ANGELINA FM 58 (0576-02-068)

Items: 87

County: ANGELINA
Length: N/A
Highway: FM 58
District: LUFKIN
Control Number: 0576-02-068
DBE Goal: N/A
Project: F 2023(668)
Guaranty: N/A
Time: 331 WORKING DAYS
Engineer's Estimate: $7,487,233.79
Date: 05/05/2023 (3 years ago)
Contract Number: N/A
Type: HIGHWAY IMPROVEMENT
Mail/Deliver Bids To: N/A
JESSE SISCO
SHANNON RAMOS
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$7,487,233.79
$9,734,197.56
Over/Under Est: 30.01% $2,246,963.77
Over/Under Est: 31.35% $2,347,186.59
Amt Left: 1.03% $100,222.82
Subcontractor Percentage Amount
A R BROTHERS CONSTRUCTION SERVICES, INC. 13.23% $1,296,781.55
PINTO CONSTRUCTION CO., INC. 8.50% $833,155.19
COLD CREEK CONSTRUCTION, LTD 2.65% $259,748.38
J. H. ODEN CONTRACTING COMPANY 1.51% $148,007.57
STRIPING TECHNOLOGY, L.P. 1.12% $109,780.45
H4 CONSTRUCTION SERVICES, LLC 0.69% $67,632.60
MURRAY CONSTRUCTION 0.51% $49,989.31
PANOLA SIGN & BARRICADE, INC. 0.35% $34,306.39
WEST TEXAS ROCK RESOURCES, LLC 0.14% $13,722.56
Total: 28.70% $2,813,124.00

Bid Items & Bid Tabulations

87 Total 0 of 87
ANGELINA  |  FM 58  |  LUFKIN  |  0576-02-068  |  05/05/2023  |  $7,487,233.79  |  F 2023(668)  |  HWY IMPRV  |  331 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
A. L. HELMCAMP, INC.
DREWERY CONSTRUCTION COMPANY, INCORPORATED
PREPARING ROW
STA 329.000 $1,200.000 $1,250.000 $1,500.000
REMOVING CONC (DRIVEWAYS)
SY 42.000 $25.000 $30.500 $160.000
SUBGRADE WIDENING (ORD COMP)
STA 328.000 $400.000 $625.000 $400.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 25,870.000 $18.000 $26.000 $16.750
BLADING
STA 328.000 $275.000 $350.000 $230.000
SPEC EXCAV WORK (HYD EXCAVATOR)
HR 175.000 $110.000 $63.000 $230.000
BLOCK SODDING
SY 3,352.000 $5.000 $6.000 $7.350
BROADCAST SEED (TEMP) (WARM)
SY 36,527.000 $0.150 $0.190 $0.160
BROADCAST SEED (TEMP) (COOL)
SY 36,527.000 $0.150 $0.190 $0.160
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 73,054.000 $0.550 $0.630 $0.900
VEGETATIVE WATERING
MG 3,001.000 $10.000 $1.000 $8.000
SPRINKLING (DUST CONTROL)
MG 1,023.000 $0.500 $1.000 $14.000
FL BS (RDWY DEL)(TY D GR 1-2 OR GR 5)
TON 9,841.000 $55.000 $53.000 $61.000
CEMENT
TON 1,836.000 $250.000 $260.000 $253.000
CEMENT TREAT(MX EXST MTL & NW BS)(12")
SY 102,300.000 $4.250 $6.500 $6.500
ASPH (RC-250)
TON 110.000 $1,425.000 $1,000.000 $1,130.000
AGGR (TY PE OR PL GR 4)
CY 758.000 $190.000 $277.000 $215.000
AGGR (TY E OR L GR 5)
CY 732.000 $190.000 $233.000 $230.000
ASPH (AC-15P OR CRS-2P)
TON 183.000 $1,000.000 $900.000 $1,165.000
CEM STABIL BKFL
CY 222.000 $200.000 $273.000 $275.000
CUT & RESTORE CONC PAVING
SY 62.000 $120.000 $151.000 $151.200
TRENCH EXCAVATION PROTECTION
LF 953.000 $7.500 $20.000 $19.950
TEMPORARY SPL SHORING
SF 132.000 $45.000 $23.000 $65.000
CL C CONC (COLLAR)
EA 16.000 $1,000.000 $945.000 $945.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 42.000 $200.000 $215.000 $225.000
CONC BOX CULV (3 FT X 3 FT)
LF 20.000 $350.000 $787.000 $790.000
CONC BOX CULV (4 FT X 3 FT)
LF 27.000 $500.000 $787.000 $787.500
CONC BOX CULV (6 FT X 3 FT)
LF 168.000 $700.000 $1,050.000 $1,050.000
RC PIPE (CL III)(18 IN)
LF 2,884.000 $50.000 $72.500 $75.000
RC PIPE (CL III)(24 IN)
LF 386.000 $75.000 $99.000 $115.000
RC PIPE (CL III)(30 IN)
LF 218.000 $130.000 $163.000 $173.000
RC PIPE (CL III)(36 IN)
LF 22.000 $160.000 $188.000 $200.000
INLET(COMPL)(PAZD)(FG)(3FTX3FT-3FTX3FT)
EA 2.000 $5,250.000 $6,825.000 $8,000.000
HEADWALL (CH - PW - S) (DIA= 24 IN)
EA 1.000 $12,000.000 $6,676.000 $9,000.000
WINGWALL (FW - 0) (HW=3 FT)
EA 2.000 $12,000.000 $10,292.000 $11,000.000
WINGWALL (FW - 0) (HW=4 FT)
EA 4.000 $10,000.000 $11,087.000 $11,086.950
WINGWALL (FW - 0) (HW=8 FT)
EA 1.000 $19,000.000 $25,200.000 $28,000.000
WINGWALL (PW - 2) (HW=4 FT)
EA 2.000 $11,000.000 $14,700.000 $14,700.000
WINGWALL (PW - 2) (HW=8 FT)
EA 1.000 $25,000.000 $31,500.000 $31,500.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 8.000 $650.000 $840.000 $900.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 202.000 $750.000 $998.000 $1,150.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 9.000 $1,100.000 $1,260.000 $1,400.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 1.000 $2,750.000 $1,470.000 $1,575.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 26.000 $1,200.000 $1,575.000 $1,725.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 6.000 $1,750.000 $2,310.000 $2,455.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 6.000 $3,500.000 $2,888.000 $3,250.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 2.000 $5,500.000 $6,563.000 $7,000.000
CLEAN EXIST CULVERTS
EA 11.000 $1,410.000 $1,470.000 $1,575.000
REMOV STR (PIPE)
EA 111.000 $250.000 $525.000 $700.000
MOBILIZATION
LS 1.000 $680,000.000 $825,000.000 $1,000,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 20.000 $1,500.000 $11,000.000 $14,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 560.000 $36.000 $38.000 $41.000
ROCK FILTER DAMS (REMOVE)
LF 560.000 $10.000 $10.000 $13.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 224.000 $25.000 $10.000 $29.000
CONSTRUCTION EXITS (REMOVE)
SY 224.000 $11.500 $5.000 $13.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 7,992.000 $3.150 $4.000 $3.150
TEMP SEDMT CONT FENCE (REMOVE)
LF 7,992.000 $0.800 $0.800 $1.050
DRIVEWAYS (CONC)
SY 627.000 $115.000 $159.000 $168.000
DRIVEWAYS (ACP)
SY 10,681.000 $45.000 $84.000 $65.000
TURNOUTS (SURF TREAT)
SY 1,514.000 $45.000 $49.000 $100.000
RUMBLE STRIPS (SHOULDER)
LF 65,764.000 $0.200 $0.220 $0.180
RUMBLE STRIPS (CENTERLINE)
LF 32,882.000 $0.350 $0.220 $0.170
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 4.000 $550.000 $472.000 $575.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 46.000 $250.000 $157.000 $310.000
MAILBOX INSTALL-D (WC-POST) TY 3
EA 19.000 $250.000 $210.000 $310.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 1.000 $730.000 $651.000 $720.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 7.000 $1,000.000 $719.000 $790.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 7.000 $1,100.000 $913.000 $980.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 21.000 $455.000 $457.000 $405.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 15.000 $550.000 $504.000 $485.000
REMOVE SM RD SN SUP&AM
EA 51.000 $100.000 $79.000 $175.000
INSTL OM ASSM (OM-2Z)(WFLX)SRF(BI)
EA 42.000 $110.000 $142.000 $95.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 65,548.000 $0.380 $0.260 $0.260
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 65,548.000 $0.600 $1.640 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,292.000 $0.900 $3.200 $2.600
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 85.000 $1.100 $2.100 $2.100
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
LF 65,616.000 $0.600 $0.860 $0.850
RE PM W/RET REQ TY I (Y)6"(BRK)(090MIL)
LF 5,791.000 $0.600 $1.000 $1.000
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
LF 35,645.000 $0.590 $0.860 $0.850
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 15.000 $15.000 $32.000 $31.500
PREFAB PAV MRK TY C (Y) (24") (SLD)
LF 71.000 $15.000 $21.000 $21.000
REFL PAV MRKR TY II-A-A
EA 680.000 $4.600 $4.250 $4.200
SP MIXES SP-C SAC-A PG70-22
TON 11,254.000 $140.000 $180.000 $188.000
BONDING COURSE
GAL 5,116.000 $5.000 $4.000 $5.500
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,500.000 $25,000.000 $31,500.000
TMA (STATIONARY)
DAY 662.000 $175.000 $235.000 $110.000
TMA (MOBILE OPERATION)
DAY 10.000 $150.000 $285.000 $50.000
Totals: $7,487,233.790 $9,734,197.560 $9,834,420.380