ANGELINA VA (0911-00-123)

Items: 48

County: ANGELINA
Length: N/A
Highway: VA
District: LUFKIN
Control Number: 0911-00-123
DBE Goal: 300.0%
Project: F 2024(103)
Guaranty: N/A
Time: 110 WORKING DAYS
Engineer's Estimate: $1,916,703.50
Date: 07/09/2024 (1 year ago)
Contract Number: N/A
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$1,916,703.50
$1,672,687.00
Over/Under Est: -12.73% -$244,016.50
$1,942,278.21
Over/Under Est: 1.33% $25,574.71
Amt Left: 16.12% $269,591.21
$1,987,694.63
Over/Under Est: 3.7% $70,991.13
Amt Left: 18.83% $315,007.63
Delta: -2.34% -$45,416.42
$2,066,750.00
Over/Under Est: 7.83% $150,046.50
Amt Left: 23.56% $394,063.00
Delta: -3.98% -$79,055.37
Over/Under Est: 33.7% $645,894.50
Amt Left: 53.2% $889,911.00
Delta: -23.99% -$495,848.00
Subcontractor Percentage Amount
TEX-BRASKA, LLC 3.74% $62,558.49
EJT HAULING LLC 0.93% $15,555.99
AMERICAN REMEDIATION OPTIONS, INC. 0.53% $8,865.24
Total: 5.20% $86,979.72

Bid Items & Bid Tabulations

48 Total 0 of 48
ANGELINA  |  VA  |  LUFKIN  |  0911-00-123  |  07/09/2024  |  $1,916,703.50  |  F 2024(103)  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  110 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GARRET SHIELDS INFRASTRUCTURE
THK CONSTRUCTION LLC
TI-ZACK CONCRETE, LLC
RHINO EQUITY, LLC
TIGHT LINE CONSTRUCTION, LLC
PREPARING ROW
STA 135.000 $500.000 $1,000.000 $1,000.000 $1,114.670 $2,088.000 $1,500.000
REMOVING CONC (DRIVEWAYS)
SY 920.000 $15.000 $40.000 $30.000 $32.710 $40.000 $55.000
REMOVING CONC (CURB)
LF 362.000 $10.000 $20.000 $10.000 $10.390 $20.000 $55.000
REMOVING CONC (CURB AND GUTTER)
LF 36.000 $120.000 $20.000 $50.000 $20.900 $30.000 $150.000
REMOVING CONC (SIDEWALK OR RAMP)
SY 93.000 $100.000 $40.000 $30.000 $16.180 $40.000 $75.000
REMOVING STAB BASE AND ASPH PAV (6")
SY 2,014.000 $10.000 $10.000 $10.000 $18.680 $40.000 $50.000
EXCAVATION (ROADWAY)
CY 1,214.000 $35.000 $40.000 $20.000 $61.980 $18.000 $45.000
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 200.000 $50.000 $40.000 $20.000 $37.620 $45.000 $125.000
SPEC EXCAV WORK (HYD EXCAVATOR)
HR 3.000 $200.000 $120.000 $150.000 $110.000 $150.000 $350.000
FURNISHING AND PLACING TOPSOIL (4")
SY 4,053.000 $5.500 $5.000 $4.500 $4.400 $5.000 $15.000
BLOCK SODDING
SY 4,053.000 $10.000 $12.000 $8.668 $5.500 $7.000 $9.000
VEGETATIVE WATERING
MG 162.000 $30.000 $200.000 $10.000 $1.100 $10.000 $50.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 675.000 $300.000 $100.000 $180.000 $115.500 $110.000 $100.000
RIPRAP (CONC)(4 IN)
CY 1.000 $650.000 $1,000.000 $3,000.000 $802.660 $900.000 $1,800.000
RAIL (HANDRAIL)(TY E)
LF 60.000 $210.000 $200.000 $362.250 $330.000 $300.000 $250.000
RAIL (TY PR11)
LF 150.000 $210.000 $200.000 $209.750 $176.000 $250.000 $250.000
INLET (COMP) (TY SIDEWALK BRIDGE)
EA 4.000 $20,000.000 $5,000.000 $8,000.000 $10,513.650 $3,000.000 $25,000.000
ADJUSTING INLETS
EA 1.000 $3,250.000 $3,000.000 $5,000.000 $752.400 $1,000.000 $1,500.000
ADJUSTING MANHOLES & INLETS
EA 3.000 $2,500.000 $2,000.000 $4,000.000 $752.400 $1,000.000 $1,500.000
ADJUSTING MANHOLES (ELECTRIC BOX)
EA 3.000 $1,750.000 $1,000.000 $1,000.000 $752.400 $1,500.000 $1,500.000
REMOV STR (SET)
EA 1.000 $1,000.000 $1,000.000 $500.000 $165.000 $1,000.000 $5,000.000
MOBILIZATION
LS 1.000 $200,000.000 $175,000.000 $190,000.000 $161,624.930 $200,000.000 $200,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $3,500.000 $1,000.000 $2,975.010 $3,850.000 $8,000.000 $3,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 6,588.000 $5.000 $5.000 $5.000 $0.110 $5.000 $8.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 6,588.000 $1.500 $2.000 $1.000 $0.110 $1.500 $4.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 30.000 $15.000 $4.000 $15.000 $5.500 $6.000 $15.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 30.000 $3.000 $2.000 $1.000 $5.500 $2.000 $3.000
CONC CURB (TY I)
LF 857.000 $120.000 $40.000 $30.000 $57.730 $30.000 $75.000
CONC CURB & GUTTER (TY II)
LF 36.000 $180.000 $50.000 $60.000 $57.730 $40.000 $100.000
CONC CURB (TY C1)
LF 650.000 $100.000 $50.000 $45.000 $95.260 $150.000 $100.000
CONC CURB (TY F2)
LF 150.000 $100.000 $40.000 $45.000 $190.520 $250.000 $100.000
DRIVEWAYS (CONC)
SY 898.000 $175.000 $100.000 $95.000 $127.540 $140.000 $80.000
DRIVEWAYS (ACP)
SY 2,250.000 $50.000 $60.000 $150.000 $84.700 $90.000 $75.000
CONC SIDEWALKS (5")
SY 5,833.000 $75.000 $90.000 $90.000 $127.540 $80.000 $150.000
CONC SIDEWALKS (6")
SY 131.000 $120.000 $100.000 $90.000 $150.440 $90.000 $200.000
CURB RAMPS (TY 5)
EA 4.000 $3,500.000 $3,000.000 $4,000.000 $1,978.500 $3,000.000 $3,000.000
CURB RAMPS (TY 10)
EA 8.000 $3,200.000 $3,000.000 $4,000.000 $1,978.500 $2,500.000 $3,500.000
MAILBOX INSTALL-S (TIM-POST) TY 5
EA 21.000 $350.000 $400.000 $366.300 $550.000 $500.000 $500.000
MAILBOX INSTALL-D (TWG-POST) TY 4
EA 3.000 $500.000 $500.000 $372.900 $550.000 $600.000 $500.000
MAILBOX INSTALL-M (TWG-POST) TY 4
EA 3.000 $700.000 $500.000 $687.500 $550.000 $600.000 $500.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 4.000 $1,000.000 $800.000 $874.500 $550.000 $700.000 $850.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $1,200.000 $1,000.000 $1,186.900 $550.000 $700.000 $1,250.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 24.000 $600.000 $500.000 $448.800 $165.000 $700.000 $700.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 1.000 $800.000 $500.000 $568.700 $550.000 $700.000 $850.000
RELOCATE SM RD SN SUP&AM TY S80
EA 2.000 $700.000 $500.000 $744.700 $165.000 $300.000 $850.000
REMOVE SM RD SN SUP&AM
EA 29.000 $125.000 $100.000 $250.000 $165.000 $200.000 $250.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $20,000.000 $1,000.000 $20,000.000 $1.100 $15,000.000 $17,000.000
TMA (STATIONARY)
DAY 92.000 $250.000 $300.000 $300.000 $1.100 $200.000 $350.000
Totals: $1,916,703.500 $1,672,687.000 $1,942,278.214 $1,987,694.630 $2,066,750.000 $2,562,598.000