ANGELINA US 69 (0200-02-042)
Items: 11
County: ANGELINA
Length: N/A
Highway: US 69
District: LUFKIN
Control Number: 0200-02-042
DBE Goal: N/A
Project: NH 1702(519)
Guaranty: N/A
Time: 109 WORKING DAYS
Engineer's Estimate: $1,113,175.85
Date: 07/12/2017 (8 years ago)
Contract Number: N/A
Type: CLEARING AND GRUBBING
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (12)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,113,175.85 | |||
| $890,456.22 |
-20.01%
-$222,719.63
|
|||
| $1,161,178.72 |
4.31%
$48,002.87
|
30.4%
$270,722.50
|
||
| $1,188,479.10 |
6.76%
$75,303.25
|
33.47%
$298,022.88
|
-2.35%
-$27,300.38
|
|
| $1,537,581.67 |
38.13%
$424,405.82
|
72.67%
$647,125.45
|
-29.37%
-$349,102.57
|
|
| $1,552,014.75 |
39.42%
$438,838.90
|
74.29%
$661,558.53
|
-0.94%
-$14,433.08
|
|
| $1,631,689.75 |
46.58%
$518,513.90
|
83.24%
$741,233.53
|
-5.13%
-$79,675.00
|
|
| $1,681,309.85 |
51.04%
$568,134.00
|
88.81%
$790,853.63
|
-3.04%
-$49,620.10
|
|
| $1,756,655.13 |
57.81%
$643,479.28
|
97.28%
$866,198.91
|
-4.48%
-$75,345.28
|
|
| $2,041,497.43 |
83.39%
$928,321.58
|
129.26%
$1,151,041.21
|
-16.22%
-$284,842.30
|
|
| $2,422,295.25 |
117.6%
$1,309,119.40
|
172.03%
$1,531,839.03
|
-18.65%
-$380,797.82
|
|
| $2,749,119.14 |
146.96%
$1,635,943.29
|
208.73%
$1,858,662.92
|
-13.49%
-$326,823.89
|
|
| $3,182,203.30 |
185.87%
$2,069,027.45
|
257.37%
$2,291,747.08
|
-15.75%
-$433,084.16
|
E
Engineer's Estimate
$1,113,175.85
1
Awarded
$890,456.22
Over/Under Est:
-20.01%
-$222,719.63
$1,161,178.72
Over/Under Est:
4.31%
$48,002.87
Amt Left:
30.4%
$270,722.50
$1,188,479.10
Over/Under Est:
6.76%
$75,303.25
Amt Left:
33.47%
$298,022.88
Delta:
-2.35%
-$27,300.38
$1,537,581.67
Over/Under Est:
38.13%
$424,405.82
Amt Left:
72.67%
$647,125.45
Delta:
-29.37%
-$349,102.57
$1,552,014.75
Over/Under Est:
39.42%
$438,838.90
Amt Left:
74.29%
$661,558.53
Delta:
-0.94%
-$14,433.08
$1,631,689.75
Over/Under Est:
46.58%
$518,513.90
Amt Left:
83.24%
$741,233.53
Delta:
-5.13%
-$79,675.00
$1,681,309.85
Over/Under Est:
51.04%
$568,134.00
Amt Left:
88.81%
$790,853.63
Delta:
-3.04%
-$49,620.10
$1,756,655.13
Over/Under Est:
57.81%
$643,479.28
Amt Left:
97.28%
$866,198.91
Delta:
-4.48%
-$75,345.28
$2,041,497.43
Over/Under Est:
83.39%
$928,321.58
Amt Left:
129.26%
$1,151,041.21
Delta:
-16.22%
-$284,842.30
$2,422,295.25
Over/Under Est:
117.6%
$1,309,119.40
Amt Left:
172.03%
$1,531,839.03
Delta:
-18.65%
-$380,797.82
$2,749,119.14
Over/Under Est:
146.96%
$1,635,943.29
Amt Left:
208.73%
$1,858,662.92
Delta:
-13.49%
-$326,823.89
$3,182,203.30
Over/Under Est:
185.87%
$2,069,027.45
Amt Left:
257.37%
$2,291,747.08
Delta:
-15.75%
-$433,084.16
Bid Items & Bid Tabulations
11
Total
0 of 11