Show Job Controls
Bid Cobra

ANDERSON US0287 (6412-19-001)

Items: 12

County: ANDERSON
Length: N/A
Highway: US0287
District: TYLER
Control Number: 6412-19-001
DBE Goal: N/A
Project: RMC - 641219001
Guaranty: N/A
Time: 70 W
Engineer's Estimate: $4,708,983.00
Date: 09/07/2022 (3 years ago)
Contract Number: N/A
Type: MILL AND INLAY
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$4,708,983.00
$4,990,502.50
Over/Under Est: 5.98% $281,519.50
Over/Under Est: 18.7% $880,521.30
Amt Left: 12% $599,001.80
Over/Under Est: 34.63% $1,630,562.02
Amt Left: 27.03% $1,349,042.52
Delta: -13.42% -$750,040.72

Bid Items & Bid Tabulations

12 Total 0 of 12
ANDERSON  |  US0287  |  TYLER  |  6412-19-001  |  09/07/2022  |  $4,708,983.00  |  RMC - 641219001  |  MILL AND INLAY  |  70 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
DREWERY CONSTRUCTION COMPANY, INCORPORATED
TEXAS MATERIALS GROUP, INC.
PLAN & TEXT ASPH CONC PAV(2" TO 4")
SY 2,259.000 $5.000 $3.500 $3.000 $5.750
PLANE ASPH CONC PAV (2")
SY 135,082.000 $2.000 $2.500 $3.000 $4.110
PLANE ASPH CONC PAV (3")
SY 32,980.000 $2.000 $3.000 $3.000 $5.750
MOBILIZATION
LS 1.000 $400,000.000 $450,000.000 $275,000.000 $630,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $20,000.000 $10,000.000 $45,000.000 $25,000.000
WK ZN PAV MRK SHT TERM RMV (W)(4")
LF 5,905.000 $1.500 $3.500 $1.000 $0.750
WK ZN PAV MRK SHT TERM RMV (Y)(4")
LF 16,805.000 $1.500 $3.500 $1.000 $0.750
MEMBRANE UNDERSEAL
GAL 42,581.000 $4.000 $6.000 $4.300 $3.750
SP MIXES SP-C SAC-A PG70-22
TON 16,059.000 $160.000 $160.000 $179.000 $188.000
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 5,831.000 $185.000 $190.000 $252.000 $265.500
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 376.000 $100.000 $125.000 $235.000 $50.000
TMA (STATIONARY)
DAY 38.000 $300.000 $175.000 $800.000 $3,000.000
Totals: $4,708,983.000 $4,990,502.500 $5,589,504.300 $6,339,545.020