ANGELINA VA (0911-00-139)
Items: 47
County: ANGELINA
Length: N/A
Highway: VA
District: LUFKIN
Control Number: 0911-00-139
DBE Goal: 0.0%
Project: C 911-00-139
Guaranty: N/A
Time: 170 WORKING DAYS
Engineer's Estimate: $1,936,690.50
Date: 06/05/2024 (2 years ago)
Contract Number: N/A
Type: TRAFFIC SIGNAL IMPROVEMENTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (4)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,936,690.50 | |||
| $1,611,271.97 |
-16.8%
-$325,418.53
|
|||
| $1,923,405.50 |
-0.69%
-$13,285.00
|
19.37%
$312,133.53
|
||
| $1,980,121.75 |
2.24%
$43,431.25
|
22.89%
$368,849.78
|
-2.95%
-$56,716.25
|
|
| $2,276,516.70 |
17.55%
$339,826.20
|
41.29%
$665,244.73
|
-14.97%
-$296,394.95
|
E
Engineer's Estimate
$1,936,690.50
1
Awarded
$1,611,271.97
Over/Under Est:
-16.8%
-$325,418.53
$1,923,405.50
Over/Under Est:
-0.69%
-$13,285.00
Amt Left:
19.37%
$312,133.53
$1,980,121.75
Over/Under Est:
2.24%
$43,431.25
Amt Left:
22.89%
$368,849.78
Delta:
-2.95%
-$56,716.25
$2,276,516.70
Over/Under Est:
17.55%
$339,826.20
Amt Left:
41.29%
$665,244.73
Delta:
-14.97%
-$296,394.95
| Subcontractor | Percentage | Amount |
|---|---|---|
| BAY CITY TRAFFIC | 26.10% | $424,441.56 |
| Total: | 26.10% | $424,441.56 |
Bid Items & Bid Tabulations
47
Total
0 of 47