Bid Cobra

ANGELINA FM 1194 (2960-01-012)

Items: 46

County: ANGELINA
Length: N/A
Highway: FM 1194
District: LUFKIN
Control Number: 2960-01-012
DBE Goal: N/A
Project: STP 2018(254)HES
Guaranty: N/A
Time: 50 WORKING DAYS
Engineer's Estimate: $449,923.90
Date: 11/02/2017 (8 years ago)
Contract Number: N/A
Type: PROVIDE ADDITIONAL PAVED SURF WIDTH
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (8)
E
Engineer's Estimate
$449,923.90
$459,200.62
Over/Under Est: 2.06% $9,276.72
Over/Under Est: 9.4% $42,272.86
Amt Left: 7.19% $32,996.14
Over/Under Est: 20.25% $91,108.50
Amt Left: 17.82% $81,831.78
Delta: -9.92% -$48,835.64
Over/Under Est: 26.18% $117,784.32
Amt Left: 23.63% $108,507.60
Delta: -4.93% -$26,675.82
Over/Under Est: 46.33% $208,440.92
Amt Left: 43.37% $199,164.20
Delta: -15.97% -$90,656.60
Over/Under Est: 59.41% $267,279.10
Amt Left: 56.19% $258,002.38
Delta: -8.94% -$58,838.18
Over/Under Est: 79.37% $357,101.80
Amt Left: 75.75% $347,825.08
Delta: -12.52% -$89,822.70
Over/Under Est: 111.93% $503,598.90
Amt Left: 107.65% $494,322.18
Delta: -18.15% -$146,497.10

Bid Items & Bid Tabulations

46 Total 0 of 46
ANGELINA  |  FM 1194  |  LUFKIN  |  2960-01-012  |  11/02/2017  |  $449,923.90  |  STP 2018(254)HES  |  PROVIDE ADDITIONAL PAVED SURF WIDTH  |  50 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PINTO CONSTRUCTION CO., INC.
MOORE BROTHERS CONSTRUCTION COMPANY
A. L. HELMCAMP, INC.
DREWERY CONSTRUCTION COMPANY, INCORPORATED
LONGVIEW BRIDGE AND ROAD, LTD.
L. S. EQUIPMENT CO., INC.
STATELINE CONSTRUCTION, LLC
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 34.000 $400.000 $350.000 $565.000 $1,100.000 $285.000 $600.000 $1,000.000 $1,000.000 $1,200.000
SUBGRADE WIDENING (ORD COMP)
STA 34.000 $150.000 $250.000 $288.240 $550.000 $480.000 $600.000 $400.000 $525.000 $750.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 24.000 $30.000 $25.000 $25.000 $36.000 $38.000 $40.000 $75.000 $200.000 $35.000
BACKFILL (TY B)
STA 34.000 $100.000 $200.000 $292.650 $500.000 $110.000 $220.000 $500.000 $475.000 $250.000
SPEC EXCAV WORK (HYD EXCAVATOR)
HR 4.000 $200.000 $150.000 $150.000 $84.000 $200.000 $235.000 $100.000 $125.000 $150.000
BLOCK SODDING
SY 250.000 $5.000 $7.000 $6.600 $6.300 $8.000 $8.000 $5.000 $7.000 $5.500
BROADCAST SEED (TEMP) (WARM)
SY 20,278.000 $0.150 $0.140 $0.130 $0.050 $0.010 $0.120 $0.500 $1.000 $0.500
BROADCAST SEED (TEMP) (COOL)
SY 20,278.000 $0.150 $0.140 $0.130 $0.050 $0.010 $0.120 $0.500 $1.000 $0.500
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
SY 40,556.000 $0.250 $0.350 $0.310 $0.150 $0.010 $0.350 $0.500 $3.000 $0.500
VEGETATIVE WATERING
MG 1,628.600 $15.000 $0.010 $5.000 $1.000 $1.000 $25.000 $10.000 $12.000 $38.000
CEM TRT(PLNT MX) (CLN)(TYA)(GR1-2)(10")
SY 2,254.000 $40.000 $40.000 $42.170 $47.000 $75.000 $65.000 $5.000 $46.000 $60.000
ASPH (RC-250)
GAL 752.000 $3.500 $4.700 $12.000 $6.500 $6.700 $7.500 $5.000 $18.500 $8.000
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 4,101.000 $3.500 $5.000 $4.250 $3.700 $2.800 $4.500 $5.000 $6.500 $8.000
AGGR (TY-PE, E, L OR PL GR 3)
CY 89.000 $110.000 $140.000 $100.000 $140.000 $200.000 $250.000 $250.000 $500.000 $300.000
AGGR (TY E OR L GR 5)
CY 24.000 $110.000 $300.000 $300.000 $250.000 $320.000 $500.000 $250.000 $500.000 $300.000
SUPERPAVE MIXTURES SP-C SAC-A PG70-22
TON 806.000 $95.000 $110.000 $107.510 $102.000 $135.000 $108.000 $125.000 $139.000 $140.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
SY 800.000 $60.000 $48.000 $72.830 $72.000 $50.000 $60.000 $200.000 $34.000 $200.000
CUT & RESTORE ASPH PAVING
SY 15.000 $120.000 $137.500 $142.000 $130.000 $88.000 $190.000 $250.000 $125.000 $200.000
CUT AND RESTORE PAV (FLEX BASE)
SY 21.000 $50.000 $99.000 $100.000 $95.000 $51.000 $90.000 $200.000 $65.000 $100.000
CL C CONC (COLLAR)
EA 1.000 $300.000 $1,100.000 $1,200.000 $1,100.000 $1,300.000 $2,500.000 $800.000 $3,000.000 $1,500.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 6.000 $150.000 $230.000 $235.000 $230.000 $210.000 $260.000 $500.000 $225.000 $185.000
RC PIPE (CL III)(18 IN)
LF 112.000 $40.000 $60.000 $61.000 $56.000 $53.000 $75.000 $50.000 $65.000 $85.000
RC PIPE (CL III)(24 IN)
LF 12.000 $75.000 $88.000 $90.000 $83.000 $82.000 $130.000 $75.000 $95.000 $105.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 18.000 $500.000 $770.000 $770.000 $730.000 $660.000 $700.000 $1,500.000 $850.000 $1,850.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 4.000 $700.000 $880.000 $880.000 $850.000 $785.000 $1,000.000 $1,500.000 $1,000.000 $2,500.000
REMOV STR (PIPE)
EA 5.000 $200.000 $330.000 $330.000 $320.000 $240.000 $800.000 $50.000 $500.000 $500.000
MOBILIZATION
LS 1.000 $45,000.000 $35,000.000 $38,000.000 $42,000.000 $63,000.000 $60,000.000 $50,000.000 $70,000.000 $90,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $2,000.000 $1,050.000 $1,455.000 $5,000.000 $1,450.000 $4,000.000 $1,400.000 $3,500.000 $8,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 778.000 $3.000 $4.000 $3.850 $3.000 $3.700 $4.000 $5.000 $3.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 778.000 $1.000 $1.000 $1.100 $0.800 $1.050 $1.000 $1.000 $1.000 $2.000
DRIVEWAYS (ACP)
SY 525.000 $40.000 $30.000 $27.810 $37.000 $30.000 $35.000 $125.000 $40.000 $42.000
TURNOUTS (ACP)
SY 324.000 $55.000 $65.000 $48.780 $47.000 $65.000 $65.000 $125.000 $52.000 $42.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 6.000 $350.000 $200.000 $193.000 $165.000 $185.000 $235.000 $800.000 $400.000 $650.000
MAILBOX INSTALL-D (WC-POST) TY 3
EA 1.000 $800.000 $210.000 $203.000 $185.000 $195.000 $250.000 $800.000 $1,000.000 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 1.000 $700.000 $680.000 $705.000 $800.000 $672.000 $860.000 $700.000 $1,000.000 $650.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 8.000 $500.000 $294.000 $310.000 $380.000 $294.000 $380.000 $900.000 $550.000 $650.000
REMOVE SM RD SN SUP&AM
EA 9.000 $100.000 $90.000 $82.000 $75.000 $80.000 $100.000 $900.000 $250.000 $60.000
INSTL DEL ASSN (OM-2Z)(FLX)(WAP)
EA 6.000 $60.000 $135.000 $135.000 $70.000 $130.000 $150.000 $200.000 $75.000 $100.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 3,380.000 $1.000 $1.650 $0.010 $1.000 $1.600 $2.000 $1.500 $1.750 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 338.000 $1.000 $1.500 $1.000 $1.000 $1.600 $2.000 $1.000 $2.750 $5.000
WK ZN PAV MRK SHT TERM RMV (Y)(4")
LF 85.000 $1.000 $3.300 $3.000 $1.000 $1.300 $4.000 $4.000 $5.000 $20.000
REF PROF PAV MRK TY I(W)4"(SLD)(090MIL)
LF 6,760.000 $0.500 $1.650 $1.650 $1.600 $1.600 $2.000 $1.500 $1.750 $2.000
REF PROF PAV MRK TY I(Y)4"(SLD)(090MIL)
LF 5,070.000 $0.500 $1.650 $1.650 $1.600 $1.600 $2.000 $1.500 $1.750 $2.000
REF PROF PAV MRK TY I(Y)4"(BRK)(090MIL)
LF 90.000 $0.500 $3.300 $3.300 $3.200 $3.150 $4.000 $3.000 $3.500 $2.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 12.000 $11.000 $16.500 $16.500 $16.000 $16.000 $20.000 $15.000 $20.000 $20.000
REFL PAV MRKR TY II-A-A
EA 85.000 $4.000 $4.400 $4.400 $4.500 $4.200 $5.000 $4.000 $5.000 $15.000
Totals: $449,923.900 $459,200.626 $492,196.760 $541,032.400 $567,708.220 $658,364.820 $717,203.000 $807,025.700 $953,522.800