ANDERSON US0079 (6422-20-001)

Items: 10

County: ANDERSON
Length: N/A
Highway: US0079
District: TYLER
Control Number: 6422-20-001
DBE Goal: N/A
Project: MMC - 642220001
Guaranty: N/A
Time: 120 CALENDAR DAYS
Engineer's Estimate: $1,564,350.00
Date: 10/06/2022 (3 years ago)
Contract Number: N/A
Type: HOT MIX
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (2)
E
Engineer's Estimate
$1,564,350.00
$1,451,700.00
Over/Under Est: -7.2% -$112,650.00
Over/Under Est: -0.31% -$4,850.00
Amt Left: 7.43% $107,800.00

Bid Items & Bid Tabulations

10 Total 0 of 10
ANDERSON  |  US0079  |  TYLER  |  6422-20-001  |  10/06/2022  |  $1,564,350.00  |  MMC - 642220001  |  HOT MIX  |  120 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
BIG CREEK CONSTRUCTION, LTD.
SP MIXTURES SP-C PG64-22 (PICKUP)
TON 1,000.000 $102.300 $95.000 $95.000
SP MIXTURES SP-C PG64-22 (DELIVERY)
TON 3,500.000 $114.300 $107.000 $115.000
SP MIXTURES SP-D PG64-22 (PICKUP)
TON 1,000.000 $104.100 $96.000 $95.000
SP MIXTURES SP-D PG64-22 (DELIVERY)
TON 7,000.000 $116.100 $108.000 $115.000
SP MIXTURES SP-C PG64-22 (DEL) (SITE 2)
TON 200.000 $120.000 $107.000 $135.000
SP MIXTURES SP-C PG64-22 (DEL) (SITE 3)
TON 200.000 $120.000 $110.000 $135.000
SP MIXTURES SP-C PG64-22 (DEL) (SITE 4)
TON 200.000 $120.000 $107.000 $135.000
SP MIXTURES SP-D PG64-22 (DEL) (SITE 2)
TON 200.000 $122.000 $108.000 $135.000
SP MIXTURES SP-D PG64-22 (DEL) (SITE 3)
TON 200.000 $122.000 $111.000 $135.000
SP MIXTURES SP-D PG64-22 (DEL) (SITE 4)
TON 200.000 $122.000 $108.000 $135.000
Totals: $1,564,350.000 $1,451,700.000 $1,559,500.000