RESTORING PAV
SY 420.000 $263.000 $100.000 $175.220 $400.000 $220.000 $25.000 $200.000
CEM STABIL BKFL
CY 219.000 $512.000 $320.000 $194.740 $280.000 $300.000 $300.000 $300.000
TEMPORARY SPL SHORING
SF 6,780.000 $60.000 $28.000 $38.850 $65.000 $30.000 $55.000 $25.000
RIPRAP (MOW STRIP)(4 IN)
CY 77.000 $700.000 $750.050 $558.560 $1,100.000 $550.000 $750.000 $700.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 65.000 $175.000 $250.000 $98.800 $400.000 $250.000 $350.000 $280.000
RAIL (TY T631)
LF 510.000 $97.000 $95.000 $111.020 $105.000 $90.000 $100.000 $85.000
CONC BOX CULV (10 FT X 8 FT)
LF 174.000 $2,415.000 $2,000.000 $1,327.810 $1,250.000 $1,850.000 $2,000.000 $3,000.000
CONC BOX CULV (10 FT X 10 FT)
LF 232.000 $2,925.000 $2,150.000 $1,114.610 $1,350.000 $2,100.000 $2,200.000 $3,000.000
WINGWALL (PW - 1) (HW=10 FT)
EA 2.000 $60,000.000 $90,000.000 $54,841.430 $90,000.000 $80,000.000 $97,000.000 $100,000.000
WINGWALL (PW - 1) (HW=12 FT)
EA 2.000 $90,000.000 $100,000.000 $62,448.160 $100,000.000 $110,000.000 $110,000.000 $150,000.000
REMOV STR (WINGWALL)
EA 4.000 $1,770.000 $7,500.000 $1,534.150 $7,000.000 $15,000.000 $8,000.000 $8,000.000
REMOV STR (BOX CULVERT)
LF 322.000 $48.500 $150.000 $45.200 $230.000 $600.000 $1,000.000 $300.000
MOBILIZATION
LS 1.000 $237,827.330 $300,000.000 $340,559.560 $381,000.000 $380,000.000 $385,000.000 $350,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $16,000.000 $2,500.000 $35,365.100 $10,000.000 $25,000.000 $25,000.000 $30,000.000
TMA (STATIONARY)
DAY 35.000 $240.000 $250.000 $169.750 $150.000 $200.000 $500.000 $300.000
TMA (MOBILE OPERATION)
DAY 5.000 $195.000 $500.000 $169.750 $150.000 $400.000 $1,000.000 $300.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 444.000 $34.000 $10.000 $47.530 $50.000 $30.000 $42.000 $1.000
CONSTRUCTION EXITS (REMOVE)
SY 444.000 $12.000 $1.000 $12.450 $20.000 $12.000 $11.000 $1.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,565.000 $6.000 $4.000 $4.530 $5.000 $4.000 $4.000 $1.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,565.000 $2.000 $1.500 $1.130 $2.000 $2.000 $1.000 $1.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 990.000 $60.000 $70.000 $46.840 $65.000 $81.000 $105.000 $120.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 990.000 $5.000 $25.000 $9.340 $15.000 $20.000 $15.000 $30.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 990.000 $11.000 $35.000 $12.730 $30.000 $20.000 $22.000 $40.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 3,380.000 $0.210 $3.500 $4.020 $3.000 $3.000 $2.000 $4.000
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 1,690.000 $0.300 $3.500 $0.190 $3.000 $5.500 $2.000 $4.000
MTL W-BEAM GD FEN (TIM POST)
LF 725.000 $40.000 $26.000 $34.410 $25.000 $28.000 $35.000 $25.000
REMOVE METAL BEAM GUARD FENCE
LF 850.000 $2.750 $5.000 $2.550 $4.000 $4.000 $2.000 $2.500
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,500.000 $3,500.000 $2,803.790 $3,500.000 $3,500.000 $3,500.000 $3,200.000
GUARDRAIL END TREATMENT (REMOVE)
EA 8.000 $260.000 $500.000 $253.010 $400.000 $400.000 $215.000 $500.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $2,750.000 $1,500.000 $1,438.650 $2,000.000 $3,500.000 $2,500.000 $3,000.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,100.000 $1,365.000 $848.760 $1,500.000 $1,200.000 $1,500.000 $2,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $10,065.000 $22,000.000 $6,959.850 $10,000.000 $11,000.000 $9,000.000 $10,000.000
WIRE FENCE (TY C)
LF 1,320.000 $36.000 $25.000 $20.380 $40.000 $22.000 $35.000 $25.000
REPLACE EXISTING ALUMINUM SIGNS(TY A)
SF 27.000 $45.000 $100.000 $29.710 $50.000 $40.000 $35.000 $1,500.000
RELOCATE SM RD SN SUP&AM TY S80
EA 1.000 $650.000 $250.000 $657.790 $1,500.000 $1,000.000 $1,340.000 $2,000.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 58.000 $41.000 $50.000 $29.710 $30.000 $30.000 $40.000 $30.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 170.000 $0.300 $3.000 $5.660 $6.000 $1.200 $1.000 $5.000
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 22.000 $0.260 $5.000 $5.660 $6.000 $160.000 $1.250 $5.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 25.000 $0.300 $5.000 $5.660 $6.000 $1.300 $1.000 $5.000
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 600.000 $4.000 $8.000 $9.050 $9.000 $9.000 $8.000 $10.000
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 4,585.000 $1.000 $2.000 $2.260 $3.000 $1.500 $1.250 $2.000
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 24.000 $12.000 $15.000 $19.980 $16.000 $12.000 $10.000 $10.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 18,000.000 $1.300 $2.250 $1.700 $2.000 $1.600 $1.250 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 172.000 $0.500 $8.000 $9.050 $6.000 $3.600 $3.000 $5.000
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 3,380.000 $0.840 $2.000 $3.400 $4.000 $3.600 $3.000 $4.000
TY I HIGH PERF PM (Y)6"(BRK)(100MIL)
LF 430.000 $0.820 $2.000 $5.660 $6.000 $3.600 $3.000 $4.000
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 490.000 $0.860 $2.000 $5.660 $6.000 $3.600 $3.000 $4.000
PAVEMENT SLER 6"
LF 4,300.000 $0.230 $1.250 $1.130 $1.500 $0.700 $0.500 $1.000
REFL PAV MRKR TY II-A-A
EA 29.000 $3.550 $25.000 $16.980 $16.000 $12.000 $10.000 $15.000
ELIM EXT PM & MRKS (4")
LF 375.000 $0.250 $1.500 $0.640 $12.000 $10.000 $1.000 $5.000
BONDING COURSE
GAL 600.000 $5.000 $6.000 $4.150 $4.000 $5.000 $15.000 $5.000
Totals: $3,410,628.650 $3,345,238.250 $3,433,345.810 $3,812,320.000 $3,854,655.000 $4,100,121.150 $4,100,588.000