ANGELINA US0059 (6407-98-001)

Items: 44

County: ANGELINA
Length: N/A
Highway: US0059
District: LUFKIN
Control Number: 6407-98-001
DBE Goal: N/A
Project: RMC - 640798001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $262,350.00
Date: 07/06/2022 (3 years ago)
Contract Number: N/A
Type: TRAFFIC SIGNAL MAINTENANCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (1)
E
Engineer's Estimate
$262,350.00
$242,776.99
Over/Under Est: -7.46% -$19,573.01

Bid Items & Bid Tabulations

44 Total 0 of 44
ANGELINA  |  US0059  |  LUFKIN  |  6407-98-001  |  07/06/2022  |  $262,350.00  |  RMC - 640798001  |  TRAF SIGNAL MAINT  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BAY CITY TRAFFIC
MOBILIZATION (CALLOUT)
EA 6.000 $1,000.000 $1,200.000
CONC SIDEWALKS (4")
SY 20.000 $65.000 $70.000
CONDT (PVC) (SCH 80) (2")
LF 150.000 $13.000 $11.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 300.000 $15.000 $12.000
CONDT (PVC) (SCH 80) (4")
LF 150.000 $25.000 $17.000
CONDT (PVC) (SCH 80) (4") (BORE)
LF 300.000 $30.000 $18.000
ELEC CONDR (NO.8) BARE
LF 1,500.000 $1.100 $1.000
ELEC CONDR (NO.8) INSULATED
LF 1,000.000 $1.400 $1.350
ELEC CONDR (NO.6) INSULATED
LF 300.000 $1.900 $1.650
GROUND BOX TY D (162922)W/APRON
EA 3.000 $670.000 $807.666
REMOVE ELECTRICAL SERVICES
EA 5.000 $450.000 $220.000
ELC SRV TY D 120/240 070(NS)SS(E)SP(O)
EA 3.000 $6,500.000 $6,200.000
ELC SRV TY T 120/240 000(NS)GS(N)SP(O)
EA 3.000 $4,500.000 $5,200.000
ELC SRV TY T 120/240 000(NS)GS(N)TP(O)
EA 3.000 $3,500.000 $2,500.000
PED SIG SEC (LED)(COUNTDOWN)
EA 20.000 $300.000 $470.000
BACKPLATE W/REFL BRDR(4 SEC)
EA 30.000 $130.000 $145.000
BACKPLATE W/REFL BRDR(5 SEC)
EA 15.000 $145.000 $160.000
BACKPLATE W/REFL BRDR(3 SEC)
EA 60.000 $90.000 $135.000
TRF SIG CBL (TY A)(14 AWG)(2 CONDR)
LF 2,000.000 $1.500 $1.350
TRF SIG CBL (TY A)(14 AWG)(3 CONDR)
LF 1,000.000 $1.800 $1.450
TRF SIG CBL (TY A)(14 AWG)(4 CONDR)
LF 2,000.000 $2.000 $1.750
TRF SIG CBL (TY A)(14 AWG)(7 CONDR)
LF 1,000.000 $3.000 $2.050
INSTALL RDSD FLASH BEACON ASSEMBLY
EA 5.000 $3,000.000 $3,200.000
REMOVAL OF GROUND BOXES
EA 5.000 $250.000 $200.000
INSTALL OF SPAN CABLE ASSM
LF 500.000 $2.000 $3.000
REPLACE OF SIGNAL HEAD ASSM
EA 50.000 $325.000 $225.000
REPLACE OF PEDESTRIAN PUSH BUTTONS
EA 8.000 $150.000 $150.000
INSTALL OF FND FOR GROUND MNT CABINETS
EA 4.000 $2,000.000 $1,800.000
REPLACE OF CONTROL CABINET(POLE MNT)
EA 1.000 $1,500.000 $1,200.000
REPLACE OF SIGNAL POLE ASSM
EA 4.000 $7,500.000 $8,000.000
REMOVAL OF CONCRETE FOUNDATIONS
EA 6.000 $700.000 $345.000
INS OF TRF SIG PL FND (30" DRIL SHFT)
LF 33.000 $265.000 $220.000
INS OF TRF SIG PL FND (36" DRIL SHFT)
LF 30.000 $335.000 $270.000
INSTL PED POLE ASSM
EA 3.000 $1,700.000 $1,650.000
VIVDS CABLE (INSTALL)
LF 1,500.000 $2.000 $1.000
BBU SYSTEM (EXTERNAL BATT CABINET)
EA 4.000 $6,250.000 $6,250.000
REPLACE BBU BATTERIES
EA 6.000 $2,100.000 $1,500.000
TMA (STATIONARY)
DAY 20.000 $300.000 $300.000
LANE CLOSURE (SETUP AND REMOV)(TY 3)
EA 2.000 $800.000 $225.000
LANE CLOSURE (SETUP AND REMOV)(TY 9)
EA 2.000 $850.000 $227.500
LANE CLOSURE (SETUP AND REMOV)(TY 12)
EA 2.000 $900.000 $262.000
LANE CLOSURE (MAINTENANCE) (TY 3)
HR 8.000 $50.000 $75.000
LANE CLOSURE (MAINTENANCE) (TY 9)
HR 8.000 $50.000 $75.000
LANE CLOSURE (MAINTENANCE) (TY 12)
HR 8.000 $50.000 $75.000
Totals: $262,350.000 $242,776.998